Soaring costs at London incinerator job force M&E rethink

Aaron Morby 1 year ago
Share

Spanish contractor Acciona’s massive incinerator project in North London has been hit by spiraling costs and delays.

Civils work packages have largely completed at the Edmonton energy from waste incinerator project
Civils work packages have largely completed at the Edmonton energy from waste incinerator project

The Energy Recovery Facility forms part of the wider North London Heat and Power Project in Edmonton where costs have soared from £1.2bn to £1.5bn, due to construction material and wage inflation.

The EFR project is now at a critical stage with steelworks due to start shortly and main M&E works to follow.

But supply chain problems have forced Acciona to rethink its procurement strategy for the critical M&E stage of works.

Client body, the North London Waste Authority, representing seven councils, has revealed that the project originally due to be commissioned in 2025 will now be completed in 2027.

While civils works have proceeded well, officials from NWLA are concerned the M&E phase works could hit out-turn costs further.

The programme director for NWLA revealed Acciona has faced problem securing and mobilising subcontractors for the mechanical and electrical sections of the ERF build.

He added that the contractor was reviewing its approach to packaging tasks, to respond to feedback from potential subcontractors. The NWLA is now demanding a ‘realistic schedule and delivery plan.’

He said: “Acciona have identified issues in their delivery of the next stages of the design, procurement, and construction of the ERF facility, namely the mechanical and electrical sections of the build, in what is a challenging period for the construction industry.

“Officers are in regular discussions with Acciona to understand both how on-site momentum can be restored and how future delays can be minimised.

“Acciona are considering as part of this revising their approach to packaging work to generate increased interest from the potential supply chain.”

He added: “Our contract with Acciona provides that delays in the programme are their risk, and they may be liable to pay damages if the new facility is not delivered on time.

“However, it is not in the Authority’s interest to be working with a contractor facing significant financial challenges.”

The value of work completed so far has hit £790m with a Resource Recovery Facility to receive and transfer  waste and EcoPark House visitor centre completed on budget.

The remaining cost to complete is forecast at £730m.

The programme director said: “Until officers are satisfied of the robustness of Acciona’ s schedule and delivery plan, caution must be applied to the certainty of the costs and contingency, although the figures above represent current best estimates.”

 

Latest news

Go-ahead for £44m Oxford science park expansion

Oxford site set for five new lab and tech buildings after council approval
55 seconds ago

Cladding firm sunk by BSR delays

Essex based aluminium cladding specialist hit by hold-ups
13 minutes ago

Spencer Group stays on growth track despite £5m impairment

Strong pipeline and £83m work in hand set platform for another big year
29 minutes ago

Gratte Brothers expands across North of England

M&E specialist has eyes on more data centre work
11 minutes ago

Contractors courted for £1.7bn London DLR extension job

Firms urged to register for Thamesmead extension talks next month
3 days ago

Multiplex scales contracts league with London tower job

£400m city Dovetail Building deal tops October ranking
3 days ago

Vidi Construction went down owing £6m to subbies

Failure of main client sunk Coventry contractor
3 days ago

J&D Pierce founder hands reins to new MD duo

Joint managing directors named as Derek Pierce moves up to chairman role
3 days ago

Willmott Dixon plugs fire safety gap for CLT builds

First certified fire tests pave way for cross laminate timber builds
3 days ago

Green light for new £1.3bn neighbourhood in Salford

Ten resi towers to be built alongside 15 retail units
4 days ago

Buyers report fastest activity decline in five years

Construction hopes for better New Year
4 days ago

Ten high-rise schemes in limbo after building control firm folds

BSR pledges to reallocate cases and keep Gateway 2 clear-up on track.
4 days ago

Vistry sees demand start to return for new social housing

New build demand from housing associations rises as Government support starts to kick-in
4 days ago

Travis Perkins suppliers stunned as payment times increase

Builder's merchant giant could now take nearly three months to pay bills
4 days ago

Costain natural resources boss heads to Mitie

Sam White joins Mitie to lead 16,000-strong Technical Services arm
4 days ago

Willmott Dixon gets green light for Kirkby school rebuild

Contractor to start phased construction schedule at Nottinghamshire site
4 days ago

£60m homes plan for Sheffield city centre scrubland

Capital&Centric pushes ahead with 192-home Fitzwilliam project
4 days ago

Sizewell C financial close unlocks full-scale construction

13-bank consortium backs £5.5bn debt finance to launch full build phase in Suffolk
6 days ago

SDM Fabrications files administration notice

East Anglian steelwork contractor lodges court notice
5 days ago

Winners of £1.6bn social housing decarbonisation deal

Procure Plus awards huge retrofit and renewables framework
5 days ago

Stepnell hires Vinci development chief for Midlands push

Graham Lambert joins as regional director to drive growth
5 days ago

First data centre plans at Blackpool’s Silicon Sands site

Development aims to turn Fylde Coast into hub for digital innovation
5 days ago

Race starts for £1.5bn LHC building framework

Lower barriers and regional focus aim to draw SMEs in for PB4 deal
5 days ago

Social housing workers suffer at hands of vibrating tools

Nottingham City Homes prosecuted after builders exposed to risks
5 days ago

Building control giant Assent ceases trading

Shockwaves to hit Building Safety Regulator approval process
6 days ago

McLaren Living signs deal for £250m Reading regen

Minster Quarter to deliver 600 homes and new civic square
6 days ago

London ready-mix sales dive 32% amid housing slump

Building Safety Regulator bottlenecks blamed for steepest regional fall in the country
6 days ago

£200m plan lodged to transform Huyton town centre

Genr8 Kajima advances council HQ, hotel and 72 flats scheme
7 days ago

Luxury London developer acquires £180m Stanmore site

North west London site bought from Notting Hill Genesis
6 days ago

McAleer & Rushe wins £30m Tottenham student living job

287-room student room Printworks scheme to be built near Spurs Stadium
7 days ago