West Yorkshire transport projects delayed to save £270m

Aaron Morby 2 years ago
Share

More than 30 transport schemes in West Yorkshire are to be placed on hold or delayed due to cost inflation.

Halifax railway station upgrade to be put on hold
Halifax railway station upgrade to be put on hold

West Yorkshire Combined Authority has agreed to pause the schemes to save £270m and create headroom for other projects to proceed.

The delays agreed by the WYCA finance committee will affect road-widening projects, park and ride schemes and railway station redevelopment.

Among the biggest schemes to be paused are £48m Bradford to Shipley Corridor Improvement, the £46m South East Bradford Access Road. The authority will also pause Kirklees’ A62 to Cooper Bridge improvements and  Bradford’s £20m A650 Tong Street scheme while it seeks alternative sources of funding.

The £23m Halifax Station Gateway will also be paused along with two bus park and ride, and five rail park and ride schemes.

Paused Project  Project Status Cost
A61 (N) multi modal corridor improvements – Scott Hall Road bus £14m
A62 to Cooper Bridge Corridor Improvements FBC £69m
A629 (Phase 4) – Ainley Top FBC £26m
A629 (Phase 5) – Ainley Top into Huddersfield FBC £13m
A650 Tong Street FBC £20m
Bradford to Shipley Corridor FBC £48m
CityConnect Phase 3 Cooper Bridge OBC £1.8m
CityConnect Phase 3 Huddersfield Town Centre FBC £1.3m
Programme – Bradford – OBC £10m
Corridor Improvement Programme – Calderdale – A629 FBC £6m
Corridor Improvement Programme – Kirklees – A629 – Fenay Lane OBC £7.5m
Corridor Improvement Programme – Kirklees – Huddersfield Southern FBC £12m
Corridor Improvement Programme – Leeds – A58 Roundhay Road FBC £9.5m
Corridor Improvement Programme – Leeds – Dawsons Corner FBC £14m
Corridor Improvement Programme – Wakefield – A638 FBC £6,m
Corridor Improvement Programme – Wakefield – Owl Lane OBC £0.05m
Halifax Station Gateway FBC £11m
Huddersfield Station Gateway (Phase 1) OBC £10m
Leeds Inland Port FBC £3m
Mirfield to Dewsbury to Leeds (M2D2L) FBC £12m
Rail Parking Package – Apperley Bridge OBC £1m
Rail Parking Package – Ben Rhydding OBC £2m
Rail Parking Package – Guiseley OBC £7m
Rail Parking Package – Outwood FBC £3m
Rail Parking Package Phase 1 OBC
Rail Parking Package phase 2 x x
South East Bradford Access Road OBC £46m
A61 Bus – Cycle – Walking Improvements OBC £5m
A61 Bus – Cycle – Walking Improvements OBC £7m
A629 Wakefield Road Sustainable Travel Corridor OBC £6m

Mayor Tracy Brabin said: “As a Mayoral Combined Authority, we are one of the first to be acting so swiftly and so collaborative to get this tricky piece of work over the line.

Director of Delivery Malanie Corcoran said that the schemes would be added to a paused pipeline and taken to outline or final business case to allow a quick start if funding becomes available at a later date.

The authority’s £1bn transport programme currently has over-programming of £151m, which could potentially increase in the near future to £215m due to the impact of current inflation rates.

The committee was told that over-programming needs to be reduced and headroom created within the programme to fund unforeseen cost rises expected in the coming 12-18 months due to inflation rises.

 

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
14 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
11 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
21 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
22 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
22 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
22 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
21 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
22 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services