Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 2 years ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
12 hours ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
16 hours ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
1 day ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
16 hours ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
14 hours ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
15 hours ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
1 day ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
15 hours ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
2 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
2 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
2 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
2 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
2 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
2 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
3 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
3 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
3 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
3 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
3 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
3 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
3 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
3 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
3 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
4 days ago

Wates-owned SES restructure delivers record profit and revenue

Building services contractor revenue soars to almost £300m
4 days ago

25 groundworks firms win £100m Places for People deal

M&J Evans, Carmac and Churngold Construction feature in housing association's line-up
4 days ago

Energy efficiency firms angry at lack of CITB support

SME contractors funding bid "does not meet the current criteria for supporting productivity or EDI"
4 days ago

£400m South Cambridge science park approved

Outline approval allows former sewage treatment works to be demolished
4 days ago

McLaren gets green light for 45-storey Leeds tower

Landmark Wellington Square scheme will see 464 flats built with 360,000 sq ft of offices
7 days ago

Heavy rain causes 1.9% construction output fall

Hopes remain undampened of a resi-led recovery this summer
7 days ago

Contractor services