HS2 gears up to let £5bn of contracts this year

Aaron Morby 2 years ago
Share

HS2 procurement chiefs are gearing up for a pivotal 12-months of contract awards as the project also hits peak construction in 2024.

Big contract awards for rails systems this year ahead of 2026 start when main civils draws to a close
Big contract awards for rails systems this year ahead of 2026 start when main civils draws to a close

Around £5bn-worth of contracts will be let to oversee building of the tracks, power, signalling, overhead lines and the railway’s landmark network control centre.

Major milestones coming up early this year include the start of work on Birmingham’s new Curzon Street station and breakthrough of the first TBM being used to bore the Chilterns tunnel – the longest on the route at 10 miles.

Eleven contracts are already out to tender and are expected to be awarded in 2024, unlocking more opportunities for the UK’s construction, engineering and rail sector.

Planned Calvert infrastructure maintenance depot

Three contracts will be for the design, logistics and installation of the track system – as well as a maintenance depot at Calvert in Buckinghamshire – that will carry HS2 services at speeds of up to 225mph.

Another will cover the high-tech signalling system that feeds information directly into the cab – as an alternative to lineside signals – allowing for faster and more frequent services to maximise space on the line.

A further contract will be awarded for the high-voltage power system used by the line, delivering zero-carbon electricity from the National Grid.

Planned Washwood Heath HS2 control centre

Another winning bidder will be selected to construct HS2’s £275m ‘nerve centre’ at Washwood Heath, Birmingham.

Vinci/Keltbray is up against and VolkerFitzpatrick/VolkerRail for the single-stage design and build contract for the 30-hectare site housing the project’s rolling stock maintenance depot and network control centre.

Physical construction of many parts of HS2’s rail system along the route is expected to begin from 2026/7 when main civil engineering work reaches its conclusion.

Latest news

Steel fixer crushed by blockwork wall collapse

Contractor fined £100,000 after worker suffers life-changing injuries
2 hours ago

Conlon Chairman to retire after 38 years

Michael Conlon to hand over reigns to Guy Parker at Employee Owned Company
4 hours ago

Yorkshire brickmaker saved in last-minute rescue deal

Private equity deal saves 20 jobs at York Handmade
2 hours ago

HS2 first as giant bridge slid across live motorway

Watch timelapse footage of pioneering 4,600-tonne viaduct installation
7 hours ago

Gilbert Ash breaks ground on £120m Wilde aparthotel

Staycity’s biggest London scheme gets underway in Shoreditch
7 hours ago

Bennett wins brace of retirement home deals

Contractor to build more than 200 apartments for investor Octopus Capital
8 hours ago

Developer showed “total disregard” for site safety

Property firm fined £45,000 for failing to meet basic standards
8 hours ago

Watkin Jones takes £8.7m hit but eyes brighter 2026

A £2bn pipeline and stronger deal flow help rebuild confidence after a year of impairments
8 hours ago

Project manager caught running false invoice scam

Suspended sentence and ban for director after probe into offices to resi scheme
1 day ago

Cardo nails £52m Sussex council homes roofing deal

Firm beats 14 rivals to take Lewes and Eastbourne roofing programmes
1 day ago

Bachy turnover sinks by over £100m as HS2 surge fades

Piling specialist reports slow year as mega projects step down
1 day ago

Van Elle finds buyer for loss-making Canadian arm

Two-year North America foray ends with £2.6m exit deal
1 day ago

£100m student halls to replace derelict London Crown Court

IQ student project gets go-ahead at Blackfriars court building site
1 day ago

Safety green light for Newcastle student scheme

Gateway 2 approval process delays construction start by a year
1 day ago

Plans go in for next phase of Manchester Waters

New neighbourhood planned for island site
1 day ago

JRL names new fit-out lead to drive expansion

Graham Ardley steps up to drive next phase of commercial and residential growth
1 day ago

Construction output yo-yos as growth falters again

Quarterly output down 0.3% amid cautious investor sentiment
4 days ago

Free school build plans axed to fund £3bn SEND expansion

Education secretary scraps 28 free schools to plug SEND shortfall
4 days ago

McLaren seals £160m funding for Manchester student tower

737-bed Upper Brook Street student scheme forward funded by L&G
4 days ago

Former McAlpine boss lined up for Royal BAM board role

Paul Hamer to replace Paul Sheffield on Dutch group supervisory board
5 days ago

Plans go in for £650m retail park to resi scheme

Construction could start in early 2027 on new neighbourhood for Lewisham
5 days ago

Lovell launches Midlands refurb division

Renew Central to be headed by Carl Yale
4 days ago

M Group muscles into top five contractors after growth spurt

Private-equity backed infra giant builds £8.8bn work mountain
5 days ago

Plans in for first major build phase of £2bn York Central scheme

Developers table plans for nearly 1,000 homes, parkland and York’s new western station gateway
5 days ago

Lords push for staged Gateway 2 approval to aid design and build

Inquiry warns BSR’s over-detailed Gateway 2 demands are freezing D&B process
6 days ago

CITB wage bill tops £52m as staff numbers jump 13%

Accounts show 182 people at training body earn £60,000+ a year
5 days ago

Peterborough electrical specialist files administration notice

EML Electrical Contractors lodges court notice
5 days ago

Ant Yapi UK lands latest Chelsea Barracks deal

Fit-out work on Building 7 will last until summer 2027
5 days ago

Go-ahead for plan to level Cambridge retail park for life-science hub

Minister overturns council refusal as Railpen’s scheme promises £600m economic uplift
6 days ago

Subcontractor competition keeps build costs flat at Berkeley

"Highly competitive tendering" expected to continue next year
6 days ago