HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Bombshell cavity barrier defects wipe out Taylor Wimpey profits

Fresh £222m provision for fire safety failings behind brick facades
9 hours ago

39 firms win £3bn South East schools framework

LCP panel covers new build, retrofit and fire safety upgrade work
19 hours ago

Esh boss bullish as profits and prospects rise

North of England contractor looking forward to continued growth
1 day ago

Government sets up Platform4 to build 40,000 homes on rail land

Former Lendlease Development chief Bek Seeley to head Platform4
9 hours ago

Race starts for £858m London highways consultancy deal

Ealing Council is leading the launch of a major new highways and transport consultancy framework
10 hours ago

Bridge parts set sail for £20m Murphy Stockport site

"Dress rehearsal" bridge assembly ahead of three week rail closure
9 hours ago

22 firms win Prosper £500m new build homes framework

Deal designed with input from Believe Housing, Gentoo and Karbon Homes
19 hours ago

Civils contractor Galldris sold to staff

£125m turnover firm transitions to Employee Ownership Trust
1 day ago

Fit-out firepower drives Morgan Sindall to record half-year

£390m cash pile supports push on partnerships and frameworks
1 day ago

Grid delays now rival planning as chief threat to project delivery

Turner & Townsend flags urgent need to prioritise electricity connections on projects
1 day ago

Forterra to shut down two divisions

Materials giant exiting Formpave block paving and Bison Bespoke precast businesses
1 day ago

Vistry and Kier team up again for Wokingham homes plan

Third major partnership kicks off first phase of 1,400-home Berkshire plan
2 days ago

Wates preps £200m Middlesbrough regen site

Work begins on landmark Crown Square project with hotel, student flats and homes
2 days ago

BAM Nuttall rail boss to join Balfour

Richard Watts to become Managing Director of UK Rail business
5 days ago

Peel Ports unveils £60m expansion plan for Yarmouth

New Southern Terminal to target big infrastructure and offshore energy schemes
2 days ago

£1bn beach defence mega-framework up for grabs

Environment Agency seeks two marine contractors to protect England’s coastlines
2 days ago

Bovis set for £220m tower job near British Museum

John F Hunt to start demolition work for big West End scheme
2 days ago

Carnell poaches another National Highways director

Maintenance contractor becomes latest private firm to lure public sector chief
2 days ago

Plans go in for Warrington logistics site revamp

Outdated units to be replaced at Hawleys Lane
2 days ago

Morgan Sindall site closed after fatal accident

Tragedy at £90m Mill Yard job in Cambridge
5 days ago

DfE signs off £148m school rebuild trio

B+K and Bouygues land major academy projects across England
5 days ago

Contract race starts for £205m A9 dualling job

Latest deal involves building or upgrading nine bridges
5 days ago

Higgins to turn former care home site into council houses

Construction to start early next year on Buckinghamshire scheme
5 days ago

Green light for £1.7bn Edgware town centre revamp

Ballymore to deliver 3,365 new homes
6 days ago

Work to start on £40m Blackpool Multiversity build

Morgan Sindall to start demolition for five-storey education campus
5 days ago

Bridge faults plunge Severfield into £18m loss

Firm cuts staff by 6% and raises option to sell part of stake in Indian arm
6 days ago

BAM UK Construction back in the black after Co-op woes

Nuttall civils arm powers up profits with margin topping 5%
6 days ago

Mace sells consulting business to Goldman Sachs

Sale gives construction bosses "opportunity to refresh and simplify" operation
1 week ago

Vinci gets green light for £35m St Helens transport hub

New interchange set to anchor wider town centre revamp
6 days ago

National Highways major projects chief to join Skanska

Dean Sporn to become Operations Director at infrastructure business
7 days ago