Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 4 years ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
3 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
4 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
3 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
3 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
4 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
4 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
4 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
3 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
4 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
4 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
5 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
4 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
4 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
4 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
4 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
5 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
6 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
5 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
5 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
5 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
5 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
6 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
5 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
6 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
6 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
6 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
6 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
6 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
6 days ago

Contractor services