Balfour Beatty probe exposes new £70m black hole

Aaron Morby 9 years ago
Share

Balfour Beatty this morning revealed a further profit shortfall of £70m at its UK construction business following KPMG’s audit.

The firm also cancelled its planned £200m share-buy back programme and set out a turnaround plan to cut costs and improve project reporting.

Balfour blamed the further project deterioration on an overly complex reorganisation programme that led to high levels of employee turnover at a time of extremely challenging market conditions.

Leo Quinn, group chief executive, said Balfour Beatty had become too complex for adequate financial control and highlighted a significant opportunity to reduce costs and improve cash flow.

The latest construction profit warning follows £135m of provisions taken over the year and Quinn could not rule out further bad news when Balfour’s full-year results are reported in March.

Under his planned regime shake-up engineering, project management and customer-facing teams will be spared cuts and strengthened.

The major projects division will now report directly to Quinn. He added that the leadership team would be improved with incentives aligned to project programmes.

Balfour will strengthen its bid approval and project delivery review processes after these were heavily criticised by KPMG.

Quinn said Balfour Beatty would also roll out a programme of systematic project-level training to drive a culture of productivity and cash generation and introduce standard reporting to raise transparency.

Balfour’s board said £20m of the shortfall related to differences between the company’s own assessments of its contracts and those of KMPG’s.

A further £50m difference arose from a subsequent deterioration in project performance on current contracts.

“The summary report on UK Construction is an important step in drawing a line under a period of uncertainty for our customers, and enabling us to focus fully on delivering value”, said Quinn.

“Balfour Beatty is a large organisation which had become too complex and too devolved for adequate line of sight and financial control.

“The key is that these issues can be put right and we now have clear action plans in hand. Significant opportunity exists across the group to drive reduced costs, improved profits and strong cash generation to the full benefit of our shareholders.”

He added: “Working changes into the culture of the group will take time and discipline, but everything I have seen so far reinforces my first impressions about the depth of engineering capability in Balfour Beatty.

“Our goal now is to ensure that the value delivered to our customers by what is an exceptional workforce, translates into best-in-class performance and returns.”

Balfour said that a review of its portfolio of assets had raised the valuation to £1.3bn from around £1bn. He also revealed the group ended the year with a net cash balance of £180m.

Quinn said the board still needed to assess the overall level of contract risk provisions in the UK construction business in light of the operational issues identified and would announce the outcome at the full year results in March.

KMPG review findings

The KPMG shone a light on a catalogue of issues.

1. Bidding – Tendering at very low margins with optimistic assumptions around cost, programme and procurement savings, and inadequate provisions for risk.

2. Commercial and contract management – Insufficient local management challenge and review of contract performance, failure to recover genuine contract entitlement due to poor contract administration and optimistic assumptions on contract penalties.

3. Accuracy of cost and programme forecasting – Insufficient visibility, control and understanding on actual versus reported contract performance.

Latest news

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
2 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
2 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
2 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
2 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
2 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
2 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
2 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
3 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
3 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
3 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
3 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
3 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
3 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
4 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
4 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
4 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
4 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
4 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
5 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
5 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
5 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
5 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
5 days ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
5 days ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
5 days ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
6 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
6 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
6 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
6 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
6 days ago

Contractor services