Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 1 year ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

Moving in to new markets paying off for McLaren

Contractor carving out new niche as leading player in heavy refurbs
2 days ago

Plan to add retentions record to payment reporting law

Government consults on tougher reporting to include disputed invoices and retention policies
3 days ago

Morgan Sindall wins £88m Beckton DLR depot upgrade

Delayed work to start on Docklands Light Railway train maintenance depot in East London
3 days ago

Hare and Severfield win £250m Sellafield deal

Country's two biggest steelwork contractors secure 17-year framework
3 days ago

Max Steward returns to head up ISG’s Agility fit-out arm

Former ISG project director returns after three years to take up MD role
3 days ago

McLaren wins massive Portland House refurb

Construction to start this year on £380m revamp of 28-storey building in central London
3 days ago

Green light for £275m HS2 Midlands nerve centre

Trio of contractors battling it out to win huge new depot near Birmingham
3 days ago

Winners named for Government £10bn offsite framework

29 firms secure places on mega framework for schools, healthcare, defence and justice jobs
4 days ago

ISG, Amey and Costain now industry’s quickest payers – list

Average payment times from main contractors slip by a day
5 days ago

Staff at Outco Surfacing start looking for new jobs

Administration notice filed two years after acquisition of NMC Group
4 days ago

£4.75m building work provision tips Higgins into the red

Partnerships business counts cost of changes to building safety rules
4 days ago

John F Hunt snaps up London temporary works design firm

Demolition contractor buys geotechnical and structural engineering design specialist RKD Consultant
4 days ago

Vital Energi lands £13m package at Plumstead regen site

Specialist will start on site this summer helping to transform the former home of Arsenal FC
4 days ago

Galliford Try to start £14m Scunthorpe Market scheme

Firm will build NHS staff accommodation and offices in two phases
4 days ago

Vast £500m British Library expansion go-ahead

London Mayor still needs to give final nod to 800,000 sq ft extension at St Pancras site in London
5 days ago

Wates names new chief executive

Cork-born Eoghan O’Lionaird to join later this month
5 days ago

Keltbray director joins Barhale as North East chief

Mark Wood heads operations in Yorkshire and North East England
5 days ago

Major London City building green deep retrofit approved

St Bride’s Tavern near Fleet Street will be demolished for the building expansion
5 days ago

Gilbert Ash lands starring role in £38m Welsh theatre revamp

Contractor to start work this year on Theatr Clwyd upgrade
5 days ago

Property clients to ramp up spending on decarbonising

Survey reveals nearly half of property chiefs plan to speed up spending on net-zero programmes over next twelve months
5 days ago

Average self employed labour rates top £1,000 a week

Average weekly earnings reach high for skilled trades
6 days ago

BAM wins £49m Harrogate Convention Centre revamp

Local council hopes to sanction work start this autumn
6 days ago

Renaker to top-out Manchester with 71-storey skyscraper

Developer lifts the lid on planned five-building cluster for phase 3 of Great Jackson Street development
6 days ago

Costain bridge lift delayed by ground conditions

National Highways chiefs postpone planned lifting operation
6 days ago

Nexus sells utilities and EV contracting arms for £78m

Group to now focus on remaining business at south east housing civils contractor Tamdown
6 days ago

Speller Metcalfe lands lead role on £40m Tamworth revamp

Town centre to be transformed under ambitious plans
6 days ago

Scaffold boss banned over covid loan abuse

Eleven-year director ban after misuse of £50,000 loan
6 days ago

Gove issues six weeks ultimatum to sign building safety contract

Developers told to sign Government contract issued today or be banned from building homes
7 days ago

Firm fined £120,000 for lifting two builders in a telehandler bucket

Rochdale builder Hoyle Developments fined after repeated safety breaches
1 week ago

Hunt quashes reports HS2 will stop at Old Oak Common

Chancellor says no "conceivable circumstance" where HS2 would not terminate in Central London
1 week ago

Contractor services