Government told to stop dithering over HS2 Euston tunnel start date

Aaron Morby 1 year ago
Share

Spending watchdog MPs have called on the Government to urgently take a decision on the start date for the last remaining phase one tunnel drive to Euston station.

In a highly critical report published this morning, the Public Accounts Committee warned that there are still huge uncertainties over key areas of the project that threatened to continue to see costs soar.

The MPs said that the decision to axe the second phase of HS2 meant the project now offers very poor value for money to the taxpayer, and the Department and HS2 Ltd could not set out what the final benefits of the project would be.

The report warns that the Department of Transport must take a decision soon on funding the tunnelling from Old Oak Common to Euston to avoid incurring much greater costs from stopping and restarting work. 

It also raised concerns that the Government has failed to set out a plausible proposal on how its expects to attract private sector investment to deliver Euston station and the final tunnel drive from Old Oak Common.

The Government has redirected £6.5bn of expenditure away from Euston, and the Department of Transport is now looking for private funding to cover the costs of the re-scoped Euston station and the over-site development.

It recommended the Government must develop plans for a range of private investment scenarios, including different levels of public finance, as part of its consideration of how to progress with the station at Euston.

Dame Meg Hillier MP, Chair of the Committee, said: “The decision to cancel HS2’s Northern leg was a watershed moment that raises urgent and unanswered questions, laid out in our report.

“HS2 is the biggest ticket item by value on the Government’s books for infrastructure projects.

“As such, it was crying out for a steady hand at the tiller from the start.

“But, here we are after over a decade of our warnings on HS2’s management and spiralling costs – locked into the costly completion of a curtailed rump of a project and many unanswered questions and risks still attached to delivery of even this curtailed project.”

The MPs are also concerned about the uncertainty of the cost impact on the final project bill of the complex challenge of connecting HS2 to the West Coast Mainline.

A spokesperson for HS2 Ltd said: “We’ve been clear about our cost challenges, which have been compounded by significant levels of inflation.

“HS2 Ltd is now under new leadership and implementing changes across the programme aimed at controlling costs and learning the lessons of the past.”

 

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
5 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 hours ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
14 hours ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
12 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
12 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
19 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
2 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
20 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
20 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
20 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
20 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
1 day ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
7 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
6 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
6 days ago

Contractor services