HS2 Euston needs full design reset as costs set to double

Aaron Morby 3 months ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Ilke Homes put up for sale in battle to save modular builder

Works stops at factory and sites as loss-making offsite specialist fights for survival
23 hours ago

Henry Construction crashes into administration

Hundreds of trade contractors hit by collapse of £400m revenue firm
2 days ago

Barratt to demolish 36 new homes with faulty foundations

Problems found on Cambridge estate
1 day ago

Firms readied for £750m Parliament repairs deal

Strategic Estate is renewing the estate repair framework
1 day ago

Magna Park developer to build 1.4m sq ft of spec sheds

Four major warehouse units to be spec built as total space hits 13m sq ft
1 day ago

Second staircases to delay resi tower projects by 9 months

Cost consultants cuts London tender price rise forecast to 2% this year
1 day ago

Plan approved for tallest resi tower in Wales

£55m project will be built next to Cardiff's Central Square
2 days ago

Bowmer + Kirkland bags £46m events centre in Derby

Developer keeps to original fixed price contract figure despite inflationary pressures
1 day ago

Costain dropped from £1.3bn A66 road job

National Highways pulls Costain off TransPennine upgrade and demands its £1bn A12 widening now shared as a JV
2 days ago

Laing O’Rourke plans to cut 200 staff jobs

Dartford head office to see bulk of job cuts
3 days ago

SES Services restructures senior team

New MD Rob Clifford to head four new divisions at M&E specialist
2 days ago

Galliford Try ranks top in May contracts league

Kier holds pole position for highest value of work won over last 12 months
2 days ago

£800m NEPO construction framework winners

BAM, B&K, Caddick, Esh and Morgan Sindall secure places for first time
2 days ago

Manchester Uni reboots 3,300-bed campus plan

Initial £7m demolition package out to tender ahead of planning submission
2 days ago

Subcontractors wanted across Derbyshire

Register now to meet big name buyers at latest Constructionline event
2 days ago

House builder Lane End owes £12m to suppliers

Administrators probing claims by creditors about company transactions prior to failure
4 days ago

£500m Suffolk construction framework winners

Fourteen contractors and seven M&E specialists secure spots on East of England framework
3 days ago

Illegal cartel whistleblower reward raised to £250,000

Competition watchdog hikes rewards to flush out more construction bid rigging activity
3 days ago

McLaren wins £28m East London health centre job

New three-storey health centre to be built in Hornchurch
3 days ago

Balfour sells telecoms division to Obelisk

Irish infrastructure firm continues expansion plans with Balfour acquisition
4 days ago

Blackburn M65 £20m junction 5 revamp to go-ahead

Balfour Beatty to be confirmed this week to start mobilising in November for 2025 start
4 days ago

Unfit planning system means 4,700-year wait for onshore wind

Call for urgent planning reform for even a chance to meet net zero and housing ambitions
3 days ago

Commercial work boosts construction new orders

Buyers report inflation easing to its weakest for 32 months
4 days ago

Mace, T&T and Atkins secure place on MoD framework

JV wins provide technical services on £5bn defence optimisation programme
4 days ago

Enabling works start on £200m Cambridge station

Murphy starts site preparation ahead of main contractor award next month
5 days ago

Industry aims to be almost diesel-free by 2035

Big players agree first steps to eliminate diesel from most sites
4 days ago

Weston Homes plans £50m East London scheme

Land deal for 147 homes at Town Quay Wharf in Barking
4 days ago

Lee Marley Brickwork hires Countryside regional FD

Matt Sheehan joins from house builder's partnerships arm
4 days ago

Demolition deal awarded on Chancery Lane refurb

General Demolition Ltd lands demolition and enabling works package
4 days ago

Contractors no longer lagging on digital transformation

Construction shrugs-off image as late adopter of technology
4 days ago

Contractor services