Extra design work digs £200m deeper into HS2 contingency

Aaron Morby 3 years ago
Share

The cost of extra design work on the HS2 main work contracts has eaten £200m into contingency funding for the project in the last six months.

Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year
Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year

The latest progress report on the mega project reveals that HS2 has had to dig deeper into its £5bn contingency funds.

Significant amounts of the original design work on HS2’s Euston station have been ditched after the decision was taken for the station to be scaled back from 11 to 10 platforms.

HS2 chiefs are now projecting around £1.9bn of net additional cost pressures on phase 1, an increase of about £200m since March and £700m more than a year ago.

So far the mega project has drawn £1.5bn or 28% of its £5.6bn contingency for phase 1, leaving about £4bn in the pot to complete phase one of the project within the 2029 to 2033 time frame.

The latest project spend figures are based on 2019 prices and do not take into account industry-wide construction materials inflation which hit 18% according to official Government figures in the year to August.

HS2 is now ramping up to hit peak construction next year and is now supporting 29,000 construction jobs, with nearly 2,600 firms to date working on the project.

Transport secretary Mark Harper in a six-month HS2 monitoring report to Parliament said:  “While inflation is not affecting the overall affordability of HS2 in real terms because the total budgets and cost estimates for each phase are set in 2019 prices, it is creating pressures against its existing annual funding settlements, which have been set in cash.

“I am clear that HS2 Ltd and its supply chain must do all that they can to mitigate inflationary pressures.”

He said that HS2 was tasked in September to develop and implement actions to bring projected costs back in line with the target cost.

It has since identified an estimated £800m of net savings and efficiencies within phase 1.

These principally consist of savings across the main works civils portfolio and savings in the acquisition and resale of land and property.

These have partly offset gross cost pressures resulting in the latest published net figure.

Harper reported that HS2 phase 1 was still on track to be delivered within its maximum targeted cost including contingency of £45bn.

The phase 2a budget remains unchanged, with a cost range of £5.2bn to £7.2bn.

Government intends to set a target cost alongside the publication of the full business case shortly.

On phase 2b Western Leg, the overall cost range has fallen by around £3bn after removing the Golborne Link.

 

Latest news

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
29 minutes ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
6 hours ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
7 hours ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
8 hours ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
8 hours ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
8 hours ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
8 hours ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
8 hours ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
1 day ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
1 day ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
1 day ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
1 day ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
1 day ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
1 day ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
4 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
5 days ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
4 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
4 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
4 days ago

Profits double at Octavius as road and rail work grows

Recent acquisitions add to turnover growth at infrastructure specialist
5 days ago

Quarterly construction output growth masks orders slide

New orders down by over 8% driven by fall in infrastructure and offices
5 days ago

Vinci UK swings back into profit after group restructure

£166m cash injected to strengthen building and facilities operations balance sheets
6 days ago

Staged procurement to make comeback as pricing risk bites

Developers turn to staged deals to control costs on big-ticket commercial jobs
5 days ago

McGee profit halves as project start delays hit

Revenue up 24% but profits fall on higher carry costs
5 days ago

Vistry to deliver 2,300 homes at Rugeley power station site

139-acre brownfield site has already been extensively remediated
5 days ago

Andrew Scott wins role on Swansea’s next big office build

Contractor appointed for detailed design of 800-desk city centre hub.
5 days ago

Knights Brown to start £29m Poole flood wall job

1.5km barrier to protect homes and unlock regeneration plans
5 days ago

Kier lands £16m first ECI job with Southern Water

Design deal covers nitrogen cut and UV upgrade at Hampshire wastewater sites
6 days ago

Watkin Jones seals deal on 200-bed student scheme

Bristol project will involve four brick buildings rising to seven storeys
6 days ago

Severfield brings in new CEO from Laing O’Rourke ranks

Everton Stadium job chief Paul McNerney to take the helm in the autumn
6 days ago