Water industry revives PFI model for £1bn job

Aaron Morby 3 years ago
Share

United Utilities is set to become the first major water company to pioneer a reinvented design, build and finance model to construct major infrastructure projects in the sector.

Previous surface works on Haweswater Aqueduct upgrade
Previous surface works on Haweswater Aqueduct upgrade

The water company is going ahead with the ‘ground-breaking new contract model’, after receiving formal consent from water regulator Ofwat.

United Utilities will trailblaze the design, build, finance and maintain approach for the upgrade of the 110km Haweswater Aqueduct from Cumbria to Greater Manchester which has supplied water for more than 70 years.

It is one of five water companies to be given the go-ahead to use the new Direct Procurement for Customers model, which requires contractors to bring private finance to the table with their bids in a similar way to the old PFI procurement route.

One contractor told the Enquirer: “If this advances work more quickly then I welcome it. But he warned: “It could also see major international contractors entering the market and flexing financial muscle.

“That could be to the detriment of the UK supply chain, having a much more negative long term consequence.”

Another civils firm source said: “UK contractors may be understandably cautious about this new PFI model type, given past experience and the present inflationary environment.”

United Utilities has spent three years of planning and commercial development for its pathfinder £1bn Haweswater Aqueduct Resilience Programme and now plans to kick off bidding for six replacement tunnels in July.

Neil Gillespie, director of Strategic Programmes at United Utilities, said: “A project of this scale will always be challenging from a technical and planning perspective, but we have also had to start from scratch to develop the commercial framework for the procurement model.

“We are seeking to appoint a Competitively Appointed Provider (CAP) to design, build and fund six replacement tunnel sections of the Haweswater Aqueduct and maintain it for a period of 25 years post-construction.”

“We have put a lot of effort into engaging the market over the last three years, hosting a number of events to test our thinking and take on board feedback to help us to refine the DPC model. This has also given potential bidders early insight into what the winning CAP will be responsible for and this process has generated considerable interest from investors and construction companies.”

The water regulator Ofwat has approved the financing model arguing it will bring big savings for customers through innovation and lower whole-life costs of the project.

Keith Mason, senior director, Future Assets and Resources at Ofwat said “Direct procurement for customers has, through competition, the potential to benefit customers in England and Wales in delivering the largest and most complex water and wastewater assets at a lower cost, while allowing new providers to introduce new ideas.

“We welcome the HARP project. It is a pathfinder being the first project to be procured under our DPC process which we expect will become a model for future infrastructure delivery.”

He added: “We believe that by outsourcing the delivery of infrastructure projects using DPC, water companies can achieve significant benefits for customers. This includes both through innovation and lower whole-life costs of the project.”

HARP in detail


HARP will be the largest infrastructure project undertaken by United Utilities since privatisation.

The original aqueduct was completed in the 1950s to increase supplies of water into Manchester and the Pennines region from the Lake District.

The original pipeline under construction

The project will see the replacement of six tunnel sections along the 80-mile aqueduct route, ensuring the resilience of the asset for decades to come.

The scope of the HARP DPC Project is the delivery of:

(a) design, construction, testing and commissioning of the works.

(b) planned and corrective maintenance, including lifecycle maintenance, of the assets following the completion of each section of the tunnel.

(c) the project management of the activities.

(d) financing of the activities.

While the commercial framework was being developed, considerable preparatory work was undertaken to support the design process. Costain was onboard for early assessment and survey work of the aqueduct network

United Utilities also partnered with the British Geological Survey to generate a 3D ground model to allow prospective bidders to understand the ground conditions.

Latest news

Skanska lifts margin to 4.3% as profit hits £78m

Infrastructure and FM drive near-tripling of profits
37 minutes ago

Durkan dogged by legacy jobs despite return to trading profit

Durkan scales down new homes contracting to focus on retrofit work
4 hours ago

Inland Homes creditors face £38m hit

Administrator confirms no cash for supply chain
7 hours ago

Barking build to rent towers face rebuild

Major remedial work needed on resi scheme built by Shapoorji Pallonji UK Ltd
14 hours ago

London new home starts plunge 38% as Building Safety Act bites

Capital only region to see Q1 fall in NHBC new home registrations
1 day ago

Sureserve swoops for rival compliance outfit Kinovo in £56m deal

Recommended cash offer will take AIM listed contractor private
14 hours ago

Crown Golf tees up £1bn plan to build 3,000 homes on course land

Major housing plan for spare land on eight UK courses
13 hours ago

Green light for Peterborough Station Quarter £48m revamp

First phase to start before the end of the year
14 hours ago

Morgan Sindall starts £38m Caerphilly leisure hub

New swimming pool and health suite forms part of town regeneration plan
13 hours ago

145 firms win places on £800m building safety framework

Fusion21 confirms latest winners: Full list
1 day ago

Higgins Homes and site workers face manslaughter charges

Contractor and four site staff charged after woman killed by falling pallet of bricks
2 days ago

Operator spots cracked mast on Hinkley tower crane

Hinkley Point C contractor hit with safety notice over failed mast pin and cracks
2 days ago

Countdown starts for £1bn Birmingham highways bid race

Council will break-up mega framework into five lots
2 days ago

Acciona wins £400m Thames waterworks upgrade

Lea Valley Coppermills water treatment works to get full overhaul
2 days ago

Pension giants pledge £25bn for infrastructure push

Seventeen pension providers pledge to invest in projects
2 days ago

Safety row over London tower ducking fire regs by 30cm

Fire union calls on Mayor to block Bromley flats plan over single staircase
2 days ago

Midgard lands £145m deal to build Edition Birmingham

Construction to start shortly on twin residential towers
2 days ago

McAleer & Rushe set to break £500m turnover barrier

Pre-tax profit jumped 16% to £46m last year
2 days ago

Top design team picked for £2.5bn York Central scheme

Massive city centre regen scheme moves to detailed design
3 days ago

MoD to bid £100m command HQ enabling works

Hertfordshire joint forces command centre expansion advances
3 days ago

Failed shed specialist Marbank owed suppliers £10m

Contractor was facing a string of adjudication claims
3 days ago

New scaffolding training trade body launches

Scaffolding Training Alliance formed amid disquiet caused by planned training changes
2 days ago

£1.8bn framework planned for green retrofit drive

Procure Plus to invite bids later this month
3 days ago

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5-mile TBM drive in 652 days
5 days ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
6 days ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
6 days ago

Leicester rebids £22m station revamp after failed tender race

Council opts for ECI route after receiving one bid for project
6 days ago

Kier wins £58m East Coast College rebuild job in Great Yarmouth

Work to start this summer for 1,300-student college
6 days ago

R G Carter wins £28m hospital car park job in King’s Lynn

MSCP paves way for £1.5bn Queen Elizabeth Hospital rebuild in 2027
6 days ago

London to relax green belt building rules

Sadiq Khan shifts position on planning
6 days ago

Contractor services