Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 3 months ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

Gove threatens ban on cladding suppliers failing to pay for retrofits

Cladding and insulation suppliers now in firing line for cash for £9bn post-Grenfell remediation bill
5 hours ago

Green light for Birmingham Paradise landmark hotel

17-storey hotel will be the 'cornerstone' of Phase 2
3 days ago

Structural steel price jumps another £50 a tonne

British Steel blames New Year's price hike on continuing high product costs
3 days ago

Enabling works start at £400m Manchester First Street

Downing to start main construction in March of three resi buildings rising up to 45 storeys
3 days ago

Former BAM Nuttall chief to join Murphy

Adrian Savory to start new role as director of Major Projects division next month
3 days ago

Bouygues set for London Tustin Estate 700-home rebuild

Phased building programme to start towards the end of the year
3 days ago

Safety horror show on housing site leads to director ban

Court hears contractor ignored multiple prohibition and improvement notices
3 days ago

JV North calls up local firms for £250m new home works

Framework for home building projects worth up to £2m
3 days ago

Kier more than halves debts to below £200m

Kier chief reports steady progress in first six months of trading
4 days ago

Barhale boosts funds as it looks to rebuild turnover

Contractor confident as water companies ramp-up spending plans
4 days ago

HS2 labour agency looks to float on AIM

£23m turnover labour supply business looks to raise funds for expansion
4 days ago

Kane scores £29m M&E deal with Willmott Dixon

Off site works to play crucial role in major London estate contract
4 days ago

Graham secures third Audley retirement village

Work starts on Audley Villages site at Scarcroft, West Yorkshire.
4 days ago

Keltbray wins first deal for former nmcn infrastructure arm

Hull waste processing contract for rescued division
5 days ago

50 firms win £750m decarbonisation framework

Fusion21 framework to target 'whole building' works on homes and schools
5 days ago

Balfour Beatty UK construction MD to step down

Tom Edgcumbe to depart after just over a year as MD construction services in England and Wales
5 days ago

Crest Nicholson trebles cladding retrofit provisions to £43m

House builder revises building safety retrofit costs in face of new Government guidance
5 days ago

BAM bags £110m refurb of iconic Covent Garden tower

Landmark Seifert-designed 15-storey Space House to get two extra floors
5 days ago

Winvic to start UK’s largest speculative shed

Ellesmere Port warehouse understood to be worth around £80m
5 days ago

Kier signs deal for £169m Luton hospital revamp

Main construction work to start this month and last until 2024
5 days ago

Willmott Dixon nabs £30m Kirklees police HQ

Work to start within next few weeks on regional police HQ
5 days ago

Kier reported to be in talks to buy Tilbury Douglas

Talks reported to be at an advanced stage between both boards
6 days ago

Finance sealed for next-generation London office job

Goldman Sachs takes stake in London Bridge office project
6 days ago

John F Hunt starts giant clean-up on £110m Walsall site

Land remediation work at contaminated site will take two years
6 days ago

Build to rent boom lifts Watkin Jones profit to £52m

Surging build to rent market lifts development pipeline to £1.8 billion
6 days ago

HS2 awards £310m station lifts and escalators deal

TK Elevator signs 160 lifts and 130 escalators deal for four stations
6 days ago

Robot cutter set to revolutionise paving jobs for Eurovia

Automated system will spell end for noisy slab cutting on busy sites
6 days ago

First mass built carbon negative homes get underway

St Modwen first volume developer to build affordable carbon-negative homes
7 days ago

GMI Construction names new CEO

Lee Powell takes helm as CEO at GMI Construction in growth push
7 days ago

514-home London scheme clears final hurdle

Inland Homes declares victory after three-year planning battle over Hillingdon Master Brewer site
7 days ago

Contractor services