HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Civils winners revealed for £12bn National Grid high voltage work

Contractor wins complete £59bn investment programme
9 hours ago

United Living quits new-build housing as costs mount

£136m-turnover housing arm to wind down as focus shifts to core infrastructure
12 hours ago

Fight looms for £3bn West Midlands building framework

Galliford Try, Morgan Sindall and others face fight to keep CWM seats
12 hours ago

Industry anger over sudden CITB funding changes

Smaller contractors lose funding route worth £10,000 a year
12 hours ago

Plans in to transform former GSK London HQ with 2,300 homes

Landmark 13-acre scheme set to transform Brentford Great West Road campus
11 hours ago

Watch Murphy near completion of major new rail bridge

Latest video reveals progress on Greek Street bridge during 21-day train suspension
12 hours ago

Mount Anvil’s in-house builder drives results in testing market

Group development pipeline holds steady at 3,384 homes despite dip in profit
13 hours ago

Costain margin heads for 4.5% after half-year profit rise

Roads and HS2 rephasing hit transport revenues but £5.6bn forward book to support growth
1 day ago

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
2 days ago

Farrans to build new £59m Paisley bridge

Work to start soon on transport project for Renfrewshire Council
2 days ago

Crown Estate hires Olympics village veteran to lead delivery push

John Nicholson to oversee £16bn portfolio’s major UK development pipeline.
1 day ago

Henry Boot gets green light for 2,500 new homes

Hallam Land division sees signs planning system is speeding-up
2 days ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
2 days ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
2 days ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
3 days ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
2 days ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
3 days ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
2 days ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
2 days ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
4 days ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
3 days ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
3 days ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
4 days ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
3 days ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
3 days ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
7 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
1 week ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
7 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
6 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
6 days ago