Manchester town hall refurb costs hit £525m

Grant Prior 1 hour ago
Share

The refurbishment of Manchester Town Hall will cost another £95m and not be completed until Spring 2027 by main contractor Bovis.

The latest total £525m budget and time scale increase has  been confirmed in a project update by Manchester City Council.

Bovis – then known as Lendlease – started the job in 2020 with an original budget of £330m and completion date of 2024.

The scheme has been hit by a series of cost and time increases in the intervening years and the council described it as “the largest and most complex heritage project undertaken in living memory anywhere in the UK.”

The council update said:  “The project has been impacted by a unique combination of challenges since its construction phase started in 2020.

“Wider factors have ranged from disruption caused by the Covid pandemic and a volatile economic climate, influenced by external factors such as the war in Ukraine, to unprecedented materials and labour cost inflation in the construction industry.

“More directly project-related factors include a shortage of specialist labour capacity in the supply chain, issues with the supply of materials (which under strict heritage rules need to closely match those used in the original construction) and ongoing discovery of further construction challenges, all of which unavoidably cause delays and associated costs.

‘These challenges range from minor obstructions and quirks from the original Victorian build all the way through to structural issues which require design solutions before work can continue.

“These issues have continued to assail the project since the last major update in October 2024. For instance, the wider construction industry is experiencing a steep rise in the number of companies falling into administration. Three of the contractors delivering works packages as part of the project have gone into administration in the last six months alone.

“Sourcing the required materials is also difficult. As an example, this summer the project’s principal stone contractor advised that the quarry from which approved stone (closely matching that used in the original construction) was ceasing to supply the construction industry in bulk. This has caused delay as an alternative source of suitable stone is found.

“Such is the complexity of the project that any delay to one element of work has a knock-on impact on many others.”

Most of the external work is now complete with the focus of the project moving to the interior.

Deputy Council Leader Cllr Garry Bridges said: “Like everyone, we have been frustrated by the increased time and cost involved. But if we had not acted decisively to invest in the future of this Victorian masterpiece, many parts of which were reaching the end of their natural lifespans, we would have seen it become unusable and obsolete.

“We’re glad that we’re now on a confident path to completion in spring 2027, in time for the 150th anniversary of its original opening. The results of the project will be there for people to appreciate and enjoy for the next 100 years.”

Latest news

Gateway 2 project backlog slashed but retrofit logjam drags on

Regulator halves new-build legacy logjam but safety retrofit caseload grows
9 minutes ago

Manchester town hall refurb costs hit £525m

Three subcontractors have gone bust in last six months on Bovis project
54 minutes ago

Stage set for Andover £24m new theatre bid race

Five-strong shortlist to be drawn for town-centre regeneration centrepiece
44 minutes ago

ECO4 axe pushes local retrofit firms to brink

£6.5bn cut leaves SMEs fearing collapse and thousands of cold homes abandoned
11 minutes ago

“Future of construction” firm files administration notice

Graphene pioneer Versarien looks to find buyer
15 minutes ago

Yoo Capital lodges plan for £1bn Camden Film Quarter

Hollywood-scale studios and 485 homes to be built at Kentish town industrial site
3 days ago

Electrical flashover at wind farm hits maintenance worker

Worker left with life changing injuries after accident
1 hour ago

Crane load failure at Hinkley: Video

Lucky escape as formwork shutter crashes to the ground
3 days ago

JP Morgan unveils plan for £3bn London mega-tower

Foster + Partners lined up for three-million sq ft Canary Wharf superstructure housing 12,000 staff
3 days ago

Modular specialist Thurston files administration notice

Court notice filed by £46.5m turnover business
3 days ago

Fit-out firm AC1 lands first job as main contractor

£19m student accommodation scheme in Liverpool is first win for new division
3 days ago

Concrete specialist beats Budget EOT change

Goodmix Concrete sold to staff day before tax relief cut
3 days ago

M&E specialist restarts Berwick Hospital job after Merit collapse

Opus takes on most of Merit’s workforce to keep £35m project moving
3 days ago

CIS fraud clampdown puts directors in the firing line

Directors made accountable as Treasury cracks down on organised CIS fraud
4 days ago

Council clears way for £10bn Earls Court district

4,000-homes West London super-scheme clears planning hurdle
4 days ago

National Timber Group collapses with over 560 jobs axed

Administrators race to find a buyer to avoid further supply chain disruption
5 days ago

Construction to start next year on Lower Thames Crossing

Public funds for preparatory work on mega-scheme approach £1.5bn
5 days ago

Brandon Hire Station to close 60 branches

Owner Vp to focus on bigger contractor customers and larger projects
4 days ago

Reeves raises taxes on dividends and EOT deals

Tax relief for selling companies to staff cut in half
5 days ago

McLaren wins UK’s largest timber frame office building

William Hare subsidiary to provide frame on nine-storey Xylo building in Clerkenwell
5 days ago

£750m Marlow film studios clears green belt hurdle

Dido Properties wins appeal for 18-stage studio near London
5 days ago

Helical sets start dates for two London overstation jobs

Mace to start £200m Paddington job in Q1 and Southwark tube job next summer
5 days ago

Government goes for £33bn Heathrow third runway plan

Rival Arora scheme loses out as airport operator hopes for speedy planning decision
6 days ago

Hill breaks ground on 166-home Bristol harbourside

JV with council-backed Goram Homes unlocks tricky Spike Island site
5 days ago

Go-ahead for Digbeth 240-home Phoenix Yard scheme

Developer Hartwell's £100m mixed-use neighbourhood advances
5 days ago

Speedy looks to HSS ProService deal to stem losses

Hire giant hopes deal will add £50m+ in annual revenue
5 days ago

Plans for £59m Swadlincote leisure and office hub

South Derbyshire Council plans to start work by next September
5 days ago

Bellrock buys lift specialist

Expanding facilities management firm acquires MW Lift Services
5 days ago

£145m Birmingham towers clear Gateway 2

Midgard set to mobilise as Edition Birmingham gets full sign-off
6 days ago

Deeley returns to profit and eyes £100m milestone

Later living boom powers Midlands family builder rebound
6 days ago