ISG administrator finds just £35m to pay down £1.1bn debt

Aaron Morby 1 year ago
Share

ISG administrators have warned they will only recover £35m from cash and assets out of the rubble left behind from the collapse of the £2.2bn turnover contractor.

It means there will be no cash for trade contractors owed at least £308m.

The group is now confirmed to have sunk with total debts of £1.1bn, much of this from complex intercompany debt, cash owed to trade creditors and more than £100m owed in tax.

A new report from administrator EY reveals the firm was about to report a staggering £148m in contract writedowns in overdue accounts for 2023 that recorded a £133m pre-tax loss.

Administrators have also given an official account of the chain of events that started to see the top five contractor teeter and finally sink into administration.

They reveal that as far back as 2020, ISG trading and cash performance was being impacted by large loss-making contracts in high-rise residential projects where significant additional time and higher costs were required to deliver.

The firm was also rocked by the cancellation of a £600m Hollywood Sunset Studio job and the termination of a £300m gigafactory contract for British Volt.

By late 2023 with over £100m in dispute on its projects, ISG found it was struggling to obtain performance bonds and found clients demanding cash-backed bonds for projects squeezing cashflow even further.

In October last year a winding up petition from a subcontractor owed £70,000 spooked the insurance market despite being paid straightaway.

This petition prompted a credit insurer to remove cover for multiple suppliers stoking wider concern about ISG’s financial stability.

Around this time, dwindling cash reserves forced ISG to seek extended terms to pay a £60m VAT bill hanging over it.

By January 2024, the situation had deteriorated further and ISG decided it would have to sell its profitable fit-out business or secure a cash injection from its US owner Cathexis.

Accountant EY was engaged to approach potential buyers worldwide and secured interest from 11 private equity and trade buyers.

But this sale process was halted when ISG received an offer for the group from Antipodean Holdings, led by South African entrepreneur Andre Redinger.

By July this year, the legal documentation for the deal was at an advanced stage, but Antipodean then informed Cathexis it was encountering difficulties in transferring funds from South Africa into the UK, citing regulatory approvals in South Africa and banking process-related delays.

On 2 September Antipodean dropped its offer to just £1 but maintained its commitment to fund working capital needs.

Cathexis accepted the reduced offer as the only solvent outcome for creditors and requested evidence that Antipodean had the necessary funds.

Due to lack of progress, ISG’s board halted talks with Antipodean and decided to reopen talks with one of the most interested buyers for ISG Fit Out.

After accelerated talks, this buyer dropped out because of concern about whether critical contracts could be novated.

Other firms were hastily approached but no potential buyer could be found within the tight time frame.  A main sticking point was unpaid group VAT for which ISG Fit Out was jointly and severally liable.

At the same time, Cathexis confirmed its own refinancing process would fail to release necessary funding in the near term. With nowhere to turn ISG directors decided to appoint administrator EY on 20 September.

At the time of the collapse there were 100 live construction sites and 500 live fit out and retail sites being worked on.

 

Latest news

Tower crane collapses in London

Site photos show aftermath of failure
13 hours ago

Housing drags down fledgling construction recovery

Buyers report return to accelerated downturn but still hopeful for year ahead
11 hours ago

Taylor Wimpey to spend £150m this year on safety defects backlog

House builder reveals cavity barrier defects behind most of £222m jump in provisions
13 hours ago

Near-1,000 homes approved for Isle of Dogs site

42-storey co-living tower and 27-storey affordable housing block backed
14 hours ago

Go-ahead for Preston 500-home plan at shopping precinct

St Johns shopping centre to be demolished in city centre regeneration plan
14 hours ago

Keltbray lays foundation for HS2 Curzon Street station

Vast 2,011-pile operation finished as Birmingham build powers on
14 hours ago

John F Hunt wins Euston Tower demolition

Specialist will take-down 36-storey tower in technically challenging contract
1 day ago

GMI confirmed for green Manchester office scheme

35 Fountain Street will feature cross‑laminated timber
1 day ago

Trio bag £1bn concrete road replacement deal

Kier, Graham and Sisk win 6-year legacy concrete road framework
2 days ago

Former Balfour chief to become Barratt Redrow CEO

Dean Banks to take helm at house builder later this year
2 days ago

Galliford Try lifts full-year outlook after 20% profit surge

Margins strengthen across Building and Infrastructure as order book hits £4.1bn
2 days ago

Consultation to start on merging CITB and ECITB

Government to launch 12 week consultation this month
2 days ago

Vistry boss Greg Fitzgerald announces retirement

Industry giant to step down after 45 years in house building and construction
2 days ago

Bouygues E&S contracting arm reborn as Equans Sci-Tech

Rebrand to target work for pharma, aerospace and tech clients
2 days ago

£231m London Barbican Arts Centre overhaul approved

Major on-site works are due to begin in 2027
2 days ago

Galliford Try lands £16m Hartlepool school rebuild

St Helens Primary project targets net zero in operation
2 days ago

“Energy and optimism” at Kier after strong set of results

Contractor hits target of an average net cash position for the first time in 13 years.
3 days ago

BBA standards body has own accreditation suspended

British Board of Agrement has status suspended by UKAS National Accreditation Body
3 days ago

Scottish Water unveils £13.4bn six-year spend plan

Publicly-owned utility earmarks £8bn for core infrastructure works from 2027
3 days ago

Winners confirmed on £37bn hospital framework

Ten contractors to deliver next wave of new hospitals
3 days ago

Mears offloads education and health FM arm for £18m

Morrison Facilities Services sold to focus on housing work
3 days ago

Wates veteran to drive Caddick subcontracting growth

Mark Kearney appointed commercial director to sharpen work-winning
3 days ago

Galliford Try wins £60m RAF Lakenheath munitions hub

First US Air Force project secured
3 days ago

Bovis seals £200m London Stock Exchange revamp

Builder returns to Paternoster Square for flagship City transformation
3 days ago

Byrne Group drops O’Keefe Demolition name

Rebrand to Byrne Demolition and Byrne Groundworks
3 days ago

Gateway 2 legacy backlog cut to just three cases

Building Safety Regulator shifts 18 complex schemes into specialist process
4 days ago

Local authorities sitting on £9bn of developer contributions

Unspent cash pile grows after Section 106 and Community Infrastructure Levy payments
4 days ago

Kier veteran joins RED leadership team

RED plots growth plan with top level hires
4 days ago

Major circular construction hub opens in Royal Docks

New waste recycling hub to support Silvertown homes plan
4 days ago

Costain returns to FTSE 250 index

Contractor returns to mid-cap City list
6 days ago