Over 800 high-rise resi jobs stalled by safety regulator

Aaron Morby 5 months ago
Share

Construction starts on more than 800 high-rise residential new-build and upgrade projects are being blocked by Building Safety Regulator design checks.

Frustrated developers warn the logjam in sign-offs to start building is now threatening to undermine the Government’s housing delivery and growth drive.

According to latest figures obtained from a Freedom of Information request from consultant Project4 over 90 major new-build projects are stuck in a bottleneck awaiting Gateway 2 design approval to start work.

Just 11 new-build jobs are reported to have cleared Gateway 2 checks, although only two of these are understood to have passed through the present checking regime.

The delays are also holding up retrofit works on over 600 existing High Risk Buildings (HRB) classified as over seven storeys or 18m.

The Building Safety Regulator (BSR) has come under fire for wasting time, increasing costs, and stalling important projects.

Developers complain they are having to grapple with unclear submission requirements, limited pre-submission consultation, and poor communication.

One developer told the Enquirer said: “We’re still waiting for sign-off on a scheme submitted 40 weeks ago, compared to the 12 weeks turnaround for applications quoted by the regulator.

“Frankly it’s a struggle to communicate with the regulator or the outsourced registered building control approver.

“We’re completely in the dark about what is happening.”

Another developer warned: “There is widespread confusion about what level of design is required for Gateway 2 applications. Some say RIBA 4 design, then we are told it must be full construction issue works detail.

“There is clearly no understanding of how the industry works. Industry procurement models would need a fundamental change to fall into line with these requirements. It basically means all specialist contractor detailed designs needs to be fixed at pre-construction.”

Some developers are now said to be looking at the possibility of reducing the height of planned projects to avoid the regulatory process.

Trade body, the Fire Industry Association, supports the thrust of the Building Safety Act, but is also deeply concerned about delays to HRB projects.

It describes processes as ‘overly complex and inefficient” and has called on the BSR immediately to review processes, procedures and guidance,

“This is an urgent issue, it is holding back commencement of construction of HRBs”, warns an FIA statement.

“This situation is counter to the accepted need for new housing stock and will significantly impact parts of the country where residential construction is predominantly HRB (rather than lower rise) such as cities.”

The association echoed calls for further guidance on the extent of design information required to reduce the wasted time and effort incurred by design teams and the BSR in submitting and reviewing designs that are at an inappropriate design stage.

The association also wants to see a stepped process of design submission to give developers confidence to develop full detailed designs for approval.

A spokesperson for the Building Safety Regulator said there had been an issue with the standard of applications being submitted.

“We are dedicated to working with industry to achieve timely approval of building control applications and safe and compliant HRB project completions.

“The new gateway processes brought in following the Grenfell Tragedy are a key control to raise safety standards in buildings. However the building regulations and requirements for building work have not changed in the new regime.

“We require developers to submit high-quality and clear building control applications which fully demonstrate compliance with building regulations to ensure a smooth approval process. This will also mitigate the risk of costly delays or potentially higher borrowing costs.

“We recognise that engaging with a new system and requirements is not something which can be achieved overnight and we’re continuing to work closely with industry to identify areas where we can strengthen our advice and guidance for applicants. This includes weekly discussions with partners including the Construction Leadership Council, Construction Industry Council, Build UK, Dept for Business and Trade and Home Builders Federation”.

Latest news

Bid race takes off for £500m MAG airport small works deal

Nine-lot framework to cover civils, building and M&E jobs up to £5m
8 hours ago

Rob Perrins steps up as executive chair in Berkeley shake-up

Long-serving chief steps up to lead housebuilder’s next growth phase
47 minutes ago

Competition watchdog turns attention to civil engineering

Competition and Markets Authority launches study into road and rail delivery
18 hours ago

10-Year Infrastructure Strategy published

Full details as Government pledges £725bn of funding over the next decade
18 hours ago

Mace director joins Wates as Chief Commercial Officer

Pat Fitzgerald to lead commercial strategy at Wates
10 hours ago

Korean firm buys part built Hackney job from failed Elements Europe

Work can now restart on 21-storey hotel and office development
21 hours ago

Mark Wild radical reset plan to rescue HS2

Senior manager bonuses scrapped and non-permanent labour cutback
1 day ago

HS2 supply chain fraud claims spark ministerial probe

Transport secretary pledges one-year reset for HS2 to end 'litany of failures'
2 days ago

Lords launch inquiry into Building Safety Regulator delays

Industry asked for evidence of how system is failing: Have your say
1 day ago

Willmott Dixon director becomes co-owner of local contractor BSN

Nick Gibb targets £100m turnover at Dudley based national contractor
2 days ago

Dry lining boss sentenced after mystery account moves

Court hears of £500,000 in unexplained transfers before contractor went under
1 day ago

Barhale bags £16m shaft tank for Severn Trent Water

"Final piece in the puzzle" of Etruria Vale upgrade
23 hours ago

Keltbray strikes £30m funding deal for growth

Three-year funding deal to support push into higher-margin work
2 days ago

Take That brother buys steelwork giant William Hare

Entrepreneur Simon Orange seals deal for £350m turnover contractor
3 days ago

Civils contractor LF Solutions files administration notice

£20m-turnover specialist has labour supply arm and own plant fleet
2 days ago

Joseph Gallagher lands £50m green energy deal

Major trenchless construction contract for HyNet North West project
2 days ago

New boss drives NG Bailey to record revenue

Fresh strategy lifts M&E group's order book to £1.6bn
2 days ago

Costain wins vast underground hydrogen storage design job

Firms lands FEED contract for Cheshire salt caverns conversion
2 days ago

Graham gets green light for £70m Glasgow student tower

Construction due to start this year on 25-storey Anderston scheme
2 days ago

New £16bn National Housing Bank to drive 500k new builds

Homes England given new powers to finance stalled and complex schemes
2 days ago

Morgan Sindall upgrades profits forecast for this year

Overbury fitout and construction operations exceed trading expectations
3 days ago

Major project bidders to face ‘British jobs’ test

Contractors to face tougher jobs pledge scrutiny under new procurement shake-up
4 days ago

Green light for £32m Wythenshawe Culture Hub

Construction to start this year on first phase of £500m town centre revamp
3 days ago

Hercules delivers record first half as HS2 fuels growth

Labour supply specialist says HS2 demand climbing with 630 workers now deployed
3 days ago

Private equity firm acquires Hepworth Clay pipes business

Historic UK drainage manufacturer sold by Wavin
3 days ago

Balfour Beatty names new Scottish MD

Nick Rowan to take reins as Hector MacAulay to retire after 40 years
4 days ago

£500m rail deal locks in future for Scunthorpe steelworks

Government-backed deal with Network Rail safeguards UK production
3 days ago

Morrison rides in for £19m mountain bike R&D hub

Flagship Borders cycling R&D hub set for Caerlee Mill site
4 days ago

Revised plan submitted for Manchester landmark towers

400 more flats added to Albert Bridge House scheme
4 days ago

Job losses loom at consultant GHD

Redundancy consultation underway with jobs at risk
4 days ago