Developer told to stop building in affordable housing row

Grant Prior 1 year ago
Share

A High Court judge has served an interim injunction on a developer stopping them from building or selling more homes on a major site in a row over affordable housing.

Bolsover District Council took Arba Ground Trading Company to court over a disputed development in a Derbyshire village.

The Hawthorne Meadows scheme in Barlborough was granted planning permission in March 2011 with the s106 condition that 10% of the homes on the site be affordable housing.

The council claimed 126 houses have currently been built and sold for £31m, leaving nine left to be built, which meant Arba could not meet the affordable housing target.

His Honour Judge Tindal presided over the case in the High Court in Birmingham and stated that “a party who made promises under a s106 and then breaks those promises can expect themselves to be made subject to an injunction”.

HHJ Tindal issued an interim injunction on the developer that prohibits them from building or selling/leasing any more properties.

The case has been adjourned because the developer has appealed a February 2024 decision refusing to vary the s106 agreement to reduce their obligations. Once the appeal process is complete the matter will be returned to the High Court.

Cabinet Member for Governance, Councillor Duncan McGregor said, “We faced the real risk that the development would be completed, sold and occupied without the monies being paid and other obligations being met.

“Nothing which has occurred over the last three years gives us any confidence that the obligations would be promptly and fully complied with, that’s why we sought court action.

“But let this be a warning to developers. We issue planning permission on the proviso that its conditions are met. If they are not, then we will take legal action against those responsible.”

Latest news

Former facade boss Lee Marks joins Skanska

Experienced exec has has stints at Permasteelisa, NG Bailey, Laing O'Rourke and nmcn
19 hours ago

Mace and Arup land roles for UK’s first small modular reactor

Team named for early engineering and programme strategy for Anglesey reactor
16 hours ago

Green light for Sheffield Cole Brother store revival

Grade II listed department store set for comeback as leisure and office hub
16 hours ago

Morgan Sindall starts delayed £29m Newcastle leisure centre

Ground broken on West Denton scheme six years after old pool closed
15 hours ago

UK’s biggest AI data centre plan approved

North Lincolnshire scheme to cost £7.5bn to build
24 hours ago

Vistry boss buys £893k shares after stock slide

Outgoing chief Greg Fitzgerald snaps up shares after brutal market sell-off
23 hours ago

CITB accused of cutting cash for small contractors

More changes to how training body hands levy funds back to contractors
23 hours ago

£25m Dartford town centre housing job heads for tender

Council pushes ahead with former Co-op site 69 home redevelopment
24 hours ago

Galliford back in affordable housing with £28m Chester job

Contractor returns to partnership housing after 6-year break
2 days ago

Morgan Sindall submits Crystal Palace refurb plans

Major revamp unveiled for iconic south London sports centre
24 hours ago

Data centre sites to jump queue for grid connections

Consultation starts on what schemes get priority for power
2 days ago

Balfour Beatty construction margin hits 3.5%

Power generation projects drive record order book to nearly £23bn
2 days ago

Plans unveiled for 70-storey Liverpool tower

Liverpool's tallest building will rise to 727ft
3 days ago

Birmingham sets out high-rise city centre vision

5,000 homes and major commercial quarter planned around HS2 station
2 days ago

Forterra ‘insulated’ from Iran war gas price shocks

Materials giant has short-term energy supplies secured
2 days ago

Keepmoat and Cussins to complete £200m South Shields site

Construction starts on final phase of Holborn regeneration
2 days ago

FRC probes accountants over Vistry South division reporting

Accounting watchdog probes conduct of two former Vistry employees after profit warnings
3 days ago

Costain builds record £7bn order book as profit jumps a third

Stronger margins and cash generation offset lower revenue as transport slows
3 days ago

Bid race starts for £3bn West Midlands framework

Firms fight for 20 spots on third generation building framework
3 days ago

North East Mayor to pump cash into arena and film studio jobs

Kick-start funding for Sunderland film studios and Gateshead arena schemes
3 days ago

Persimmon brick factory working 24/7 to meet demand

In-house materials investment helps boost profits
3 days ago

Two firms and site manager fined after asbestos blunders

HSE steps-in at demolition site riddled with asbestos
3 days ago

Market sounding starts on £46m Mid Wales school

Bids to be invited at end of May for for new Ysgol Bro Hyddgen campus
3 days ago

£150m Cambridge to Cambourne busway job heads for tender

Construction is expected to start in early 2027
4 days ago

Manchester city council JV to build 1,600 homes

Pension fund backs city housing push on seven sites
5 days ago

Graham set for £100m Cardiff Crossrail phase one

City council to rubberstamp deal this month for Summer start
5 days ago

Go-ahead for 2,300-home scheme at former GSK London HQ

Reuse-first strategy to save 34,500 tonnes of embodied carbon in construction phases
5 days ago

Muse gets green light for office-to-apartments conversion

Latest stage of £500m regeneration of Wythenshawe.
4 days ago

Habiko submits first 240-home scheme in Warrington

PIC, Muse and Homes England partnership lodges plans for twin affordable housing blocks
7 days ago