Roadbridge supply chain owed millions on HS2

Grant Prior 3 years ago
Share

Subcontractors and suppliers are holding outstanding invoices worth millions for work on HS2 following the failure of civils contractor Roadbridge.

The firm is now in the hands of receivers from Grant Thornton who are “seeking to maximise asset realisations for the benefit of the company’s creditors.”

Roadbridge UK was working on two HS2 sites where hundreds of its staff were sent home last week.

The firm’s contracts on the project are understood to have been worth up to £60m.

The largest deal was in a joint venture with Tarmac working for main contractor EKFB (Eiffage, Kier, Ferrovial Construction and BAM Nuttall).

Roadbridge was also working on a smalller contractor as a subcontractor to the Align JV of Bouygues, Sir Robert McAlpine, and VolkerFitzpatrick.

One site source said: “This all unraveled pretty quickly and has left a lot of suppliers owed money.

“HS2 is the biggest job in the country and no-one expects to be out of pocket working on such a high profile project.”

An HS2 Ltd spokesperson said: “Roadbridge UK was delivering a number of subcontracts for our main works contractors, both directly and as part of a joint venture with Tarmac.

“Contingency plans are in place and talks ongoing with Tarmac who remain responsible for delivering contracts signed by the joint venture. We are monitoring the situation.”

Grant Thornton is now in charge of Roadbridge UK and its parent company Roadbridge Limited (RBL) in Ireland.

The receiver said: “Following significant cashflow pressures, the group, its bankers and its advisors worked very hard to deliver a successful future for the business.  However, a buyer for the group has not been found and the Company and RBL were unable to continue to trade.

Rob Parker, Director at Grant Thornton UK LLP, added: “It is very disappointing that efforts to save the Company and other companies within the RBL group from insolvency were not successful and our efforts now turn to supporting the Company’s employees during this difficult time and seeking to maximise asset realisations for the benefit of the Company’s creditors.

“We are currently assessing whether it is possible to salvage some or all of the business and invite any interested parties to get in touch with the joint administrations, however operations have temporarily ceased, whilst we explore the options available”.

In the UK, the company employed approximately 215 staff and “the majority of employees have been temporarily sent home, pending further updates whilst a strategy for the administration is being reviewed.”

Latest news

Civils winners revealed for £12bn National Grid high voltage work

Contractor wins complete £59bn investment programme
9 hours ago

United Living quits new-build housing as costs mount

£136m-turnover housing arm to wind down as focus shifts to core infrastructure
12 hours ago

Fight looms for £3bn West Midlands building framework

Galliford Try, Morgan Sindall and others face fight to keep CWM seats
12 hours ago

Industry anger over sudden CITB funding changes

Smaller contractors lose funding route worth £10,000 a year
12 hours ago

Plans in to transform former GSK London HQ with 2,300 homes

Landmark 13-acre scheme set to transform Brentford Great West Road campus
11 hours ago

Watch Murphy near completion of major new rail bridge

Latest video reveals progress on Greek Street bridge during 21-day train suspension
12 hours ago

Mount Anvil’s in-house builder drives results in testing market

Group development pipeline holds steady at 3,384 homes despite dip in profit
13 hours ago

Costain margin heads for 4.5% after half-year profit rise

Roads and HS2 rephasing hit transport revenues but £5.6bn forward book to support growth
1 day ago

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
2 days ago

Farrans to build new £59m Paisley bridge

Work to start soon on transport project for Renfrewshire Council
2 days ago

Crown Estate hires Olympics village veteran to lead delivery push

John Nicholson to oversee £16bn portfolio’s major UK development pipeline.
1 day ago

Henry Boot gets green light for 2,500 new homes

Hallam Land division sees signs planning system is speeding-up
2 days ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
2 days ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
2 days ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
3 days ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
2 days ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
3 days ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
2 days ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
2 days ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
4 days ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
3 days ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
3 days ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
4 days ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
3 days ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
3 days ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
7 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
1 week ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
7 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
6 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
6 days ago