Regulator opens probe into National Highways delivery

Aaron Morby 11 months ago
Share

The Office of Rail and Road has opened an investigation into National Highways and its delivery of schemes after a concerning performance dip.

The roads and rail regulator said the investigation, which will run to April, would focus on the root causes of the current under performance and whether the second road investment strategy can be delivered as planned.

It said the formal investigation was being launched with 13 months remaining on RIS2 to allow time for corrective action to be taken before the end of the road period, should it be necessary.

National Highways has been hit by project start delays and soaring cost of delivery on projects.

As well as concerns about road delivery, it is understood industry whistleblowers have approached the regulator about irregular activities in subcontract awarding practices on some projects.

Feras Alshaker, director of planning and performance at ORR, said: “National Highways has generally delivered well for road users, but in recent months we have become concerned that its performance has dipped in a number of areas and issues are recurring.

“We are opening an investigation now to help ORR and National Highways achieve a common understanding of what is causing the current dip in performance, and whether it is still reasonable for us to expect the levels of performance set out in the second Road Investment Strategy.”

The ORR said it would also scrutinise whether National Highways has the right processes in place to deliver its agreed commitments by the end of the road investment period in March 2025.

The regulator first raise concerns in its annual assessment of National Highways’ performance, published in July 2023. It said then that it had identified a number of potential risks, such as delivery of its capital portfolio and asset management strategy.

At the time, ORR pointed out that with a more back-end loaded programme of work, the impact of future inflation and any further delays to construction of major enhancements would pose a risk to meeting National Highways’ forecasted efficiencies of £2.22bn needed to deliver the RIS 2 on budget.

Since then, ORR said those risks have materialised, and performance has dipped across several areas.

Last year plans to build a new road linking the M6 with south Lancaster were shelved due to soaring cost pressures.

The green light for the £1.3bn A66 Northern Trans-Pennine upgrade project has also been delayed with the Government putting off a decision on whether to grant development consent until early March.

Latest news

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
11 hours ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
11 hours ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
11 hours ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
1 day ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
10 hours ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
10 hours ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
1 day ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
1 day ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
1 day ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
2 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
1 day ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
2 days ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
1 day ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
2 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
5 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
2 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
6 days ago

Hercules to offload suction excavator arm

Fleet of 30 trucks generates around £5m revenue a year
2 days ago

Tarmac trials new technique to cut concrete road noise

Quieter trips for drivers and longer-lasting roads
2 days ago

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 week ago

Solar panel installer fined £120,000 after roof fall

Court hears how employee broke his leg in fall
6 days ago

Network Rail chief Andrew Haines knighted

Thin pickings for construction in this year's New Year Honours
1 week ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 weeks ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 weeks ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
3 weeks ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
3 weeks ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
3 weeks ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
3 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
3 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
3 weeks ago

Contractor services