HS2 hails big carbon saving on UK’s longest rail bridge

Aaron Morby 2 years ago
Share

Design and construction teams on the HS2 Colne Valley Viaduct project are on track to slash embedded carbon by 28%.

Narrowing the width of the viaduct has delivered a significant reduction in carbon across the 3.4km viaduct structure, set to be the UK’s longest railway bridge.

Reductions in concrete and steel on the project helped to slash embedded carbon by 63,300 tonnes CO2e – the equivalent of 234,500 flights from London to Edinburgh.

Main works contractor Align JV – a team made up of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick – worked for four years on the design with architects Grimshaw and design partners Jacobs and Ingerop-Rendel.

Starting from the reference design produced as part of the HS2 parliamentary process, they refined the design, challenged assumptions, and found efficiencies to help reduce the amount of steel and concrete in the structure.

This included working closely with rail systems experts at HS2 to allow the structure to be narrowed by over 1m, while still allowing sufficient space for signalling and control equipment alongside the line.

Inside the viaduct, the engineers opted for a ‘post-tension’ design, with lightweight super-strong steel cables running the full length of structure.

They also worked to bring the northbound and southbound tracks closer together further north, which in turn significantly reduced the amount of earthworks required for the approach embankment.

Piling is well advanced along the viaduct route

Noise barriers will be changed from the original solid concrete to a composite design with noise absorbing steel cassettes at the bottom and transparent acrylic at the top, helping to reduce the amount of concrete.

An extensive programme of test piling resulted in a 10-15% reduction in the depth of the piles and associated time, cost and carbon savings.

Billy Ahluwalia, HS2 Ltd Senior Project Manager, said: By providing a cleaner, greener way to travel, HS2 will help cut the number of cars and lorries on our roads, cut demand for domestic flights, and help the fight against climate change.

“But we’re also serious about reducing the amount of carbon we use during construction, and the Colne Valley Viaduct is a great example of how we’re using the latest engineering techniques to do just that.

“Concrete is one of our industries’ biggest sources of embedded carbon – and this design will help us cut our carbon footprint while delivering a lighter, stronger and more elegant structure.”

The main deck of the viaduct will be built in sections at a temporary factory nearby before being assembled from north to south starting next year.

 

Latest news

Geoffrey Osborne files administration notice

£325m turnover contractor employs 800 staff
43 mins ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
19 hours ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
23 hours ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
2 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
24 hours ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
22 hours ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
22 hours ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
2 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
23 hours ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
2 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
2 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
2 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
2 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
3 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
3 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
3 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
3 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
3 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
3 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
4 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
3 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
4 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
4 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
3 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
4 days ago

Wates-owned SES restructure delivers record profit and revenue

Building services contractor revenue soars to almost £300m
4 days ago

25 groundworks firms win £100m Places for People deal

M&J Evans, Carmac and Churngold Construction feature in housing association's line-up
4 days ago

Energy efficiency firms angry at lack of CITB support

SME contractors funding bid "does not meet the current criteria for supporting productivity or EDI"
4 days ago

£400m South Cambridge science park approved

Outline approval allows former sewage treatment works to be demolished
4 days ago

McLaren gets green light for 45-storey Leeds tower

Landmark Wellington Square scheme will see 464 flats built with 360,000 sq ft of offices
7 days ago

Contractor services