HS2 gears up to let £5bn of contracts this year

Aaron Morby 1 year ago
Share

HS2 procurement chiefs are gearing up for a pivotal 12-months of contract awards as the project also hits peak construction in 2024.

Big contract awards for rails systems this year ahead of 2026 start when main civils draws to a close
Big contract awards for rails systems this year ahead of 2026 start when main civils draws to a close

Around £5bn-worth of contracts will be let to oversee building of the tracks, power, signalling, overhead lines and the railway’s landmark network control centre.

Major milestones coming up early this year include the start of work on Birmingham’s new Curzon Street station and breakthrough of the first TBM being used to bore the Chilterns tunnel – the longest on the route at 10 miles.

Eleven contracts are already out to tender and are expected to be awarded in 2024, unlocking more opportunities for the UK’s construction, engineering and rail sector.

Planned Calvert infrastructure maintenance depot

Three contracts will be for the design, logistics and installation of the track system – as well as a maintenance depot at Calvert in Buckinghamshire – that will carry HS2 services at speeds of up to 225mph.

Another will cover the high-tech signalling system that feeds information directly into the cab – as an alternative to lineside signals – allowing for faster and more frequent services to maximise space on the line.

A further contract will be awarded for the high-voltage power system used by the line, delivering zero-carbon electricity from the National Grid.

Planned Washwood Heath HS2 control centre

Another winning bidder will be selected to construct HS2’s £275m ‘nerve centre’ at Washwood Heath, Birmingham.

Vinci/Keltbray is up against and VolkerFitzpatrick/VolkerRail for the single-stage design and build contract for the 30-hectare site housing the project’s rolling stock maintenance depot and network control centre.

Physical construction of many parts of HS2’s rail system along the route is expected to begin from 2026/7 when main civil engineering work reaches its conclusion.

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
5 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 hours ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
14 hours ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
12 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
12 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
19 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
2 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
20 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
20 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
20 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
20 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
1 day ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
7 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
6 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
6 days ago

Contractor services