Expanded starts work on giant HS2 station box

Grant Prior 1 year ago
Share

Expanded has started work to construct the 850m-long station box at HS2’s Old Oak Common site.

Expanded has been appointed by Balfour Beatty, Vinci Systra joint venture (BBVS) to deliver the reinforced concrete structure that will form the frame and base for the HS2 station building.

Construction will see Laing O’Rourke company Expanded excavate 20m below ground level removing 690,000 cubic metres of clay, before placing 32,000 tonnes of steel and pouring 190,000 cubic tonnes of reinforced concrete.

The “top down” excavation will allowsthe ground floor slab to be constructed initially with a series of mole holes allowing access for the large excavators to remove the earth from within.

The box at the east of the site allows the Tunnel boring machines (TBM) to be launched towards Euston. The west of the site is where the spray concrete lined tunnel between Old Oak Common and the Victoria Road Crossover box finishes.

Work to build the station will provide 2,300 jobs (with Expanded providing 500 of those, including 10 apprentices) and act as a catalyst for the UK’s largest regeneration project in the Old Oak and Park Royal area.

HS2’s Deputy Project Client for Old Oak Common Station, Rob Avery, said: “The start of work on the gigantic station box structure is a key milestone for the team at Old Oak Common. Work is progressing well on site and we are pleased that Expanded have now joined us on site as the programme continues to move forward.”

Expanded Business Unit Leader Peter Lyons said: “The award of this contract builds on our extensive experience in the rail sector, especially in London and will see us work on another HS2 project where we have previously delivered bridges utilising our modular bridges capabilities.

“We are proud to be joining forces with the BBVS joint venture in delivering the main station box. We began pre-construction works in May and the team are pleased to have now started this mammoth task.”

Designs for the station show that the six high-speed platforms will be situated underground with an integrated connection to the adjoining conventional station by a split-level public concourse and dramatic conventional rail overbridge to provide seamless interchange.

These are unified by a vaulted roof inspired by the site’s industrial heritage.

BBVS Project Director Nigel Russell said: “We are pleased to be working with Expanded on the delivery of the station box, which represents an integral part of Old Oak Common Station.

“The reinforced concrete box will form the frame and base for the new state of the art HS2 station building as well as the six underground high-speed platforms.”

Old Oak Common will provide high-speed rail services to the Midlands, Scotland and the North and trains to central London and Heathrow and Wales and the West of England.

Latest news

John Lewis £500m funding deal to build 1,000 rental homes

Deal to advance BTR flats at store sites in Bromley, West Ealing and Reading
11 hours ago

Eric Wright wins tricky £52m Liverpool transformation

Contractor working with engineers at Ridge and Partners on "challenging" Stanley Lock Flight site
3 days ago

Investment giant buys Bristol M&E contractor

RDCP Infrastructure acquires Avon Combined Electrical Services
3 days ago

Demolition start for £50m Farnworth town centre rebuild

Caddick Construction is tipped for main works due to start in the spring
3 days ago

L&G Modular strikes deal to build 1,000 affordable homes

Modular homes business teams up with Hampshire's Vivid housing association
3 days ago

Former Erith operations director joins John F Hunt

Scott Exell named new operations director at demolition specialist John F Hunt
3 days ago

Green light for £135m Leeds twin tower resi scheme

Construction to start in New Year on 500 build-to-rent apartments
4 days ago

Mace hits 1m tonnes carbon saving target for clients

Present work pipeline betters 2026 carbon emission saving target
3 days ago

Plans in for £40m surf park at former Kent colliery

Seahive surf lagoon and health resort will be built near Deal
4 days ago

Crushed demolition worker vows to return to industry

Shannon Brasier hoping to return to construction following horror accident
4 days ago

Mount Anvil to start 900-home North London estate rebuild

Planning approval paves way for Barnsbury Estate rebuild in Islington
4 days ago

Green light for major laboratory campus in Cambridge

Developer BioMed to tender first building on 600,000 sq ft lab complex in the New Year
4 days ago

Belfast firm signs the biggest work deal yet under Project Gigabit

Fibrus to hook-up rural Cumbria to lightning-fast broadband under £108m deal
4 days ago

McLaren wins Leeds logistics park contract

Work to start imminently on warehouse complex for Firethorn Trust
5 days ago

Work restarts on £683m waste power plant after site death

Construction suspended for a week of investigations following fatality
5 days ago

Demolition starts on £135m Wigan Galleries scheme

Contractor BCEGI starts work on project to redevelop Wigan town centre
5 days ago

Amey CEO to step down following private equity buyout

Amanda Fisher to leave once business is transferred to new owners
5 days ago

New body set up to vet plant operator card schemes

Contractor trades bodies unite to tackle competency concerns over plant operator skills cards
5 days ago

Kier leads switch to hybrid battery generators

Battery units work alongside smaller generators cutting run times by nearly 60%
5 days ago

Plans in for first Leeds co-living scheme

Watkin Jones submits plan to convert old Direct Line HQ into 230 studio flats
5 days ago

Demolition worker crushed by excavator

Court hears 20-year-old woman was left with "life changing injuries"
6 days ago

Government pays £700m for 50% stake in Sizewell C

New body, Great British Nuclear, will be set up to develop pipeline of nuclear projects
6 days ago

Costain wins Heathrow Airport asset renewal deal

Firm takes early contractor involvement role in Terminal 2 baggage handling upgrade
6 days ago

Worker killed on £683m waste power plant site

Fatal collision involving heavy goods vehicle on giant north London site
6 days ago

HS2 JV shifts four Wembley Stadiums of earth in record time

EKFB team digs and hauls 15 million cu m of muck in 20 months
6 days ago

Milestone wins £300m Wiltshire highways upkeep

Ringway will hand over to Milestone in March next year
6 days ago

Low-risk business model helps Renew post record results

Renew reveals latest acquisition with £15.6m purchase of water specialist Enisca
6 days ago

London Albert Embankment hotel towers approved

Two separate hotels rising to 26 and 29 storeys approved
6 days ago

Keltbray names new director of strategic engineering

Tim Lohmann takes up newly-formed role to drive innovative engineering solutions
6 days ago

Go-ahead for £200m lithium refinery on Teesside

Work to start next year on Europe's first lithium hydroxide processing plant
7 days ago

Contractor services