Extra design work digs £200m deeper into HS2 contingency

Aaron Morby 1 year ago
Share

The cost of extra design work on the HS2 main work contracts has eaten £200m into contingency funding for the project in the last six months.

Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year
Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year

The latest progress report on the mega project reveals that HS2 has had to dig deeper into its £5bn contingency funds.

Significant amounts of the original design work on HS2’s Euston station have been ditched after the decision was taken for the station to be scaled back from 11 to 10 platforms.

HS2 chiefs are now projecting around £1.9bn of net additional cost pressures on phase 1, an increase of about £200m since March and £700m more than a year ago.

So far the mega project has drawn £1.5bn or 28% of its £5.6bn contingency for phase 1, leaving about £4bn in the pot to complete phase one of the project within the 2029 to 2033 time frame.

The latest project spend figures are based on 2019 prices and do not take into account industry-wide construction materials inflation which hit 18% according to official Government figures in the year to August.

HS2 is now ramping up to hit peak construction next year and is now supporting 29,000 construction jobs, with nearly 2,600 firms to date working on the project.

Transport secretary Mark Harper in a six-month HS2 monitoring report to Parliament said:  “While inflation is not affecting the overall affordability of HS2 in real terms because the total budgets and cost estimates for each phase are set in 2019 prices, it is creating pressures against its existing annual funding settlements, which have been set in cash.

“I am clear that HS2 Ltd and its supply chain must do all that they can to mitigate inflationary pressures.”

He said that HS2 was tasked in September to develop and implement actions to bring projected costs back in line with the target cost.

It has since identified an estimated £800m of net savings and efficiencies within phase 1.

These principally consist of savings across the main works civils portfolio and savings in the acquisition and resale of land and property.

These have partly offset gross cost pressures resulting in the latest published net figure.

Harper reported that HS2 phase 1 was still on track to be delivered within its maximum targeted cost including contingency of £45bn.

The phase 2a budget remains unchanged, with a cost range of £5.2bn to £7.2bn.

Government intends to set a target cost alongside the publication of the full business case shortly.

On phase 2b Western Leg, the overall cost range has fallen by around £3bn after removing the Golborne Link.

 

Latest news

London £3bn housing framework out to tender

SMEs allocated slots on London Construction Programme housing framework refresh
50 mins ago

BAM wins first major RAAC school rebuild

Contractor seals £46m deal for St Leonards school in Durham
1 hour ago

Failed strip out specialist owes £1.5m to supply chain

More than 100 subcontractors and suppliers left with unpaid bills by Type Ten Limited
2 hours ago

Councils to turn screw on building owners over fire safety upgrades

Government tells councils to step up legal action against rogue building owners
2 hours ago

Green light for £300m Fenland energy from waste scheme

Wisbech incinerator will generate 50MW from half a million tonnes of waste
15 hours ago

Multiplex starts on 50-storey Thames tower

Developer green lights construction of latest phase of £3bn Bankside Yards scheme
21 hours ago

McLaren lodges fresh Reading Broad Street Mall plan

Town centre scheme will deliver 600 homes in four towers
1 day ago

Beard bags £24.5m Bristol office revamp

Construction to start in April
1 hour ago

SMEs star in £3.2bn social housing upkeep deal

Around 85% of Efficiency North's framework winners are local firms
1 day ago

Scottish NHS new building projects delayed for two years

Spending clampdown hits over a dozen planned projects
1 day ago

Balfour M25 workers hold strike ballot

Motorway maintenance crews unhappy with 3.4% pay rise offer
1 day ago

Rainsford Contracts acquires M&E specialist

Expanded contractor will have turnover of £45m
1 day ago

Statom expands with launch of Northern HQ

RC frames specialist now targeting jobs in Scotland and north of England
2 days ago

High Court dismisses Stonehenge tunnel challenge

Judge quashes legal challenge against Government consent for £1.7bn job
2 days ago

£1.5bn Teesside carbon capture scheme consented

Final investment decision expected this year for construction start
2 days ago

First viaduct steel section installed at HS2’s complex junction job

Victor Buyck Steel Construction install first 300t viaduct section
2 days ago

Sister scaffold firms file administration notices

BCM Scaffolding Services and Scaffteq West employ 100 people between them
2 days ago

McLaughlin & Harvey suffers £8.6m loss

Cost inflation and Scottish landfill tax legislation hit Antrim-based group
2 days ago

Regulator opens probe into National Highways delivery

ORR concerned about 'dip in performance' on capital projects
2 days ago

Sir Robert McAlpine chief Paul Hamer exits

Hamer replaced as CEO by former Lendlease Europe boss Neil Martin
5 days ago

Unite Students to build £250m Newcastle scheme

Work to start this summer on revamp of Castle Leazes site
2 days ago

Britcon poaches Tilbury Douglas business development chief

Don Stewart joins Britcon board as strategic director
2 days ago

Building control system on verge of collapse

Calls to delay new registration scheme
5 days ago

Go-ahead for UK’s largest mass timber structure neighbourhood

Visionary 685-home sustainable village will be built in Lewes, East Sussex
5 days ago

£90m Manchester zig-zag library approved

Work to start this summer on iconic city centre building
5 days ago

Mace clear to start £34m weather-watching HQ job

Planning granted for European Centre for Medium-Range Weather Forecasts
5 days ago

Ford Dagenham site revamp to hit nearly 4,000 homes

Latest phases approved for £1bn Beam Park redevelopment
5 days ago

Sisk names new data centres regional director

John Hennessey appointed to lead expansion
6 days ago

Balfour starts £171m Sussex Uni student DBFO job

West Slope Residences will provide 1,900 bedrooms
6 days ago

Director and site manager sentenced after labourer crushed

Worker killed during demolition on renovation scheme
6 days ago

Contractor services