Planned school rebuilds won’t be bumped by RAAC projects

Aaron Morby 2 years ago
Share

Department for Education civil servants have confirmed that already committed to school building projects will not be bumped from the existing programme due to the crisis caused by crumbly concrete.

Top civil servants yesterday confirmed that 400 school projects already identified will remain in the Government’s 10-year school programme to build 500 schools.

Quizzed yesterday by watchdog MPs on the Public Accounts Committee, DfE permanent secretary Susan Acland-Hood insisted the government would not be taking named schools out of the schools rebuilding programme.

But she said that the remaining 100 places still to be allocated in the next tranche 5 of the programme would now likely be reserved for RAAC rebuilds.

The current building programme aims to rebuild 50 schools a year, although it has so far failed to meet delivery targets.

Three months ago, the National Audit Office discovered that just 24 contracts had been awarded three years into the programme, far below a target of 83 projects.

The delay was blamed on providers not taking up contracts given instability in the construction sector and inflationary risks.

Despite poor delivery so far, Jane Cunliffe, chief operating officer of the DfE’s operations and infrastructure group, said the department was confident it had capacity to build more than 50 projects through its supply chain if needed, holding out the prospect that Government could seek to step up delivery rates in the face of the school condition crisis.

She confirmed that the bulk of extra spending requirements would fall into the next spending review covering the later part of the programme.

Tranche 1, 2 and 3 projects now have fixed time tables but many of 239 projects in tranche 4 announced in December 2022 still have to finalise building start dates allowing scope for the DfE to advance RAAC rebuild projects without impacting existing timetable projects.

List of tranches 1-4 in the new schools programme, click here.

 

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
6 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
7 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
7 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
6 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
1 day ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
1 day ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
6 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
24 hours ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
1 day ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
1 day ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
1 day ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
1 day ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
1 day ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
1 day ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
1 day ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
4 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
4 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
4 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
5 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
4 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
4 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
5 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
5 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
5 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
5 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
6 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
5 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
5 days ago