Crest Nicholson trebles cladding retrofit provisions to £43m

Aaron Morby 3 years ago
Share

House builder Crest Nicholson has upped its provision to £43m to cover post-Grenfell cladding and fire safety retrofits on its former building projects.

Lower rise buildings will now need to be retrofit under latest Government guidance
Lower rise buildings will now need to be retrofit under latest Government guidance

It is the first house builder to raise its estimates since the Government last week called on developers to stump up extra cash to fix the cladding crisis on intermediate height buildings of around four to seven storeys.

Crest this morning said it had now managed to assess the potential building safety work needed to all its properties of all heights and had made provisions for a further £29m on top of the £14m set aside a year ago.

The firm also blamed rising labour and material prices for the latest jump in expected recladding costs.

Crest revealed that so far it had clawed back £2.4m from settlements of claims against architects and subcontractors.

The Government has given firms have been given until early March to agree fully-funded plans of action including remediating unsafe cladding on mid-rise buildings of 11m-18m in height, currently estimated to cost around £4bn across the sector.

Peter Truscott, Chief Executive, said: “Following the Grenfell Tower tragedy, the group has actively worked to identify buildings where it has an obligation as legal owner, to remedy defects or meet the requirements of newly-published Government guidance.

“In addition, it has considered situations where it is no longer the owner of the building but there are design or workmanship defects because of the group, its subcontractors, product suppliers or designers falling short of their obligations at the time of construction.  In these instances, the group is taking action to ensure these issues are remedied as quickly as possible.”

He added: “As our review has progressed, we have started to receive more detailed reports on the remedies required, primarily from those schemes that have been more complex and time-consuming to investigate.

“Given the specialist nature of this work and the scarcity of qualified resource to conduct reviews, we have also seen inflation in our costs to complete for both labour and materials.”

Crest said it expects to have completed any required remedies within a five-year period, using £14m of the remaining provision within one year, and the balance within two to five years.

The jump in building safety work provisions was announced as Crest revealed the business had bounced back last year making a pre-tax profit of £87m compared to a loss of nearly £14m in 2020 from revenue up 16% to £787m.

Truscott added: “We were delighted to increase profit expectations twice in the year and we have started 2022 with a strong forward order book and everyone in Crest Nicholson is excited about our plans for expansion. 

 

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
2 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
3 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
2 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
2 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
3 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
3 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
3 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
2 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
3 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
3 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
3 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
4 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
3 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
3 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
3 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
3 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
4 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
5 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
4 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
4 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
4 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
4 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
5 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
4 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
5 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
5 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
5 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
5 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
5 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
5 days ago

Contractor services