Two tonne temporary roof blown off scaffold

Grant Prior 10 years ago
Share

Specialist contractor Pyeroy has been fined £10,000 after the roof of a temporary extension at Lynemouth Power Station was blown off in high winds.

A 25-metre span of the roof, that was around six metres long and weighed two tonnes, was blown off its eight-metre high scaffolding end supports on 23 December 2012.

It struck the roof of an adjacent biomass shed before landing 50 metres away beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians.

Fortunately the timing of the incident just before Christmas meant that the normally busy road was deserted.

Bedlington Magistrates’ Court heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

In 2011 Pyeroy Ltd had been instructed by the owners of the power station to build a temporary extension to the biomass shed that was designed by an external scaffold design company.

This was dismantled in August 2011 once it was no longer required.

Then in May 2012, Pyeroy was asked to install another temporary extension, this time designed by its in-house design team. Although similar to the first structure, it was to be shorter and lower.

It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. But poor communication resulted in an incomplete design plan being used.

HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

Magistrates were told that on 22 December it was noted that the weather was worse than normal, with the winds picking up. This meant some of the sheeting on the structure needed to be re-tied.

The temporary roof was blown off its end supports early the following morning. It ended up straddling a safety barrier and a dry riser pipeline between the main delivery access road and the legs of an adjacent conveyor.

HSE inspectors concluded that Pyeroy had failed to ensure those involved in the construction of the extension had the necessary knowledge and experience to do the work.

The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

Pyeroy of Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to safety breaches.

After the case, HSE inspector Andrew Woodhall said: “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

“It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

“Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof.

“As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
2 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
3 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
3 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
3 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
1 day ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
21 hours ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
3 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
20 hours ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
1 day ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
1 day ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
1 day ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
1 day ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
1 day ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
1 day ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
1 day ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
4 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
4 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
4 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
5 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
4 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
4 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
5 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
5 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
5 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
5 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
6 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
5 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
5 days ago