Regulator opens probe into National Highways delivery

Aaron Morby 2 years ago
Share

The Office of Rail and Road has opened an investigation into National Highways and its delivery of schemes after a concerning performance dip.

The roads and rail regulator said the investigation, which will run to April, would focus on the root causes of the current under performance and whether the second road investment strategy can be delivered as planned.

It said the formal investigation was being launched with 13 months remaining on RIS2 to allow time for corrective action to be taken before the end of the road period, should it be necessary.

National Highways has been hit by project start delays and soaring cost of delivery on projects.

As well as concerns about road delivery, it is understood industry whistleblowers have approached the regulator about irregular activities in subcontract awarding practices on some projects.

Feras Alshaker, director of planning and performance at ORR, said: “National Highways has generally delivered well for road users, but in recent months we have become concerned that its performance has dipped in a number of areas and issues are recurring.

“We are opening an investigation now to help ORR and National Highways achieve a common understanding of what is causing the current dip in performance, and whether it is still reasonable for us to expect the levels of performance set out in the second Road Investment Strategy.”

The ORR said it would also scrutinise whether National Highways has the right processes in place to deliver its agreed commitments by the end of the road investment period in March 2025.

The regulator first raise concerns in its annual assessment of National Highways’ performance, published in July 2023. It said then that it had identified a number of potential risks, such as delivery of its capital portfolio and asset management strategy.

At the time, ORR pointed out that with a more back-end loaded programme of work, the impact of future inflation and any further delays to construction of major enhancements would pose a risk to meeting National Highways’ forecasted efficiencies of £2.22bn needed to deliver the RIS 2 on budget.

Since then, ORR said those risks have materialised, and performance has dipped across several areas.

Last year plans to build a new road linking the M6 with south Lancaster were shelved due to soaring cost pressures.

The green light for the £1.3bn A66 Northern Trans-Pennine upgrade project has also been delayed with the Government putting off a decision on whether to grant development consent until early March.

Latest news

Cheshire M&E specialist Gilks files administration notice

Management tells staff firm will close days before salaries due to be paid
20 hours ago

Severfield facing strike action next week

Industrial action to hit Bolton factory
2 days ago

Jackson wins race for £22m East Sussex bridge

Construction set-to start on Exceat Bridge replacement
21 hours ago

Plans ramp-up for Wythenshawe £500m town centre revamp

Food hall latest phase of Manchester regen
20 hours ago

Kier set to bag £35m Bristol station car park job

Seven-storey MSCP will free up land for homes at Bristol Temple Meads
21 hours ago

Leeds £1bn Eastgate Quarter vision moves up a gear

Consultant team assembled for Leeds’ last big city centre site
2 days ago

Morgan Sindall eyes bumper 2026 on record workload

High-flying fit-out arm triggers another profit upgrade
2 days ago

Funding agreed for £220m Paddington overstation job

Mace lined-up to start main construction works next month
2 days ago

Salford set for record £525m wastewater reset

United Utilities alliance firms gear up to deliver twin wastewater works upgrades
2 days ago

Construction grew 1.8% last year despite sharp Q4 fall

Private housing slump behind 2.1% output fall in final quarter
2 days ago

Firms fined after two killed when MEWP overturns

Tragedy during testing of warehouse racking system
2 days ago

Hill bags £45m Kent high-rise flats job

Firm beats rival Higgins and Lovell to Springfield Library redevelopment
2 days ago

Willmott Dixon gets start date for £43m Kent leisure job

Spring start for Gravesend Cascades Leisure Centre
2 days ago

D-Day for £37bn NHS hospital framework

Winners due to be announced imminently for mega deal
3 days ago

Severfield hires ex-ISG finance chief to steer turnaround

New CFO Andrew Page joins at “pivotal time” for steel specialist
3 days ago

Barratt Redrow £1bn safety upgrade works shift up a gear

Nearly 200 blocks now at tender or on site as remediation spend tops £73m in half year
3 days ago

Green light for Liverpool Street Station revamp

Plans approved to upgrade Britain's busiest station
3 days ago

Two arrested after 999 construction fly-tipping call

Rogue waste dumpers caught after lorry gets stuck in field
3 days ago

Barhale secures hat-trick of Thames Water sewer schemes

Firm bags Brent Cross, Benson and Basingstoke development-led sewer upgrades
4 days ago

Skanska seals £273m delayed Broadgate office overhaul

Retained frame and six-storey extension to transform One Appold Street
4 days ago

JRL lands £68m North London housing tower job

Long-stalled Brent 30-floor housing block job moves into delivery
4 days ago

School building winners to give apprentice guarantees

Contractors called on to create 13,000 new training places
4 days ago

DfT tests market for privately financed HS2 Euston station job

Market engagement opens on design, build, finance and maintain deal
5 days ago

Muse go-ahead for 1,600-home Solihull town centre reset

Demolition to start for Mell Square transformation
4 days ago

Subcontractors wanted across the Midlands

Work available at latest Constructionline event
4 days ago

Robertson Construction bounces back into the black

Contractor shakes off previous £13m loss year with £31m profit comeback
5 days ago

Glencar tipped for latest London data centre

Contractor to build next phase of £1bn Brent Cross campus
5 days ago

Muse to lead redevelopment of Wakefield shopping centre

Council moves to demolish The Ridings for 1,000-home quarter
5 days ago

Long-empty Southend HMRC tower set for 557-flat rebirth

Section 106 agreement paves way for construction start
5 days ago

RED starts revamp of Lincoln’s Inn Fields

First phase of refurbishment work at historic London site
5 days ago