Extra design work digs £200m deeper into HS2 contingency

Aaron Morby 1 year ago
Share

The cost of extra design work on the HS2 main work contracts has eaten £200m into contingency funding for the project in the last six months.

Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year
Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year

The latest progress report on the mega project reveals that HS2 has had to dig deeper into its £5bn contingency funds.

Significant amounts of the original design work on HS2’s Euston station have been ditched after the decision was taken for the station to be scaled back from 11 to 10 platforms.

HS2 chiefs are now projecting around £1.9bn of net additional cost pressures on phase 1, an increase of about £200m since March and £700m more than a year ago.

So far the mega project has drawn £1.5bn or 28% of its £5.6bn contingency for phase 1, leaving about £4bn in the pot to complete phase one of the project within the 2029 to 2033 time frame.

The latest project spend figures are based on 2019 prices and do not take into account industry-wide construction materials inflation which hit 18% according to official Government figures in the year to August.

HS2 is now ramping up to hit peak construction next year and is now supporting 29,000 construction jobs, with nearly 2,600 firms to date working on the project.

Transport secretary Mark Harper in a six-month HS2 monitoring report to Parliament said:  “While inflation is not affecting the overall affordability of HS2 in real terms because the total budgets and cost estimates for each phase are set in 2019 prices, it is creating pressures against its existing annual funding settlements, which have been set in cash.

“I am clear that HS2 Ltd and its supply chain must do all that they can to mitigate inflationary pressures.”

He said that HS2 was tasked in September to develop and implement actions to bring projected costs back in line with the target cost.

It has since identified an estimated £800m of net savings and efficiencies within phase 1.

These principally consist of savings across the main works civils portfolio and savings in the acquisition and resale of land and property.

These have partly offset gross cost pressures resulting in the latest published net figure.

Harper reported that HS2 phase 1 was still on track to be delivered within its maximum targeted cost including contingency of £45bn.

The phase 2a budget remains unchanged, with a cost range of £5.2bn to £7.2bn.

Government intends to set a target cost alongside the publication of the full business case shortly.

On phase 2b Western Leg, the overall cost range has fallen by around £3bn after removing the Golborne Link.

 

Latest news

Geoffrey Osborne files administration notice

Latest accounts show £325m turnover and 800 staff
3 hours ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
21 mins ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
3 hours ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
2 hours ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
2 hours ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
2 hours ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
23 hours ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
1 day ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
2 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
1 day ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
1 day ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
1 day ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
2 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
1 day ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
2 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
2 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
2 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
2 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
3 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
3 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
3 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
3 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
3 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
3 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
4 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
3 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
4 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
4 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
3 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
4 days ago

Contractor services