Specialist contractor Pyeroy has been fined £10,000 after the roof of a temporary extension at Lynemouth Power Station was blown off in high winds.

A 25-metre span of the roof, that was around six metres long and weighed two tonnes, was blown off its eight-metre high scaffolding end supports on 23 December 2012.

It struck the roof of an adjacent biomass shed before landing 50 metres away beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians.

Fortunately the timing of the incident just before Christmas meant that the normally busy road was deserted.

Bedlington Magistrates’ Court heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

In 2011 Pyeroy Ltd had been instructed by the owners of the power station to build a temporary extension to the biomass shed that was designed by an external scaffold design company.

This was dismantled in August 2011 once it was no longer required.

Then in May 2012, Pyeroy was asked to install another temporary extension, this time designed by its in-house design team. Although similar to the first structure, it was to be shorter and lower.

It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. But poor communication resulted in an incomplete design plan being used.

HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

Magistrates were told that on 22 December it was noted that the weather was worse than normal, with the winds picking up. This meant some of the sheeting on the structure needed to be re-tied.

The temporary roof was blown off its end supports early the following morning. It ended up straddling a safety barrier and a dry riser pipeline between the main delivery access road and the legs of an adjacent conveyor.

HSE inspectors concluded that Pyeroy had failed to ensure those involved in the construction of the extension had the necessary knowledge and experience to do the work.

The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

Pyeroy of Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to safety breaches.

After the case, HSE inspector Andrew Woodhall said: “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

“It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

“Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof.

“As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

Latest news

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
2 hours ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
5 hours ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
9 hours ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
9 hours ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
9 hours ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
9 hours ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
9 hours ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
9 hours ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
6 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Contractor services