Prefab building collapses on churchgoers

Grant Prior 10 years ago
Share

A modular construction specialist has been fined after a two-storey portable building collapsed at a church where more than 30 children and parents were playing in the lower room.

South Derbyshire Magistrates’ Court heard the incident happened at Ashbourne Elim Pentecostal Church in Derbyshire where two volunteers were preparing parcels for the church’s foodbank in the upper cabin.

The two cabins had been refurbished and installed by Relocatable Building Systems Ltd in September 2013.

A month later, on 24 October, both cabins dropped when a bolt on the jacking leg of the lower unit sheared off. The top part of the leg came out of the wooden frame, causing the collapse.

The upper cabin came to rest on the roof of the lower one at one corner, sending a number of food items falling off the shelves in the upper building.

One of the volunteers suffered a bruised arm and, although no-one else was injured, all were badly shaken.

Senior pastor, Rev Ben Brown said it was a ‘miracle’ the lower cabin had not collapsed on them.

An HSE investigation found the company had refurbished the buildings before their installation at the church.

New inner sections of the jacking legs were installed but the original pins, used to adjust the height of the legs, could not be fitted due to the holes not being drilled to the correct size.

Instead,  smaller bolts, which were not designed for this purpose, were used, meaning they would fail at some time in the future.

An Improvement Notice was served by HSE on Relocatable Building Systems Ltd requiring the company to develop safe systems of work to ensure refurbished buildings were safe.

Both cabins at the church were repaired and reinstalled.

Relocatable Building Systems Ltd, of Hilton, Derby was fined a total of £8,000 with £1,589 costs after admitting two safety breaches.

Speaking after the hearing HSE inspector Steve Shaw said: “This was a terrifying incident for those involved and left a lot of people scared and upset.

“During installation the company should have carried out a final check to ensure all the work had been completed and the two cabins were bolted together safely.

“It is very lucky that the top cabin stayed in contact with three of the jacking legs as this prevented the full weight coming to rest on the wooden frame of the lower unit where children were playing.

“The wooden frames are not designed to take the weight of an upper unit so it could have quite easily come crashing down with horrific consequences.

“The collapse could have been avoided by Relocatable Building Systems had the refurbishment been undertaken in a suitable manner using the same or better specification material as the original.

“The church was unable to rent out the rooms while they were away being fixed and when they were reinstalled some months later, there was a lot of suspicion and doubt about their safety from the community the church serves.”

Senior Pastor, Rev Ben Brown, whose wife and two-year-old son were in the lower room at the time of the incident, said:

“It was a complete miracle that it did not fall further but came to rest where it did. Another half inch and the consequences would have been devastating. I think someone was certainly looking after us that day.

 

Latest news

Apprentice saws-off thumb on hotel refurb site

Court hears how digit was reattached and teenager continued training with another firm
4 minutes ago

Buyers see recovery in house building sector

But civil and commercial work still in the doldrums
1 hour ago

Laing O’Rourke tops June contracts league

£919m animal super lab dominates new orders
5 hours ago

TSL turnover smashes £500m as profit almost trebles

Data centre and logistics contractor rises high on surging demand
4 hours ago

Gleeson Homes chief exec leaves business after restructure

Management revamp after "challenging" year
4 hours ago

Green light for 1,600-home Oldham town centre overhaul

Plans for over 1,600 homes across six regeneration sites approved
4 hours ago

DSM wins Norwich city centre clearance job

Anglia Square shopping centre clearance for £300m scheme
4 hours ago

13-year-old becomes UK’s youngest qualified digger driver

Grandson of Gallagher Group chairman sets industry record
13 hours ago

Cubby reborn in £12m Svella-backed takeover

£50m revenue target set as 14 firms combine under new Cubby Group banner
1 day ago

North East NHS trusts plot £3bn health estate overhaul

Market engagement begins for major construction push across four trusts
1 day ago

HG goes green on cranes in £1.2m switch to battery power

Diesel-free crane drive cuts fuel bills by 94%
1 day ago

Developer fined £165,000 for fire safety failings

Firm ignored fire safety orders on apartment job in Preston
1 day ago

Bidding to start for £1.8bn North West framework

Contractors invited to bid for latest Procure Partnerships deal
1 day ago

Hill hits record £90m profit as homes pipeline swells

Build-to-rent push and £4.8bn contracting book to fuel next growth phase
2 days ago

Rayner unveils £39bn plan to build 300,000 social homes

Council building revival and rent reform feature in social and affordable homes plan
2 days ago

Keltbray bounces back with £3.2m profit

Tighter controls and smarter project selection fuel strong turnaround
2 days ago

VINCI JV wins 500-home twin town centre revamps

Chester Northgate phase 2 and Northwich Weaver Square schemes move to delivery stage
2 days ago

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
3 days ago

How to see your stories on the Enquirer

Join our Suppliers and Buyers directory to get your news published
2 days ago

Henley lands Midland Mill revamp on Leeds tower scheme

Restoration of 18th-century mill kicks off on South Bank regeneration project
2 days ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
3 days ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
3 days ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
3 days ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
3 days ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
4 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
4 days ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
3 days ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
4 days ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
4 days ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
4 days ago