M1 fraud probe exposes contract management problems

Aaron Morby 4 months ago
Share

A National Highways fraud probe revealed by the Enquirer last year has found a string of concerning management issues on the M1 J13-16 smart motorway scheme.

The investigation by the agency’s in-house counter fraud squad has now concluded and found that National Highway has suffered financial loss.

But the national roads agency has decided not to pursue any criminal prosecution due to ‘insufficient conclusive evidence’, according to the final report seen by the Enquirer.

The investigation was launched into the Costain Galliford Try joint venture job after multiple accusations were leveled between 18 September 2020 and 2 February 2021, each alleging wrongdoing on the project.

These implied procurement fraud, theft of assets and collusion leading to false claims.

This scheme for a stretch between Milton Keynes and Northampton was awarded to the CGT JV with an agreed budget of £297m. This has ballooned to £453m.

Investigators for National Highways found £320,000 of central barrier scrap metal was ‘missing from the records and unaccounted for’ .

But after failing to secure any reliable witness testimony, the probe team said they were unable to prove the allegation of theft.

The investigation also failed to find hard evidence to support allegations of the use of ghost workers on the job, and bribes for subcontract work or business favours.

While labour supply on the project soared from £362,000 to around £9.5m, an investigation by the CGT JV uncovered no evidence to support whistleblowers claims, says the report.

In response to allegations of “brown envelopes” being passed around, National Highways investigators said that, although there was evidence cash-filled envelopes changed hands, it accepted the explanation that the money was requested from subcontractors to contribute to project staff parties.

Investigators also looked at a large package contract, which jumped from an original order value of £28m to a forecast end cost of £68m.

This was due for the most part to 1,389 compensation events, which were accepted as resulting from a number of complex underlying reasons.

National Highways’ commercial assurance partners have worked with the internal project team to understand the causes for the overspends and to challenge the escalating costs where appropriate.

In the final report, investigators did raise several concerns that ‘presented an increased risk of fraud and further possible accusations of bribery or corruption’ if not addressed.

These included poor contract management, in relation to escalating costs and proper implementation of the compensation events process.

They also highlighted a lack of record-keeping supporting key decisions during a live procurement and to validate ongoing subcontractor costs throughout the life-cycle of the project.

The team also red-flagged lack of governance around single-source procurement decisions.

A CGT JV spokesperson said: “The CGT JV responded comprehensively to all the issues brought to light with a detailed and thorough investigation, with appropriate action taken and further strengthening of its compliance procedures.

“Both companies in the JV have strong policies and procedures in place, fully promote a culture of transparency and encourage potential whistle-blowers to come forward.

“Both the CGT JV and National Highways investigations confirmed that there is no connection between any of the allegations and increased costs of the M1 junction 13-16 project.

“Any inference that the two are connected in any way or that the alleged activities that were under investigation have incurred a cost to the taxpayer is incorrect. Project scopes can evolve as was the case here, and those changes have the support of all parties involved.”

National Highways smart motorways programme director David Bray said: “We take any suggestion of criminal behaviour on our projects extremely seriously and investigate every allegation thoroughly. 

“We investigated, working collaboratively with our contractors, the allegations around the M1 and M6 schemes and prevented the payment of any amounts that we were not fully satisfied with.” 

Latest news

Hunt starts for £250m Stockport 8 site developer

Town centre 8-acre site is earmarked for 1,200 homes, shops and leisute
3 hours ago

Water industry revives PFI model for £1bn job

Vast Haweswater Aqueduct upgrade to pilot new DPC model, hailed as the future for water companies
8 hours ago

VolkerRail fined £550,000 after trench collapse

Court hears how two metre deep excavation was unsupported
10 hours ago

Plans in for £500m Hollow Mountain pumped hydro scheme

Work removing 2m tonnes of rock could start within two years
7 hours ago

‘Ratty the Robot’ takes bite out of costly pipe inspections

Pipe-crawling tetherless robo-rat makes light work of complex underground inspections
8 hours ago

Graham gets green light for £124m M25 Junction 28

Consent allows work to start this Autumn on Essex junction upgrade
23 hours ago

Six win £600m panelised housing DPS deal

Better Building alliance of 29 housing associations signs up manufacturers
10 hours ago

Watkin Jones reports record £2bn pipeline

Student rooms and BTR builder plans corporate name change in big rebrand
9 hours ago

Race starts for £500m Scottish zero carbon hospital job

Bidding starts for new University Hospital Monklands near Airdrie
1 day ago

Manchester airport taxis out £60m terminal 2 pier job

Bidding to start before the end of 2022 for project start early next summer
1 day ago

Plan for 1,100-home complex at Leicester factory site

Galliford Try investments plots Corah Factory transformation
1 day ago

Axed House by Urban Splash staff plan legal action

Ex-workers consult with lawyers following administration
1 day ago

Summer slowdown fears as latest contract award data droops

Latest Barbour ABI Snap Analysis paints uncertain picture
1 day ago

Farrans wins £39m Somerset recycling hub

Site preparation gets underway for Keynsham Recycling Hub
1 day ago

Balfour gets green light for £250m M25 junction 10

Autumn start for M25 junction 10/A3 Wisley interchange improvement scheme
4 days ago

Leeds plumbing contractor sinks with loss of 30 jobs

Dickinsons Plumbing and Heating goes down but renewables arm salvaged in sale
4 days ago

HS2 achieves first diesel-free construction site

Skanska Costain STRABAG JV runs Kilburn site with green kit
4 days ago

Administration confirmed at House by Urban Splash

160 jobs lost following "operational issues" at modular factory
5 days ago

Network Rail fined £1.4m after worker crushed by track machines

Judge highlights "many layers of failure" within site management
5 days ago

Kier picked for £350m Leatherhead regen plan

Property arm to draw up plans to redevelop two large town centre sites
5 days ago

Two seriously injured in London steelwork collapse

Two steel erectors left fighting for their lives after collapse at Ardmore site
6 days ago

Urban Splash modular staff start looking for new jobs

Work stops at House by Urban Splash factory and housing sites
6 days ago

Building facade specialist CMS goes into administration

Building envelope firm had turnover of £43m
6 days ago

Office work uplift returns construction output to growth

New commercial work drives output uplift for the first time since the pandemic
5 days ago

More suppliers wanted on £683m waste power plant

Meet the buyer event for North London Heat and Power Project: Register now
6 days ago

Vistry Partnerships lands £128m London flats deal

Legal & General signs up firm for 480-flats over five buildings in Wandsworth
6 days ago

HS2 Project Bank Accounts “not worth paper they are written on”

Subcontractors furious after payment protection promises evaporate in wake of Roadbridge collapse
6 days ago

Taylor Wimpey to tear down half-built £48m Hackney Wick scheme

Concrete frame to be demolished after discovery of "potential structural issue"
6 days ago

Data centre work lifts TClarke orders to record high

Orders hit £585m, more than £100m on last year
6 days ago

BAM lands largest ever fit-out job

Firm to fit-out landmark 12-storey Edinburgh St James Quarter 'ribbon' hotel
1 week ago

Contractor services