Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 3 years ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

Fall in office and housing activity dents industry output

Confidence fragile after 0.2% dip in output for second month
1 day ago

Cat deal sees Flannery plant investment top £100m this year

Leading plant hirer continues to invest in fleet
1 day ago

Lendlease OK’d to start Birmingham’s £1.9bn Smithfield scheme

First phase of 400 build to rent homes at Manor Square approved
1 day ago

Fresh plan for £170m Newcastle resi tower and hotel

Gainford Group scales down New Bridge Street scheme to 29 storeys
1 day ago

Berkeley warns over-regulation a drag on planning reform gains

House builder joins calls for urgent Gateway 2 building safety regulator reform
1 day ago

Mace confirmed for £140m Gatwick Airport Pier 6 extension

Contractor PJ Hegarty has started enabling works in middle of busy airport
2 days ago

Cost of M3 upgrade soars by £70m

Budget for VolkerFitzpatrick/Balfour Beatty road job jumps to £280m
1 day ago

Graham takes on ISG £45m Coventry cultural hub job

Firm will start conversion work in the Spring on former IKEA store
2 days ago

Alun Griffiths to “restructure and resize” after £95m loss

Redundancies due to be announced at Welsh civils contractor
3 days ago

Fire safety project approval delays hit Van Elle profits

Piling specialist also reviews future of Canadian operation amid fresh economic uncertainty
2 days ago

JRL Malaysian backers plan £150m London city office refurb

Ardmore set to deliver landmark 25 Finsbury Circus building overhaul
2 days ago

500-home block to replace 19 storey Sutton office tower

Landmark project to deliver 312 Build to rent and 195 co-living homes
2 days ago

Building envelope specialist Bailey buys Comar

Specialist now offers complete building envelope solutions
2 days ago

Subcontractors wanted for work across Wales

Big name buyers at latest Constructionline event: Register now
2 days ago

Balfour Beatty profit dented by £83m building safety hit

Increased order book at £18bn secures growth over next two years
3 days ago

Expanding utilities specialist Ipsum buys Matrix Power

Power engineering contractor takeover will strengthen offer in North East
3 days ago

Historic scaffolding firm files administration notice

Hertfordshire based Rodells has been trading since 1898
3 days ago

Planning Bill to have “seismic” impact on construction

Building-boosting reforms go before Parliament
4 days ago

Briggs & Forrester hits record revenue and orders

M&E specialist rebounds with strong growth across three divisions
3 days ago

Man Utd confirm plan for £2bn ‘super-tent’ stadium

Club to press ahead with 100,000-seat 'Wembley of the North'
4 days ago

Government spending keeps profits edging-up at Kier

91% of work now with public sector and regulated companies
4 days ago

Costain on track for step change to 5% margin

Alex Vaughan says order book has jumped £1.5bn to £5.4bn
4 days ago

Mace tops February contracts league

Confirmation of £300m London Victoria Street project lifts firm to pole position
4 days ago

Wates raids Laing O’Rourke for new construction operations chief

George Mosey leaves Laing O'Rourke after 16 years
5 days ago

Travis Perkins CEO Pete Redfern steps down due to ill health

Redfern joined builders' merchant last year after 14 years at Taylor Wimpey
5 days ago

Morgan Sindall wins £61m Liverpool lab scheme

Construction to start this Autumn on latest Knowledge Quarter project
4 days ago

Glencar to build timber-framed office block

Work to start next month on 79,200 sq ft scheme in Maidenhead
5 days ago

Shed specialist Marbank files administration notice

£67m turnover portal-framed building specialist files court notice
5 days ago

Birmingham council submits £1bn Druids Heath plan

High rise estate to be replaced by-3,500 home eco village
5 days ago

Cannabis farm gang posed as utilities contractor

Gang jailed for 28 years after diverting power to more than 100 cannabis farms
1 week ago

Contractor services