Willmott Dixon ousts Vinci from £43m hospital job

Aaron Morby 10 years ago
Share

Willmott Dixon has undercut preferred bidder Vinci for a seven-storey medical research centre at the site of the Royal Free Hospital car park in north London.

Vinci was appointed as preferred bidder at the end of last year in a two-stage contest for the contract to build the Pears Building at the Hampstead site, which will be home to the University College London Institute of Immunity and Transplantation.

But at stage 2 final price submission Vinci submitted a figure of £45.6m, against the client’s original budget of £30.1m, and refused to accept the proposed design risk allocation under the construction phase contract.

Client The Royal Free Hampstead Charities is now aiming to strike a deal with Willmott Dixon, which ranked second in stage 1 bidding after it offered to do the job for at least £2.8m less.

Willmott Dixon is also promising an extra saving of up to £1.7m through further design development.

A statement seen by the Enquirer from the client said that it had decided to change contractor because Vinci’s offer price, equivalent to £5,300/m2, was well above the benchmark range for similar projects of £3,500-£4,700/m.

It said: “Further it is inappropriate to contract with Vinci on the basis of Vinci’s current proposed contract terms as it refuses to accept the proposed design risk allocation under the construction phase contract.

“Willmott Dixon, however, will accept a risk profile more aligned with the authority’s original intentions for the contract.

“If the abridged pre-construction service agreement is not awarded to Willmott Dixon by mid-October 2015, and the construction contract in place by 17 December 2015, there will be a significant adverse impact on the programme for delivery of the works and no guarantee of cost savings.

“In these circumstances the most likely outcome is the cancellation of the project.

“As any tender conducted now will likely produce prices in excess of any affordable budget and jeopardise the project, it is extremely urgent that the authority secure the project by appointing the next placed contractor from the tender process.

“Substituting the contractor now will not alter the overall nature of the contract as the scope of works will remain as originally tendered.”

The money for the new building has been raised by the Royal Free Charity and UCL. An additional £25m will be secured for the appointment of research teams.

Pears Building Hampstead

The Hopkins designed Pears Building will allow more patients to have access to ground-breaking medical treatments through clinical trials.

Scientists at the IIT are carrying out research into immune-related conditions such as leukaemia, type 1 diabetes and HIV.

It is being project managed by Buro Four with BDP on board as M&E design consultant.

As well as the IIT, the Pears Building will include patient accommodation, office space for volunteers and a car park.

Latest news

BSR backlog swells as new build approvals run to 36 weeks

First official Government figures expose full extent of Gateway project logjam
1 day ago

Repair slowdown drags down construction output

New work activity rises in May despite overall 0.6% output fall
1 day ago

Equans suffers £29m loss as new build exit drags on

Refocused retrofit contractor still dogged by legacy losses despite profitable core work
1 day ago

Scaffolding trade body NASC facing discrimination claim

Former training manager to take trade body to Employment Tribunal
1 day ago

ACS lands lead role on Stafford transformers lab

Contractor to start main £20m expansion in live site environment
1 day ago

GRAHAM sees profits rise despite dip in turnover

Record order book as contractor confident about future prospects
1 day ago

Nixon Hire sells 200-strong welfare van fleet to Sunbelt

Sunbelt more than doubles mobile site welfare capability
2 days ago

Henry family and directors face claims topping £31m

Administrators chasing dividend payout, unpaid loans and family benefits
2 days ago

Vistry eyes second-half affordable homes work surge

Government rent reforms and funding pledges power-up work pipeline
2 days ago

JV picked to progress Severn-Thames water transfer plan

AtkinsRéalis and Stantec to map pipeline or canal link
2 days ago

Police catch on the run construction boss

Director missing for months after failing to appear in court after site death
2 days ago

Green light for £800m Poplar estate revamp

Construction to start next year at Teviot Estate
3 days ago

Civil engineering trade body boss leaves to join Mace

CECA Chief Executive Alasdair Reisner joins consulting arm
3 days ago

House builders offer £100m to drop competition probe

CMA set to strike deal with cash going to affordable housing programmes
3 days ago

Transport Secretary axes £1.4bn road jobs in south east

Alexander pulls plug on A12 and A47 upgrades in budget crackdown
3 days ago

Fusion taps HG for first Birmingham student job

622-bed Bristol Road scheme kicks off contractor’s Midlands push
3 days ago

VolkerWessels UK parent group to sell core Dutch business

UK, German and North American operations remain with Dutch owner Reggeborgh
3 days ago

Union claims sex pests are rife in construction

Shock assault figures following Unite survey of 100 workers
3 days ago

Green light for two more City of London towers

Combined 77 more storeys of office schemes approved
4 days ago

John F Hunt starts enabling works on £200m Strand Premier Inn

Main contractor due to be appointed this summer
4 days ago

£200m deal unlocks full 1,000-home Digbeth scheme

Caddick has started early works on the Moda-led Stone Yard project
4 days ago

10 big road and rail upgrades get funding green light

£1.3bn A66 dualling, Simister Island junction upgrade and Midlands Rail Hub get funding
4 days ago

Design, build and finance plan for £1bn Cheddar 2 reservoir

South West Water starts pre-bid market engagement on 75km pipeline and reservoir
4 days ago

Illegal working blitz catches Indian builders

Home Office raids target migrants working cash-in-hand on sites
5 days ago

Major Sizewell concrete win for local supplier

Eastern Concrete Ltd wins its biggest ever contract
4 days ago

SIG chief put on gardening leave

New CEO appointed as Gavin Slark steps down immediately
4 days ago

Adjustable hard hat launched for different hair types

AtkinsRéalis initiative will also make PPE more comfortable for bald builders
4 days ago

Lynch appeal sees £800,000 abnormal load fine reduced to £10k

Judge rules original fine was was 'manifestly excessive'
5 days ago

Government calls up firms to explore PPP healthcare projects plan

New public-private partnership idea to be scoped out with contractors
5 days ago

Balfour Beatty terminates Danny Sullivan labour deals

Around 500 workers on HS2 will be moved to alternative agencies or be taken on direct
1 week ago