Gateway gridlock hits build-to-rent delivery as starts nosedive

Aaron Morby 1 week ago
Share

Delays at the Building Safety Regulator are being blamed for a sharp fall in build-to-rent construction starts, threatening future housing supply despite a strong year for completions.

Fresh figures from the British Property Federation and Savills shows 17,309 BtR homes were completed in the past 12 months, up 18% as demand rises for rental homes.

But the number of new schemes breaking ground has dropped for the fifth quarter running, with homes under construction falling 14% year-on-year.

The slowdown is being linked to mounting delays at the Gateway 2 approval stage, with the Building Safety Regulator still struggling to clear a backlog of applications inherited from collapsed private building control firms.

London has seen the steepest fall, with BtR starts down 18% to just 15,000 homes under construction. Across the regions, the pipeline has shrunk by 12% to 34,870.

Planning activity also shows signs of strain. While overall consents are up 13% and the early-stage pipeline has grown 5%, the number of detailed planning applications is down 16%—highlighting a growing disconnect between planning permissions and actual delivery.

Melanie Leech, chief executive, British Property Federation, said: “Completions remain robust, and planning activity is holding up well, but the sector is facing a real bottleneck in progressing schemes through to construction.

“Viability challenges, coupled with continued uncertainty around project timelines are slowing momentum just at a time when rental demand is rising sharply.

“Investor appetite is there but unlocking it will require a concerted effort to support the delivery of BtR homes. Urgent action is needed in particular to deal with the pipeline blockage currently being caused by the Building Safety Regulator.”

British Property Federation chief executive Melanie Leech said: “There’s a growing logjam in getting projects from planning through to construction. Delays at the Building Safety Regulator are a major factor and need urgent attention if the sector is to continue delivering at scale.”

Savills’ Guy Whittaker added: “The first quarter of 2025 marked the highest Q1 for new investment since 2022, supported by over £500m in urban multifamily forward funds, which will deliver over 1,500 homes once complete.

“There are significant challenges to future supply though, particularly for schemes facing building safety delays. This represents a substantial threat to current housing delivery and puts Government housing targets at risk.”

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
2 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
38 minutes ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
10 hours ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
9 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
8 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
16 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
1 day ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
16 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
17 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
17 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
17 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
1 day ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
7 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
6 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
6 days ago

Contractor services