Watchdog MPs raise alarm over HS2 Euston station plan

Aaron Morby 2 months ago
Share

MPs on the Public Accounts Committee have lambasted the management of the HS2 project and raised grave concerns about the latest plan to deliver the Euston terminus in London.

Grand plans for Euston, but PAC questions when it will actually get built
Grand plans for Euston, but PAC questions when it will actually get built

Their report published today calls for “fundamental reset” of the project by the summer.

They warn that they remain sceptical about the Government’s ability to successfully deliver its revised programme following a litany of failures and unheeded warnings.

The report says that the HS2 programme has become a casebook example of how not to run a major project.

“It is unacceptable that over a decade into the programme we still do not know what it will cost, what the final scope will be, when it will finally be completed or what benefits it will deliver,” states their report.

Watchdog MPs also highlighted the significant challenges facing plans to build the Euston Station terminus using a third party development body.

As plans stand, HS2 will open with a terminus at Old Old Common. Despite plans to launch the TBM tunnel drive next year to Euston from Old Oak Common there are no detailed plans or timescale for delivering the Euston Terminus, warns the report.

The Government’s Euston plans currently rest on the £6bn cost being significantly underpinned by the private sector.

The PAC said it was concerned that there is no clear plan for this, and said it was sceptical the private sector would come forward to the level required.

The government confirmed that HS2 would terminate at London Euston in the Autumn 2024 budget.

However, the PAC warns the Department still does not yet have a plan for the work at Euston which includes: the HS2 station, the existing Network Rail station, the underground station, and the commercial and housing developments near the station.

“In addition, the Department intends the work to be sustantively privately funded, but it is unclear how achievable this goal is,” they warn.

Sir Geoffrey Clifton-Brown MP, Chair of the Committee, said: “Our Committee has not made recommendations in our report on delivering better outcomes for HS2’s future passengers.

“We are long past that point. It is time to deal with HS2 as what it is – a cautionary tale that should be studied by future Governments in how not to run a major project.

“We are sceptical of Government’s ability to successfully deliver even a curtailed scheme, one which we already know will on its face bring very poor value for money. The question has instead become: what possible benefit can the Government now salvage for the taxpayer, from a mess that presents real risks to the UK’s overall reputation?”

The Department for Transport’s present cost estimated set out in November 2023 is £45bn to £54bn compared with HS2 Ltd’s latest estimate of £54bn to £66bn in June 2024.

Both cost estimates are still in 2019 prices, once adjusted for inflation, the total programme costs might be close to £80bn, states the report.

 

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
1 day ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
2 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
20 hours ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
21 hours ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
2 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
2 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
2 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
21 hours ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
2 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
2 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
2 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
3 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
2 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
2 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
3 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
3 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
3 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
4 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
3 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
3 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
3 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
3 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
4 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
3 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
4 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
4 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
4 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
4 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
4 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
4 days ago

Contractor services