ISG administrator finds just £35m to pay down £1.1bn debt

Aaron Morby 5 months ago
Share

ISG administrators have warned they will only recover £35m from cash and assets out of the rubble left behind from the collapse of the £2.2bn turnover contractor.

It means there will be no cash for trade contractors owed at least £308m.

The group is now confirmed to have sunk with total debts of £1.1bn, much of this from complex intercompany debt, cash owed to trade creditors and more than £100m owed in tax.

A new report from administrator EY reveals the firm was about to report a staggering £148m in contract writedowns in overdue accounts for 2023 that recorded a £133m pre-tax loss.

Administrators have also given an official account of the chain of events that started to see the top five contractor teeter and finally sink into administration.

They reveal that as far back as 2020, ISG trading and cash performance was being impacted by large loss-making contracts in high-rise residential projects where significant additional time and higher costs were required to deliver.

The firm was also rocked by the cancellation of a £600m Hollywood Sunset Studio job and the termination of a £300m gigafactory contract for British Volt.

By late 2023 with over £100m in dispute on its projects, ISG found it was struggling to obtain performance bonds and found clients demanding cash-backed bonds for projects squeezing cashflow even further.

In October last year a winding up petition from a subcontractor owed £70,000 spooked the insurance market despite being paid straightaway.

This petition prompted a credit insurer to remove cover for multiple suppliers stoking wider concern about ISG’s financial stability.

Around this time, dwindling cash reserves forced ISG to seek extended terms to pay a £60m VAT bill hanging over it.

By January 2024, the situation had deteriorated further and ISG decided it would have to sell its profitable fit-out business or secure a cash injection from its US owner Cathexis.

Accountant EY was engaged to approach potential buyers worldwide and secured interest from 11 private equity and trade buyers.

But this sale process was halted when ISG received an offer for the group from Antipodean Holdings, led by South African entrepreneur Andre Redinger.

By July this year, the legal documentation for the deal was at an advanced stage, but Antipodean then informed Cathexis it was encountering difficulties in transferring funds from South Africa into the UK, citing regulatory approvals in South Africa and banking process-related delays.

On 2 September Antipodean dropped its offer to just £1 but maintained its commitment to fund working capital needs.

Cathexis accepted the reduced offer as the only solvent outcome for creditors and requested evidence that Antipodean had the necessary funds.

Due to lack of progress, ISG’s board halted talks with Antipodean and decided to reopen talks with one of the most interested buyers for ISG Fit Out.

After accelerated talks, this buyer dropped out because of concern about whether critical contracts could be novated.

Other firms were hastily approached but no potential buyer could be found within the tight time frame.  A main sticking point was unpaid group VAT for which ISG Fit Out was jointly and severally liable.

At the same time, Cathexis confirmed its own refinancing process would fail to release necessary funding in the near term. With nowhere to turn ISG directors decided to appoint administrator EY on 20 September.

At the time of the collapse there were 100 live construction sites and 500 live fit out and retail sites being worked on.

 

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
6 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
5 hours ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
14 hours ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
13 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
12 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
20 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
2 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
20 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
21 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
21 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
21 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
1 day ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
7 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
6 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
6 days ago

Contractor services