Work grinds to a halt on Midas sites

Grant Prior 3 years ago
Share

Work has ground to a halt on three Midas hotel jobs in Devon while subcontractors have walked off another site in Somerset following a payment row.

Midas celebrating the hotel contract signing back in 2020
Midas celebrating the hotel contract signing back in 2020

Midas has been building two hotels worth £30m in Torbay for the Fragrance Group .

And DevonLive said work had also stopped on an £11m Premier Inn for Torbay Council.

The Fragrance Group told the Enquirer: “Over the past three months the Fragrance Group has become increasingly concerned by the very limited progress on our two new Paignton seafront hotel developments, located on the neighbouring sites of the former Park Hotel and Lighthouse club.

“We are in constant discussions with the main contractors and are now reviewing our options to complete the development of these hotels.

“Our priority is to deliver these two new seafront hotels which mark a vital investment in the wider Torbay.”

The Somerset County Gazette reported that subcontractors had walked off the Coal Orchard development in Taunton following pay disputes.

A Torbay Council spokesperson said: “We are working with Midas to identify any issues which may be affecting the site and any required solutions.”

The Enquirer has also been contacted by subcontractors frustrated by late payments on Midas jobs.

One said: “A lot of firms on the job have been unhappy for a while about payments.”

A spokesman for Midas Construction said: “As is well known in the industry there are issues relating to Brexit, Covid, ongoing shortages of materials and labour, and significant cost inflation, which are providing challenges to project delivery and timescales.

“We are working closely with all our stakeholders to resolve the situation.”

Latest results filed for Midas Group saw the contractor post its first ever loss in more than 40 years of trading.

Turnover for the 18-month period to 30th October 2020 fell to £291.3m resulting in a pre-tax loss of £2.4m while the company employed 498 staff.

Latest news

Tide gets go-ahead for over 1,000-home London scheme

Volumetric expert gains planning for co-living homes scheme in Southwark
22 minutes ago

Construction output flickers into life in March

First quarter activity flatlines after slow start to year
3 hours ago

Skanska lifts margin to 4.3% as profit hits £78m

Infrastructure and FM drive near-tripling of profits
12 hours ago

Mayor backs 46-storey student tower at Canary Wharf

City Hall overturns Tower Hamlets council rejection of 912-bed scheme
11 hours ago

Plans go in for 100 acre Port of Tilbury expansion

Construction could start next year on site the size of 70 football pitches
2 hours ago

Inland Homes creditors face £38m hit

Administrator confirms no cash for supply chain
20 hours ago

Durkan dogged by legacy jobs despite return to trading profit

Durkan scales down new homes contracting to focus on retrofit work
17 hours ago

Munnelly founder hands over CEO role to son

Paul David Munnelly steps up to CEO as father becomes chairman
3 hours ago

Barking build to rent towers face rebuild

Major remedial work needed on resi scheme built by Shapoorji Pallonji UK Ltd
1 day ago

London new home starts plunge 38% as Building Safety Act bites

Capital only region to see Q1 fall in NHBC new home registrations
2 days ago

Sureserve swoops for rival compliance outfit Kinovo in £56m deal

Recommended cash offer will take AIM listed contractor private
1 day ago

Crown Golf tees up £1bn plan to build 3,000 homes on course land

Major housing plan for spare land on eight UK courses
1 day ago

Green light for Peterborough Station Quarter £48m revamp

First phase to start before the end of the year
1 day ago

Morgan Sindall starts £38m Caerphilly leisure hub

New swimming pool and health suite forms part of town regeneration plan
1 day ago

145 firms win places on £800m building safety framework

Fusion21 confirms latest winners: Full list
2 days ago

Higgins Homes and site workers face manslaughter charges

Contractor and four site staff charged after woman killed by falling pallet of bricks
3 days ago

Operator spots cracked mast on Hinkley tower crane

Hinkley Point C contractor hit with safety notice over failed mast pin and cracks
2 days ago

Countdown starts for £1bn Birmingham highways bid race

Council will break-up mega framework into five lots
2 days ago

Acciona wins £400m Thames waterworks upgrade

Lea Valley Coppermills water treatment works to get full overhaul
2 days ago

Pension giants pledge £25bn for infrastructure push

Seventeen pension providers pledge to invest in projects
2 days ago

Safety row over London tower ducking fire regs by 30cm

Fire union calls on Mayor to block Bromley flats plan over single staircase
2 days ago

Midgard lands £145m deal to build Edition Birmingham

Construction to start shortly on twin residential towers
3 days ago

McAleer & Rushe set to break £500m turnover barrier

Pre-tax profit jumped 16% to £46m last year
3 days ago

Top design team picked for £2.5bn York Central scheme

Massive city centre regen scheme moves to detailed design
3 days ago

MoD to bid £100m command HQ enabling works

Hertfordshire joint forces command centre expansion advances
3 days ago

Failed shed specialist Marbank owed suppliers £10m

Contractor was facing a string of adjudication claims
3 days ago

New scaffolding training trade body launches

Scaffolding Training Alliance formed amid disquiet caused by planned training changes
3 days ago

£1.8bn framework planned for green retrofit drive

Procure Plus to invite bids later this month
3 days ago

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5-mile TBM drive in 652 days
6 days ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
6 days ago

Contractor services