New HS2 boss blasts cost-plus contracts for £6bn of overspend

Aaron Morby 3 years ago
Share

HS2’s new boss has laid the blame for massive phase 1 budget overruns on the Government’s decision to let cost-plus contracts for main civil works.

Sir Jon Thompson warns cost plus contracts will hamper efforts to control overspend
Sir Jon Thompson warns cost plus contracts will hamper efforts to control overspend

Incoming executive chairman Sir Jon Thompson said that 89% of the cost increase from 2020 till now was down to these contracts alone.

He said the decision had tied his hands preventing him from pulling levers on contractors to rein back costs.

The latest projected cost for HS2 Main Works Civils Contracts is £21.8bn to £23.4bn, a cost hike of £6.1bn.

The latest estimate at 2019 prices still does not take into recent rampant cost inflation across the industry, and the Government has now demanded a new cost estimate at today’s prices.

Sir Jon, who has been in post as executive chairman since Mark Thurston stepped down in September, criticised the procurement decision as he was cross-examined by the Public Account Committee yesterday.

He said: “We have to be upfront with you now, the Government decision to let cost-plus contracts where there are very few incentives or penalties around them does not provide me with any real levers on contractors to do better in relation to schedule and costs because they receive a marginal reduction in their fee.

“If they spend 100% more than what was agreed, they only get 1% reduction in their fee.”

“I can attempt to see if we can reset that in some way, but we are where we are.

“The decisions was made for all the right reasons, I assume back in 2019, but these contracts do not provide me with very much leverage.”

Sir Jon also warned that extra cost pressures loomed with plans to connect HS2 to the West Coast Main Line through a major redesign at the Handsacre junction, already a choke point on the route.

This would need to be expanded requiring extra land and incurring extra cost, he said.

At the same time, the PAC was told that the Department of Transport and HS2 were presently at odds about the final cost for Phase One with the DfT setting a £45bn-£54bn price range and HS2 estimating £49bn – £57bn.

HS2 is planning to tighten management controls on budgets with the appointment in January of a Chief Railway Officer for the project. The new role will to be to integrate all elements of phase one, working alongside a new chief executive replacement for Mark Thurston.

“A lessons learnt from Crossrail is you need a single controlling mind for the programme overall, rather than working through individual lines,” said Thompson.

He revealed that the present working completion date for the project was now 2030.

Latest news

Torsion Construction files administration notice

Directors at £165m-turnover construction arm battle cash flow crisis
19 hours ago

Civils firms upbeat on pipeline despite tough first quarter

Firms count on stronger workloads despite activity slide at the start of 2026
7 hours ago

OCS strikes £3.1bn deal to buy Mitie

Takeover creates £8.5bn UK-headquartered FM powerhouse
9 hours ago

5,000-home Royal Docks mega scheme set for 2028 start

Arada names professional team for landmark London waterfront scheme
10 hours ago

Kier closes in on £12bn order book after strong year

Strong second-half trading lifts order book 8%
10 hours ago

Skills cards stats show youngsters turning to construction

Significant jump in CSCS cards issued to workers under 25
10 hours ago

Green light for Derby city centre regeneration scheme

Planning approval paves way for demolition of Assembly Rooms building
10 hours ago

Muse picked to spearhead Bletchley station quarter revival

East West Rail station plan to drive town centre renewal
1 day ago

RED lands £42m Bristol and Bath office double

Firm to deliver Bristol's biggest office revamp alongside Bath HQ project
1 day ago

Severn Trent reveals timetable for £25bn deal race

Suppliers put on alert for AMP9, AMP10 and AMP11 frameworks
1 day ago

Railpen wins consent for London major office retrofit

Smithfield Market 120,000 sq ft office retrofit cleared for delivery
1 day ago

Tower Hamlets opens bidding on £31m social housing build

Former Bethnal Green coincil building to be cleared for 53 new homes block
1 day ago

Ethical Power contracting arms go into administration

Renewable energy specialist restructures
1 day ago

£33m race begins for Caerphilly bus and railway interchange

Main works to start in spring next year following a two-stage conest
1 day ago

Experts join forces for Sizewell piling works

Trio of specialists form Geotechnical Sub-Alliance at nuclear site
4 days ago

MOD maps out £26bn Project Royal Oak naval bases rebuild

Decade-long programme sets out dock, waterfront and engineering projects at Clyde, Devonport and Portsmouth
4 days ago

John F Hunt bags £20m enabling works deal at giant data centre

Site preparation contract for 41 acre site which will house ten data halls
4 days ago

Board suspends Alumasc CEO after trading update

Conduct investigation overshadows resilient year and stronger pipeline
4 days ago

Amey hires HS2 veteran to drive consulting growth

Jonathan Goring joins as executive advisor to expand consulting at home and overseas
4 days ago

Hill go-ahead for London New Era Estate rebuild

Work to start on 208-home tower block scheme in Hackney
4 days ago

Solihull backs 228-home Habiko mansion block build

Holbeche Place regeneration phase 2 signed off as Graham moves on phase 1
4 days ago

O’Rourke confirms major expansion of manufacturing capacity

Contractor doubles down on industrialised construction drive
5 days ago

Wates regional MD and director exit suddenly

Managing Director David Wingfield and Commercial Director Kyle McGrory have left the company with immediate effect
5 days ago

South Wales roads bodies launch £270m highways framework

Six-year framework covers highways, bridges and surfacing work
5 days ago

Construction output falls for second month

New build activity gains wiped out by housing RMI slump
5 days ago

Crest sinks to £35m loss as lender talks drag on

Net debt doubles to £142m as house builder extends covenant waiver
5 days ago

Plan for triple-tower Stratford scheme on former Sphere site

Hallmark reveals 47-storey cluster to unlock long-vacant Olympics site
5 days ago

SIG set for cost-cutting drive as materials market stalls

At least £100m target for efficiency improvements
5 days ago

Barratt claws back £38m from subcontractors in legacy job claims

House builder to double building safety spend to £300m this year
6 days ago

Chief executive Mark Lawrence leaves TClarke

CEO leaves with immediate effect after 40 years at the busines
1 week ago