McLaren Construction has confirmed its top-down build programme for O&H Properties on the £60m first phase of a Foster & Partners designed development on the corner of New Bond Street and Grafton Street in London’s West End.

The seven-storey, 5,400 square metre prime retail and office development includes lower ground, ground and first floor retail space with five storeys of office and event space above.

A complex three-storey basement provides retailers with a lower ground floor and two levels of basement beneath.

McLaren’s top-down construction programme will enable the site team to keep to programme in a busy area of Mayfair.

McLaren will cast the central section of the ground floor slab to enable the cores to be built at the same time as excavating down and casting the basement floor slabs and liner walls.

An extensive temporary works scheme includes 33m deep 1.2m diameter piles and 15m steel plunge columns to support the cores and ground floor slab, allowing the basement box and jump forming of cores to happen simultaneously.

McLaren has worked closely with the City of Westminster to develop a logistics strategy and traffic management plan to minimise impact on the local road network.

A large-scale temporary ramp allows deliveries down to site level from Grafton Street and gives access for the piling rig and crawler crane. Just in time deliveries preserve limited material storage space.

The Grade II-listed shopfront of Wartski jewellers at 14 Grafton Street has been dismantled and will be reassembled in Barlow Place during a later phase of the redevelopment. The final mixed-use redevelopment of the site between New Bond Street, Grafton Street and Bruton Street will feature new homes, a hotel, office and retail space, bars and restaurants.

McLaren Construction’s Managing Director London & South, Darren Gill, said: “There is a deep and complex basement to be constructed before this beautiful new building rises above Grafton Street.

“We know from considerable experience of working in the Oxford Street area that this technical feat will be pulled off in a tight site surrounded by a lot of activity. Occupiers and passers by will see a smart new addition to the West End without ever realising how precisely planned and engineered it needs to be.”

Construction is due to complete in Spring 2026. Key subcontractors on the project will be:

  • Groundwork, civils and concrete for the basement box: McGee
  • Steel frame: BHC
  • Pre-cast façade: Techrete
  • Glazing: Seele
  • Roofing: All Metal Roofing

Latest news

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
16 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
16 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
17 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
23 hours ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
23 hours ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
23 hours ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
2 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
4 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
6 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
7 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
6 days ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
6 days ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
1 week ago

Contractor services