HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Higgins Homes and site workers face manslaughter charges

Contractor and four site staff charged after woman killed by falling pallet of bricks
11 hours ago

Midgard lands £145m deal to build Edition Birmingham

Construction to start shortly on twin residential towers
13 hours ago

McAleer & Rushe set to break £500m turnover barrier

Pre-tax profit jumped 16% to £46m last year
14 hours ago

Top design team picked for £2.5bn York Central scheme

Massive city centre regen scheme moves to detailed design
18 hours ago

MoD to bid £100m command HQ enabling works

Hertfordshire joint forces command centre expansion advances
17 hours ago

Failed shed specialist Marbank owed suppliers £10m

Contractor was facing a string of adjudication claims
18 hours ago

New scaffolding training trade body launches

Scaffolding Training Alliance formed amid disquiet caused by planned training changes
10 hours ago

£1.8bn framework planned for green retrofit drive

Procure Plus to invite bids later this month
17 hours ago

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5-mile TBM drive in 652 days
4 days ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
4 days ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
5 days ago

Leicester rebids £22m station revamp after failed tender race

Council opts for ECI route after receiving one bid for project
4 days ago

Kier wins £58m East Coast College rebuild job in Great Yarmouth

Work to start this summer for 1,300-student college
4 days ago

R G Carter wins £28m hospital car park job in King’s Lynn

MSCP paves way for £1.5bn Queen Elizabeth Hospital rebuild in 2027
4 days ago

London to relax green belt building rules

Sadiq Khan shifts position on planning
4 days ago

Willmott Dixon wins Great Yarmouth waterfront deal

North Quay 10.5 acres mixed-use scheme to advance
5 days ago

SIG chief quits to join Travis Perkins

Gavin Slark to leave by the end of this year
4 days ago

Eight take key spots on £250m Prosper framework

Housing and public building upkeep deal for North East awarded
5 days ago

Early call-out for £150m Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
6 days ago

McLaren storms April contracts league with flurry of wins

Cardiff Bay Arena job headlines a series of big contract wins
5 days ago

Balfour Beatty lifts cash forecast after strong first quarter

Contractor set to hit £1bn average monthly net cash in 2025
5 days ago

Goldman Sachs-owned Adler & Allan buys 180-strong civils outfit

West Country's Glanville Environmental gets new owner
5 days ago

Caddick lands first contract for £200m Skelmersdale revamp

Developer gets green light for masterplan
5 days ago

Van Elle sells HGV fleet to haulage firm

WS Specialist Logistics pays £2.9m to take on fleet and drivers
5 days ago

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
6 days ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
6 days ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
6 days ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
6 days ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
6 days ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
6 days ago

Contractor services