Delay on new 2.0 hospital design stalls big build plan

Aaron Morby 3 years ago
Share

The Government needs to quadruple planned spending on its new hospital programme to get close to meeting already revised building plans.

Midland Metropolitan University Hospital, due to open next year, is 67% over budget
Midland Metropolitan University Hospital, due to open next year, is 67% over budget

A thorough audit of progress on the Boris Johnson Government’s commitment to build 40 new hospitals by 2030 has revealed serious flaws in progress to date.

The National Audit Office report warns the Government will miss its target by 2030 and urged NHS officials to speed up delivery of the second phase of projects.

Much of the major project element of the building programme has been loaded into 2025 starts, yet the plans to standardise design to modularise and cut costs of the next generation of hospitals has failed to materialise.

While the new 2.0 standard design for major hospitals is hoped to be completed by May next year, all major schemes seeking outline budget approval have been stalled by the design delay.

According to a new NAO report the whole programme is looking in serious ill health, due to inflation already driving up costs on smaller committed to projects and the lack of design certainty needed for accurate projected building cost savings on the next generation of larger hospitals expected to cost over £1bn each.

Auditors are calling on Government to push forward smaller schemes in the second phase due to start next year to avoid a serious logjam on the progress of the major hospital schemes being brought through in phase three.

The report warns that the four contractors singled out to deliver the programme –  ISG, Kier, Laing O’Rourke and Wates – could face serious capacity constraints if the throughput of projects is bunched.

Meg Hillier MP, Chair of the Committee of Public Accounts: “English hospitals are in poor condition, after years of underinvestment.

“Today’s NAO report shows the government’s woeful lack of progress against its commitment to build 40 new hospitals by 2030.

“It has failed to even begin construction on any of the new hospitals in its second cohort which it thought were quick wins.”

She added: “The Department of Health and Social Care has been trying to move the goalposts so it can claim it has met its target. Patients and clinicians are going to have to wait much longer than they expected before their new hospitals are completed.”

When the health department officially set out the plan in October 2020, eight hospital construction projects already underway were not included in the target. But recent government statements about building 40 new hospitals include these eight projects, referred to as “legacy hospitals”.

Also last May, the government changed the scope of the programme to include hospitals in urgent need of repairs, including five judged to be at risk of collapse because of crumbling concrete infrastructure.

New hospital programme progress and budgets


First phase – eight legacy projects


Second Phase – due to complete construction by early 2028


Phase three  –  bulk of major projects

Phase four

NAO recommendations to DHSC, NHS England and government more widely include:

  • Announcements about major capital programmes extending over more than one spending review period should fully reflect known uncertainties.
  • DHSC should choose future hospital construction projects transparently and keep full records.
  • Further bunching of construction schemes should be avoided.
  • NHP should reconsider assumptions that may result in ‘minimum viable product’ future hospitals being too small.

Gareth Davies, the head of the NAO said: “The programme has innovative plans to standardise hospital construction, delivering efficiencies and quality improvements.

“However, by the definition the government used in 2020 it will now deliver 32 rather than 40 new hospitals by 2030.

“Delivery so far has been slower than expected, both on individual schemes and in developing the Hospital 2.0 template, which has delayed programme funding decisions.

“There are some important lessons to be drawn for major programmes from the experience of the New Hospital Programme so far.

“These include strengthening the business case process to improve confidence on affordability and delivery dates, and improving transparency for key decisions.”

Latest news

McLaren seals go-ahead for £2bn York Central scheme

Phase one work to start next year when site investigation works finish
3 days ago

M&J Evans moves into new market as profits jump

Housing groundworks specialist expands into utilities sector
3 days ago

Berkeley calls for urgent stamp duty reform in Budget

London house builder wants 1% cap for first-time buyers and downsizers
3 days ago

Housing activity dives 5% in July as construction stagnates

Total new work output falls 0.4% in July as industry bumps along the bottom
3 days ago

RSK buys £61m turnover highways contractor MSF

Expanding group takes on another 175 staff in latest deal
3 days ago

OCU smashes through £1bn revenue barrier

Organic growth hits 25% as order pipeline passes £4bn
4 days ago

Higgins cleared to restart stalled Ealing estate rebuild

Firm brought on board to finish final 400 homes on Green Man estate regeneration
4 days ago

Consultant RLB cuts staff numbers

Employees left reeling by sudden round of redundancies
4 days ago

£2bn London Vauxhall Square tower trio approved

Nearly 3,000 homes, co-living units and student beds planned across seven buildings
4 days ago

Seddon replaces Vistry on £40m Salford resi scheme

Council lines up contractor switch for 144-home Ordsall project
4 days ago

Worker died under two tonnes of soil in trench collapse

Two firms fined £1.1m and contracts manager given suspended jail sentence
4 days ago

80 firms win places on £350m Fusion21 repairs framework renewal

Wates, Mears, Equans and Axis among firms named on four-year UK deal
4 days ago

Infrastructure demand helps Clancy to record results

Strong work pipeline and cash position boosts investment in training and plant
5 days ago

McGee boss Fossey takes top job at Permasteelisa

Specialist engineering chief moves to lead global façade giant
5 days ago

Torsion Construction went down owing suppliers £15m

Hundreds of subcontractors left holding unpaid invoices
5 days ago

London Mayor backs 3,000-home Beckton gasworks regeneration

Approval unlocks £250m enabling programme at east London riverside site
5 days ago

Plan lodged to turn BT Tower into 400-room hotel

Landmark retrofit will create 1,000 construction jobs and reopen tower to public
5 days ago

£1bn heatwave hit sparks resilience spending call

Civil engineers push for national review to put hard numbers on benefits of climate adaptation
5 days ago

Vistry pitches plan to unlock 30,000 homes a year

Choice-led shared ownership model would combine buyer mortgages with institutional capital
6 days ago

Contractor hunt for £50m South Wales link road

Council to start procurement for 1.2km Cynon Gateway route near Aberdare
6 days ago

Plans lodged for one of Europe’s tallest student towers

Scape's 851-bed Elephant & Castle scheme rises to 45 storeys
6 days ago

Wales housing giant to start race for £750m contractor deal

Codi Group seeks builder line-up for new homes and refurbishment pipeline
6 days ago

Conlon lands £18m Wigan SEND school

Employee-owned firm secures one of its biggest education jobs to date
6 days ago

London Square lands homes role on major Waterloo scheme

Developer picked for Royal Street scheme in planned life sciences district
6 days ago

Security patrols stepped-up to fight cable theft

Pro-active patrols on East Coast Main Line to deter thieves
6 days ago

Kier storms August contracts league with £530m haul

Thames Water job helps contractor sweep to top of monthly rankings
7 days ago

Building safety Gateway 2 applications soar as levy looms

Building Safety Regulator workload jumps by more than 100 live cases ahead of October levy
7 days ago

McLaughlin & Harvey lands £70m Holborn Circus office job

Main works to start later this year after Erith completes demolition
7 days ago

Tilbury Douglas gets green light for £30m Leeds SEND school

Firm is in line for Broomfield specialist learning centre job
7 days ago

Plans to slash paperwork for company reports

Government looks at cutting "nonsensical" corporate reporting rules
7 days ago