Dazzling sun causes rail repair machines to collide

Grant Prior 3 years ago
Share

A report into a collision between two road-rail vehicles in Essex has revealed the crash was caused by the driver being dazzled by bright sunlight.

The wrecked MEWP after the collision
The wrecked MEWP after the collision

The Rail Accident Investigation Branch also found that lessons from a similar earlier accident were not learnt.

On 2 May 2021 two road-rail vehicles collided while travelling on the same track towards Wickford station from a location of work near Ramsden Bellhouse, Essex.

J Murphy & Sons was Network Rail’s principal contractor on the job to repair overhead lines while the accident victims were working for subcontractor SPL Powerlines UK.

The leading vehicle, a mobile elevating work platform (MEWP), was stationary at the time of the collision and was hit from behind at around 7.5 mph by a road-rail machine, configured as a crane. The MEWP operator suffered life-changing injuries due to the collision.

Around 10 seconds before the collision, the MEWP operator had stopped to stow away a tool which was loose in the personnel basket of his machine.

Around the same time, the operator of the crane became dazzled by the rising sun ahead. The crane operator turned to look out of the side window to relieve his eyes but did not apply the brakes of the crane when he did so, resulting in the collision with the MEWP.

Before the collision, the crane operator had allowed the gap between the crane and the MEWP to reduce so that, when the MEWP stopped, it was only about 30 metres.

Network Rail standards require operators to maintain a minimum separation distance of 100 metres when travelling in convoy with other vehicles. The shortened separation distance in this case reduced the time that the crane operator had to observe and react to the obstruction ahead.

Fatigue was a possible factor in this accident, as the crane operator had not taken advantage of the opportunity to rest before the nightshift at a hotel provided by his employers. He had also not declared his actual travel time when providing his journey details at the site access control point.

A similar collision occurred at Wellingborough on 15 August 2019. The industry’s investigation into that accident found that the machine operators involved had been regularly ignoring the need to maintain an adequate separation between vehicles.

Andrew Hall, Chief Inspector of Rail Accidents said: “Sadly, this readily-avoided accident led to a member of railway staff sustaining life changing injuries.

“Bright sunlight can temporarily dazzle or obscure vision. It is important that those driving vehicles by line of sight, slow sufficiently or stop if visibility becomes poor. Even momentary dazzling can lead to an unsafe situation rapidly developing.

“When operating rail-road machines on the railway it is essential to maintain the defined safe distance of 100 metres with other moving vehicles. This accident involved differential speeds dangerously reducing the distance between the vehicles from 90 metres to approximately 30 metres during the journey.

“Recognising the true distances involved, as well as the potential consequence of road-rail vehicles travelling in convoy at different speeds, is vital to maintaining safe distances between vehicles.

“What is particularly frustrating about this accident, is that lessons from a previous accident involving the same contractor had not been learned.

“Both accidents shared similar factors including a lack of adequate separation between vehicles, a loss of attention and avoiding action not being taken.

“Not applying these lessons to improve planning of work or the site assurance processes was an opportunity missed to avoid a collision with severe consequences.”

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
6 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
7 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
7 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
7 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
1 day ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
1 day ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
7 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
1 day ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
1 day ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
1 day ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
1 day ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
1 day ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
1 day ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
1 day ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
1 day ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
4 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
4 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
4 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
5 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
4 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
4 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
5 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
5 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
5 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
5 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
6 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
5 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
5 days ago