Piling job cuts loom over safety regulator project delays

Aaron Morby 3 months ago
Share

Hold-ups on gaining safety regulator approvals for high rise building projects are starting to put workers jobs at risk deep in the supply chain.

Specialist demolition and foundation contractors are warning job cuts loom as work dries up because developers are struggling to get clearance to start construction.

Since the introduction of the new regulatory framework in April 2024, only a handful of high risk building (HRBs) projects have cleared the approval system known as Gateway 2.

Now the Federation of Piling Specialists has added its voice to calls on government to urgently address delays being caused by the Building Safety Regulator approval process.

Around 92 new build high risk building projects are in the system awaiting approval. A further 18 applications have been invalidated or rejected by the Building Safety Regulator.

Just two new build projects are understood to have cleared the Gateway 2 hurdle in the last year.

The logjam is most acute in London and other urban areas, where projects over seven storeys are stalled, creating a ripple effect across the geotechnical, demolition, and construction supply chains.

The regulator is supposed to clear applications in 12 weeks although project timelines are extending as far a 40 weeks, particularly on big new build schemes.

The Building Safety Regulator argues approval times are coming down and are now on average taking 18 weeks, although the average includes many smaller refurb and retrofit projects.

FPS chair, Malcolm O’Sullivan, said many members were now being forced to consider reducing staff numbers and scaling back investment—actions that threaten to erode core teams and exacerbate existing skills shortages once projects eventually gain approval.

He said: “While we recognise the importance of the BSR’s role in improving building safety, the reality is that approval times of six months or more are simply not viable.

“These delays are undermining investment, recruitment, and the wider stability of the sector.

“More critically, they are jeopardising the Government’s ability to deliver its target of 1.5 million new homes over the next five years. Without urgent reform, these ambitions will remain out of reach.”

The regulator has blamed delays on a surge of applications last year and poor quality submissions that fail to meet requirements.

The Government and the BSR are being urged to review the process.

Firms want to see clearer and consistent guidance to ensure a streamlined approval process.

They also want more resources channelled into to accelerating approvals and closer working with industry stakeholders to develop practical solutions.

Latest news

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
18 hours ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
20 hours ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
20 hours ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
20 hours ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
1 day ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
20 hours ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
21 hours ago

Early call-out for Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
20 hours ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
2 days ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
2 days ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
2 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
2 days ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
2 days ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
2 days ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
6 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
7 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
6 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
6 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
7 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
7 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
7 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
6 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
1 week ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
1 week ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
7 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
1 week ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
7 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
7 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
1 week ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
1 week ago

Contractor services