Everton ‘lock-in” construction costs with O’Rourke at new stadium

Grant Prior 3 years ago
Share

Everton FC has signed an agreement with Laing O’Rourke which will see the contractor deliver the final phase of the club’s new £500m stadium at Bramley-Moore Dock and “lock-in construction costs.”

Work continues on the waterfront site
Work continues on the waterfront site

The main construction contract will see O’Rourke complete construction of the new 52,888-capacity waterfront stadium “while also providing Everton with greater certainty as to the cost of the remaining stages of the project.”

The deal follows on from the Pre-Contract Services Agreement (PCSA) signed by both parties in February 2021 and the Enabling Works Contract (EWC), which was focused on delivering the preparatory works at the North Liverpool site, including the in-filling of the dock that was completed in December.

Under the new agreement, O’Rourke will deliver a programme of works which includes the completion of any outstanding enabling works, the full construction of the stadium and public realm, and remedial works to the Grade II listed Hydraulic Tower, which will be brought back into public use.

Everton Chief Executive, Denise Barrett-Baxendale, said: “This is an important agreement at a crucial time for the Club and the stadium project.

“Our agreement with Laing O’Rourke follows on from last year’s pre-contract services and enabling works agreements and brings clarity on the overall costs of our new stadium.

“We are now able to lock-in construction costs, while also benefiting from Laing O’ Rourke’s economies of scale in what is an ever-fluctuating marketplace.

“Our new agreement signifies that we have the utmost confidence in Laing O’Rourke, who are using the very best digital engineering expertise and industry-leading knowledge of modern construction methods to bring our stadium vision to life.”

Construction work on the stadium began in the summer of 2021, with significant progress made on site as non-listed structures have been demolished, heritage assets removed and preserved, the dock basin repaired and infilled, foundations laid and the concrete structure of four corners of Everton’s new home now starting to emerge from the ground.

Latest news

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
1 day ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
2 days ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
1 day ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
2 days ago

Ballymore JV picked for £500m King’s Cross scheme

Camley Street scheme to consist of 350 homes and offices
2 days ago

Digger stolen from Dorset site recovered in Poland

Machine found after four month police hunt
1 day ago

Construction firms face claw back of R&D tax credits

HMRC estimates only 38% of construction claims are "wholly compliant"
2 days ago

Willmott Dixon bounces back into profit in first half

CEO predicts ISG demise will shift client mindsets from lowest bid to best quality
2 days ago

M&E specialist Integral UK suffers fifth year of losses

Building services and FM specialist plunges to £32m loss
2 days ago

Glenbrook plans 44-storey Manchester resi tower

Scheme next to Deansgate station will contain 360 flats
2 days ago

Downing submits 430-bed London student scheme

Two-10 storey towers planned at Wandsworth Gasholder Site
2 days ago

Mace construction head steps down

Andrew Jackson leaves top role after three months
3 days ago

Pre-pack saves 60 jobs at fit-out firm WFC Contractors

Aviation fit-out group swoops on up-market hospitality fit-out specialist
3 days ago

Multiplex in talks for ISG’s £70m London offices to labs job

Plan to restart Regent Quarter life science campus with ISG project team
3 days ago

M&E firm goes under after more than 70 years in business

HBS Group Southern employed 75 staff
4 days ago

Trio of big names win £600m biscuit factory revamp

Developer Greystar confirms deals for McLaren, McAleer & Rushe and Sisk
4 days ago

HS2 London tunnels chief joins Transpennine Route Upgrade

James Richardson will take up MD role at TRU in New Year
3 days ago

Transport minister signals HS2 will run to Euston

Decision expected in spending review and budget later this month
4 days ago

£9bn Lower Thames Crossing decision delayed 7 months

Fears grow mega project could be axed in upcoming Budget
4 days ago

Vistry issues profit warning over build out costs at southern division

Probe launched after £115m hit on 9 schemes where build costs under estimated by 10%
4 days ago

ISG administrator tells subbies no funds to pay debts

EY warns trade creditors they are unlikely to see any of the cash they are owed
4 days ago

Giga factory powers McAlpine to top of contracts league

Work winning for the top 50 firms rebounded in September after August lull
4 days ago

Merit to build £30m modular NHS medicines centre

Specialist starts work on offsite components
4 days ago

Buckingham supply chain hit soars above £300m

Unpaid bills from unsecured creditors keep mounting
5 days ago

Mapping experts take control of buried pipes register

Ordnance Survey to help ensure safe digging and excavation
4 days ago

Winners of £3bn London housing major works deal

Graham, Kier, McLaren, Morgan Sindall, Vinci and Wates win places
5 days ago

BBC brickies firm went down owing £2m to suppliers

Hodgkinson Builders sold for £95,300 in pre-pack deal
5 days ago

Network Rail reveals top suppliers spend

BAM leads as biggest civils rail contractor
5 days ago

Go-ahead for £125m Immingham Ro-Ro terminal

Dragados is lined up to deliver the terminal which includes three new berths
5 days ago

Renew buys onshore wind firm for £50m

Full Circle deal adds 160 specialist technicians to workforce
5 days ago

Contractor services