Everton ‘lock-in” construction costs with O’Rourke at new stadium

Grant Prior 3 months ago
Share

Everton FC has signed an agreement with Laing O’Rourke which will see the contractor deliver the final phase of the club’s new £500m stadium at Bramley-Moore Dock and “lock-in construction costs.”

Work continues on the waterfront site
Work continues on the waterfront site

The main construction contract will see O’Rourke complete construction of the new 52,888-capacity waterfront stadium “while also providing Everton with greater certainty as to the cost of the remaining stages of the project.”

The deal follows on from the Pre-Contract Services Agreement (PCSA) signed by both parties in February 2021 and the Enabling Works Contract (EWC), which was focused on delivering the preparatory works at the North Liverpool site, including the in-filling of the dock that was completed in December.

Under the new agreement, O’Rourke will deliver a programme of works which includes the completion of any outstanding enabling works, the full construction of the stadium and public realm, and remedial works to the Grade II listed Hydraulic Tower, which will be brought back into public use.

Everton Chief Executive, Denise Barrett-Baxendale, said: “This is an important agreement at a crucial time for the Club and the stadium project.

“Our agreement with Laing O’Rourke follows on from last year’s pre-contract services and enabling works agreements and brings clarity on the overall costs of our new stadium.

“We are now able to lock-in construction costs, while also benefiting from Laing O’ Rourke’s economies of scale in what is an ever-fluctuating marketplace.

“Our new agreement signifies that we have the utmost confidence in Laing O’Rourke, who are using the very best digital engineering expertise and industry-leading knowledge of modern construction methods to bring our stadium vision to life.”

Construction work on the stadium began in the summer of 2021, with significant progress made on site as non-listed structures have been demolished, heritage assets removed and preserved, the dock basin repaired and infilled, foundations laid and the concrete structure of four corners of Everton’s new home now starting to emerge from the ground.

Latest news

Osborne makes £45m construction loss

Sale of infrastructure business balances books as contractor looks for zero-carbon wins
8 hours ago

John F Hunt forecasts record revenue and profits this year

Demolition contractor back on strong financial footing after previously setting aside £5.6m for bid rigging probe
7 hours ago

Notting Hill Genesis names £2.8bn framework winners

26 firms land places on main contractor deal: Full list
8 hours ago

Green light for dual hotel scheme at Nine Elms

Two new hotel towers will share common basement
7 hours ago

Trials start on cement-free pre-cast piles

Aarsleff is hopeful a product will come to the market shortly
8 hours ago

Ex-Telford Homes boss to run green house builder

Jon Di-Stefano takes helm at M&G backed Greencore Construction
8 hours ago

Subcontractors told to stop work on Brymor sites

£80m revenue southern contractor files letter of intent to enter administration
1 day ago

House builder Chartway sold to private equity firm

Cabot Square Capital signs another major construction deal
1 day ago

Murphy Group appoints new chairman

Capita chairman and investment banker John Cresswell to start in November
1 day ago

Tolent seals £40m Newcastle ‘future-living’ housing job

135-home Vaux scheme will be first of four neighbourhoods totalling 1,000 homes
1 day ago

Cruden takes first job at £1.3bn Edinburgh Waterfront scheme

Preferred bidder named for first 750 net zero homes at new Granton Waterfront coastal town
1 day ago

Trio of student towers to be built at Brent Cross Town

Ground works under way with main contractor due to be appointed next month
1 day ago

Keltbray gets start date for £50m motorway upgrade

Contractor hails "significant step forward" for highways business
2 days ago

Site workers settle for 5% pay increase

Contractors and unions agree one-year deal following months of talks
3 days ago

Rising wages and skills gap to overshadow materials issues

Materials and product Inflation tops 20% so far this year, but labour set to be next big headache
2 days ago

Erith pays £2.8m bonus to staff after ownership switch

Around 450 staff have on average received over £6,000 since move to employee ownership five years ago
2 days ago

Algeco lands £19.2m Leeds modular school scheme

Offsite specialist will supply and install 192 steel frame modules
2 days ago

Eight firms placed on £750m Midlands and Eastern framework

Next generation framework for jobs up to £7.5m employs a parallel plotting structure
2 days ago

Aston Villa unveil plans for £100m stadium expansion

Construction set to start next year on first phase of Villa Park upgrade
2 days ago

Skanska bans ‘swing-up’ lorry loaders after site death

Banned vehicles are used mainly to deliver bulky items like cabins and welfare units
3 days ago

HS2 agrees £78m variation on Euston tunnels cost

Skanska Costain Strabag seals extra payment for agreed changes to the scope of work
3 days ago

B&K breaks ground at £150m Newcastle HMRC job

Work gets underway on city's largest ever office project
3 days ago

New building safety laws come into force today

Leaseholders protected and new regulator for construction product manufacturers in wake of Grenfell
3 days ago

Peel submits plan for £150m cannabis production plant

Isle of Man seeks to become a leader in the emerging medicinal cannabis sector.
3 days ago

Tarmac buys first electric concrete mixer truck

Country's first battery powered mixer truck will start site deliveries this Autumn
3 days ago

Tilbury Douglas wins Dorset hospital upgrade

Construction could start in 2024 after Dorset County Hospital secures £77.3m of funding
4 days ago

McGee in £2.4m provision for bid-rigging probe

Demolition contractor says provision will cover the expected fine over cover pricing ring
4 days ago

First designs for £275m HS2 Midlands nerve centre

Contractor due to be named in Autumn next year for Washwood Heath hub
4 days ago

London Bankside Yards next project switches from resi to offices

Revised plan submitted for 18-storey office next to Blackfriars Bridge
4 days ago

Plans in for Cambridge North major mixed-use scheme

Over 400 homes and nearly 600,000 sq ft of office and shops planned for railway sidings site
4 days ago

Contractor services