Government told to stop dithering over HS2 Euston tunnel start date

Aaron Morby 3 months ago
Share

Spending watchdog MPs have called on the Government to urgently take a decision on the start date for the last remaining phase one tunnel drive to Euston station.

In a highly critical report published this morning, the Public Accounts Committee warned that there are still huge uncertainties over key areas of the project that threatened to continue to see costs soar.

The MPs said that the decision to axe the second phase of HS2 meant the project now offers very poor value for money to the taxpayer, and the Department and HS2 Ltd could not set out what the final benefits of the project would be.

The report warns that the Department of Transport must take a decision soon on funding the tunnelling from Old Oak Common to Euston to avoid incurring much greater costs from stopping and restarting work. 

It also raised concerns that the Government has failed to set out a plausible proposal on how its expects to attract private sector investment to deliver Euston station and the final tunnel drive from Old Oak Common.

The Government has redirected £6.5bn of expenditure away from Euston, and the Department of Transport is now looking for private funding to cover the costs of the re-scoped Euston station and the over-site development.

It recommended the Government must develop plans for a range of private investment scenarios, including different levels of public finance, as part of its consideration of how to progress with the station at Euston.

Dame Meg Hillier MP, Chair of the Committee, said: “The decision to cancel HS2’s Northern leg was a watershed moment that raises urgent and unanswered questions, laid out in our report.

“HS2 is the biggest ticket item by value on the Government’s books for infrastructure projects.

“As such, it was crying out for a steady hand at the tiller from the start.

“But, here we are after over a decade of our warnings on HS2’s management and spiralling costs – locked into the costly completion of a curtailed rump of a project and many unanswered questions and risks still attached to delivery of even this curtailed project.”

The MPs are also concerned about the uncertainty of the cost impact on the final project bill of the complex challenge of connecting HS2 to the West Coast Mainline.

A spokesperson for HS2 Ltd said: “We’ve been clear about our cost challenges, which have been compounded by significant levels of inflation.

“HS2 Ltd is now under new leadership and implementing changes across the programme aimed at controlling costs and learning the lessons of the past.”

 

Latest news

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
2 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
2 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
2 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
2 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
2 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
2 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
2 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
3 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
3 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
3 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
3 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
3 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
3 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
4 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
4 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
4 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
4 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
4 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
5 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
5 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
5 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
5 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
5 days ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
5 days ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
5 days ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
5 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
6 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
6 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
6 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
6 days ago

Contractor services