M1 fraud probe exposes contract management problems

Aaron Morby 2 years ago
Share

A National Highways fraud probe revealed by the Enquirer last year has found a string of concerning management issues on the M1 J13-16 smart motorway scheme.

The investigation by the agency’s in-house counter fraud squad has now concluded and found that National Highway has suffered financial loss.

But the national roads agency has decided not to pursue any criminal prosecution due to ‘insufficient conclusive evidence’, according to the final report seen by the Enquirer.

The investigation was launched into the Costain Galliford Try joint venture job after multiple accusations were leveled between 18 September 2020 and 2 February 2021, each alleging wrongdoing on the project.

These implied procurement fraud, theft of assets and collusion leading to false claims.

This scheme for a stretch between Milton Keynes and Northampton was awarded to the CGT JV with an agreed budget of £297m. This has ballooned to £453m.

Investigators for National Highways found £320,000 of central barrier scrap metal was ‘missing from the records and unaccounted for’ .

But after failing to secure any reliable witness testimony, the probe team said they were unable to prove the allegation of theft.

The investigation also failed to find hard evidence to support allegations of the use of ghost workers on the job, and bribes for subcontract work or business favours.

While labour supply on the project soared from £362,000 to around £9.5m, an investigation by the CGT JV uncovered no evidence to support whistleblowers claims, says the report.

In response to allegations of “brown envelopes” being passed around, National Highways investigators said that, although there was evidence cash-filled envelopes changed hands, it accepted the explanation that the money was requested from subcontractors to contribute to project staff parties.

Investigators also looked at a large package contract, which jumped from an original order value of £28m to a forecast end cost of £68m.

This was due for the most part to 1,389 compensation events, which were accepted as resulting from a number of complex underlying reasons.

National Highways’ commercial assurance partners have worked with the internal project team to understand the causes for the overspends and to challenge the escalating costs where appropriate.

In the final report, investigators did raise several concerns that ‘presented an increased risk of fraud and further possible accusations of bribery or corruption’ if not addressed.

These included poor contract management, in relation to escalating costs and proper implementation of the compensation events process.

They also highlighted a lack of record-keeping supporting key decisions during a live procurement and to validate ongoing subcontractor costs throughout the life-cycle of the project.

The team also red-flagged lack of governance around single-source procurement decisions.

A CGT JV spokesperson said: “The CGT JV responded comprehensively to all the issues brought to light with a detailed and thorough investigation, with appropriate action taken and further strengthening of its compliance procedures.

“Both companies in the JV have strong policies and procedures in place, fully promote a culture of transparency and encourage potential whistle-blowers to come forward.

“Both the CGT JV and National Highways investigations confirmed that there is no connection between any of the allegations and increased costs of the M1 junction 13-16 project.

“Any inference that the two are connected in any way or that the alleged activities that were under investigation have incurred a cost to the taxpayer is incorrect. Project scopes can evolve as was the case here, and those changes have the support of all parties involved.”

National Highways smart motorways programme director David Bray said: “We take any suggestion of criminal behaviour on our projects extremely seriously and investigate every allegation thoroughly. 

“We investigated, working collaboratively with our contractors, the allegations around the M1 and M6 schemes and prevented the payment of any amounts that we were not fully satisfied with.” 

Latest news

Plant bosses blast “inflexible” police over road bans

Officers spotted outside sites and depots monitoring movements of large kit
2 mins ago

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
6 hours ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
7 hours ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
23 hours ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
6 hours ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
1 day ago

Contractors face mental health quiz to win work

Prequalification specialist pushing for mental health questions in assessments
6 hours ago

Building boss banned for covid loan abuse

Latest investigation into £50,000 Bounce Back Loan
6 hours ago

Ready mix concrete giant files administration notice

Mixit Concrete Limited lodges court notice
1 day ago

Dual student towers plan for Birmingham Gun Quarter

Sama Investments goes to public consultation on 50-storey scheme
1 day ago

15 win £3.5bn Eastern Route Partnership railway deal

Amco, BAM, Morgan Sindall and Story among winners on Eastern Routes Partnership
1 day ago

Expanding Caddick Group tops £500m turnover

Construction drives revenue growth and returns to profit
1 day ago

Structure Tone returns to profit

Contractor confident about prospects in London fit out and refurb market
1 day ago

33 firms secure spots on £3.6bn Northumbrian Water framework

Applebridge, Galliford, Esh and Keltbray may
1 day ago

Construction boss in court over dodgy van deals

Suspended jail sentence after court hears how millions in unexplained payments went through Leeds contractor
1 day ago

Development firm fails hitting London building team for £2.6m

Luxury flats builder Ant Yapi was contracted to redevelop Westminster Tower site
2 days ago

Government set to fund £1bn final HS2 London tunnel drive

Final tunnel drive to be taxpayer funded upfront with cash recouped later
2 days ago

Amazon fires up Big-Box market with £500m job

Next generation triple floor super-shed to be built near Northampton
2 days ago

Stricken road sweeper specialist rescued

Parts of hire specialist Go Plant bought out of administration by Sweeptech
2 days ago

Costain highways lead joins Buro Happold

Paula Gough appointed to UK Development Director for Infrastructure
2 days ago

G&H Group lands £20m+ M&E package from JJ Rhatigan

100-strong specialist team to start on West London site next week
2 days ago

Bidding open for £800m professional services deal

Procure Partnerships encourages SMEs to bid with 9 regional lots
2 days ago

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
3 days ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
3 days ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
3 days ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
3 days ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
1 week ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
3 days ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
3 days ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
3 days ago

Contractor services