Birmingham City Council has cut hundreds of KPIs during a restructuring of its troubled £2.7bn highways PFI contract.

The tender process for a new contractor for the revamped 12-year deal will start in February.

Birmingham originally signed a 25-year, £2.7bn highways management and maintenance contract back in 2010 with Amey.

But the contractor became embroiled in a lengthy performance dispute with the council which ended in March 2020 with Amey paying £215m to terminate its involvement in the PFI deal.

Kier stepped in as interim contractor while the council and Birmingham Highways Limited – the special purpose vehicle owned by Equitix and PIP Infrastructure Investments – have been working to restructure the contract.

The new contract will cover the remaining 12 years of the initial agreement, from April 2023 to June 2035.

It will be a bespoke deal similar in length to a standard long-term maintenance contract, with operational terms and a performance regime that enables it to be “brought up to date to better reflect current industry standards which have changed over the past decade.”

Birmingham said: “The new contract has been structured to provide better governance of the project and more balanced risk between the Council, the SPV and the future contractor.

“A key element of this is a reduction in key performance indicators from over 600 to around 28 as well as prioritisation of deliverables, addressing both areas which routinely plagued the previous contractor Amey during its tenure as subcontractor.”

Prospective bidders will go through a competitive and transparent tendering process which is due to begin in February 2022, following the supplier day in January.

The process will be conducted over a period of nine months and be structured to provide bidders with sufficient time to undertake due diligence.

During the interim period, an updated Management Information System (MIS) was implemented to collect data from across the road network to provide a greater understanding of current conditions and areas for improvement.

Bidders will be provided with access to this information via a data room, which includes a database of assets and will allow bids to be informed by bidders’ due diligence and analysis.

The data room will include new information about the current status of the road network from improved data collection and analysis, including full network surveys of carriageway conditions that have been undertaken by independent surveyors.

This information will be shared with bidders during the tendering process, providing them with the most detailed understanding of the status of the network to date and provide greater clarity over what can be delivered over the term period.

The contract covers capital works and maintenance of more than 2,500km of roadways and 5,000km of footways across the UK’s largest authority and second largest city, as well as 846 structures, three tunnels, 94,000 street lighting columns, 76,000 highway trees and the city’s traffic control system.

Kevin Hicks, Assistant Director for Highways and Infrastructure of Birmingham City Council, said: “Extensive work has been put in over the last two years by all of the project parties and with the close support of the DfT in order to establish a workable and deliverable contract framework.

“Many lessons have been learned from the first 10 years of the project and with the insight we have gained from the industry through previous engagement exercises believe that we have an attractive prospect for the market.”

Latest news

Alun Griffiths set to rescue firm he sold for £36m

Tarmac to hand back Welsh civils contractor after five years of losses
2 days ago

Landsec to pump £2bn into new house building drive

Developer to build 6,000 homes as it sells offices to fund new schemes
2 days ago

Severfield to start steel on McAlpine car battery site

Specialist to start on £4bn site next month after steel package signed-off
2 days ago

Construction Manager of the Year crowned

Jason Hunt of Willmott Dixon wins for work on Bristol concert hall
2 days ago

Tide gets go-ahead for over 1,000-home London scheme

Volumetric expert gains planning for co-living homes scheme in Southwark
3 days ago

Vital Energi lands £250m Gatwick decarbonisation deal

Five-year programme to switch airport away from gas heating
2 days ago

Construction output flickers into life in March

First quarter activity flatlines after slow start to year
3 days ago

Skanska lifts margin to 4.3% as profit hits £78m

Infrastructure and FM drive near-tripling of profits
4 days ago

Mayor backs 46-storey student tower at Canary Wharf

City Hall overturns Tower Hamlets council rejection of 912-bed scheme
4 days ago

Plans go in for 100 acre Port of Tilbury expansion

Construction could start next year on site the size of 70 football pitches
3 days ago

Inland Homes creditors face £38m hit

Administrator confirms no cash for supply chain
4 days ago

Durkan dogged by legacy jobs despite return to trading profit

Durkan scales down new homes contracting to focus on retrofit work
4 days ago

Munnelly founder hands over CEO role to son

Paul David Munnelly steps up to CEO as father becomes chairman
3 days ago

Barking build to rent towers face rebuild

Major remedial work needed on resi scheme built by Shapoorji Pallonji UK Ltd
4 days ago

London new home starts plunge 38% as Building Safety Act bites

Capital only region to see Q1 fall in NHBC new home registrations
5 days ago

Sureserve swoops for rival compliance outfit Kinovo in £56m deal

Recommended cash offer will take AIM listed contractor private
4 days ago

Crown Golf tees up £1bn plan to build 3,000 homes on course land

Major housing plan for spare land on eight UK courses
4 days ago

Green light for Peterborough Station Quarter £48m revamp

First phase to start before the end of the year
4 days ago

Morgan Sindall starts £38m Caerphilly leisure hub

New swimming pool and health suite forms part of town regeneration plan
4 days ago

145 firms win places on £800m building safety framework

Fusion21 confirms latest winners: Full list
5 days ago

Higgins Homes and site workers face manslaughter charges

Contractor and four site staff charged after woman killed by falling pallet of bricks
6 days ago

Operator spots cracked mast on Hinkley tower crane

Hinkley Point C contractor hit with safety notice over failed mast pin and cracks
5 days ago

Countdown starts for £1bn Birmingham highways bid race

Council will break-up mega framework into five lots
5 days ago

Acciona wins £400m Thames waterworks upgrade

Lea Valley Coppermills water treatment works to get full overhaul
5 days ago

Pension giants pledge £25bn for infrastructure push

Seventeen pension providers pledge to invest in projects
5 days ago

Safety row over London tower ducking fire regs by 30cm

Fire union calls on Mayor to block Bromley flats plan over single staircase
5 days ago

Midgard lands £145m deal to build Edition Birmingham

Construction to start shortly on twin residential towers
6 days ago

McAleer & Rushe set to break £500m turnover barrier

Pre-tax profit jumped 16% to £46m last year
6 days ago

Top design team picked for £2.5bn York Central scheme

Massive city centre regen scheme moves to detailed design
6 days ago

MoD to bid £100m command HQ enabling works

Hertfordshire joint forces command centre expansion advances
6 days ago

Contractor services