Prep work starts for vast HS2 box slide under A46

Aaron Morby 4 months ago
Share

Balfour Beatty Vinci joint venture has completed construction of a 14,500-tonne box structure designed to allow HS2 trains beneath the A46 Kenilworth Bypass in Warwickshire.

The huge box is currently being built on land next to the A46, rather than beneath the carriageway itself, significantly minimising long-term disruption
The huge box is currently being built on land next to the A46, rather than beneath the carriageway itself, significantly minimising long-term disruption

Engineers worked around the clock to place 120 long beams to form the top of the box in just 14 days.

The lifting milestone paves the way for the vast box to be jacked 64m under the dual carriageway using a system designed by French contractor Fressynet.

The box will be jacked across on a guiding raft at a speed of up to 2.5 metres per hour.

A section of the A46 between Festival Island (Coventry) and Thickthorn Island (Kenilworth) will be closed for two weekends next month for the first stage of preparation work – with plans to move the structure into position during a full closure of the A46 Kenilworth Bypass in spring 2025 for up to three weeks.

John McNiffe, project director at BBV, said: “The safe and successful installation of 120 giant beams is another great achievement for the team who are delivering this box bridge slide in Warwickshire.

“The next stage includes construction of the deck and installation of the bridge parapets before the bridge can be moved into position under the existing carriageway, allowing HS2 trains to pass underneath.”

The structural design was carried out by Mott MacDonald and Systra JV.

Tim Akers, Engineering Manager for the Mott MacDonald SYSTRA Design Joint Venture, said: “We’re incredibly proud of the part we’ve played in the development of this structure.

“Through significant collaboration between HS2, National Highways and Balfour Beatty Vinci, the design has been reviewed and changed from a traditional ‘top down’ approach to an offline construction method with automated rapid and safe installation, reducing the impact to road users significantly.”

 

 

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
2 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
2 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
1 day ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
1 day ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
2 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
2 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
2 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
1 day ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
3 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
3 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
2 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
3 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
2 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
2 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
3 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
3 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
3 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
4 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
3 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
3 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
3 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
3 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
4 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
4 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
5 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
4 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
4 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
4 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
4 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
5 days ago

Contractor services