Morgan Sindall quits £39m Cambridge Uni project

Aaron Morby 9 years ago
Share

Morgan Sindall is walking away from a major student services centre job for Cambridge University three months into the project.

Student hub project involves a complex mix of restoration, alterations and new buildings
Student hub project involves a complex mix of restoration, alterations and new buildings

The firm said it would complete enabling works but not take on the main build contract as was expected.

The decision by the client and contractor to part company looks like the latest in a string of projects where high cost inflation has seen builders fail to agree a final lump sum price in final contract negotiations.

Just last week Bouygues, which has been lined up for a £65m project for the Great Ormond Street children’s hospital in London, failed to agree the final price during second stage negotiations forcing the client to go back to the market.

Cambridge University said it would be announcing a new contractor in due course to take forward the £39m project to create a new examination hall and student hub.

A spokesperson for the contractor said: “Morgan Sindall is completing the enabling works on the North Range project for the University of Cambridge. We had bid to deliver the full scheme but did not get to the stage of being awarded the contract.” 

The North range buildings project on the New Museum site in the city is one of two projects Morgan Sindall has on the go with the University.

It started work on a £60m genome research building at Granta Park in Cambridge last Autumn and last year completed a new £40m chemical engineering and biotechnology facility.

Student services centre Cambridge

University is turning to a new contractor to deliver the main works

The student hub project involves a complex mix of restoration, alterations and new buildings, working with both new-build and existing listed buildings.

Morgan Sindall has demolished the Examinations Halls Building to provide space for a major new building in its place. The project also includes refurbishing the Grade 2 listed arts school and ground floor of the Old Cavendish Labs (East and Raleigh Wings).

A University spokesman said: “Following the imminent completion of the enabling works (Phase 1) of the North Range Student Services Centre project on the New Museums Site by Morgan Sindall, the University has chosen to engage another contractor, name to be announced, to complete the work.”

Latest news

United Living acquires civils firm Peter Duffy

Contractor gears-up for AMP8 investment round
50 minutes ago

Wates calls for PFI reboot to unlock schools and hospitals

Firm sets out fresh model for private cash in public projects
13 minutes ago

Strabag targets £1bn UK turnover by 2028

Austrian civils contractor ramps up UK push with HARP and HS2 pipeline
29 minutes ago

BBV gears up for big HS2 viaduct slide over M6

First 119m viaduct section set to slide into place in June
8 hours ago

Council terminates Spencer bridge repair contract

Delays have hit restoration of Grimsby’s historic Corporation Road Bridge
18 hours ago

Training reform row splits scaffolding sector

Changes planned to the Construction Industry Scaffolders Record Scheme
1 hour ago

Liverpool unveils £850m highways framework line-up

Graham, Sisk and Wright land spots on city road improvement deal
12 hours ago

Tender price rise forecasts downgraded as market stalls

Schemes stall as clients drag feet on project starts
8 minutes ago

Westminster gears up for £500m housing repairs deal

Council eyes multiple strategic alliances for major housing overhaul
1 day ago

Henry Boot sets October start on £1bn cyber hub next to GCHQ

160,000 sq ft IDEA office building starts 10-year build plan
1 day ago

Cementation Skanska names new operations director

Emma Haddow now heads up UK-wide ground engineering services
1 day ago

Forterra fires-up kilns as house building demand returns

Materials giant boosts production of bricks and concrete floor beams
1 day ago

Plans in for £100m Church Wharf regeneration in Bolton

Developer Watson submits plan for over 400 homes and 130-bed hotel
1 day ago

McAvoy on the hunt for new subcontractors

Meet the Buyer event in Manchester next month: Register now
1 day ago

Ex-Lendlease boss seals £24bn Crown Estate mega sites JV

Crown Estate/Lendlease alliance to build out at Euston, Silvertown and Thamesmead sites
2 days ago

Brookfield gets green light for latest City office scheme

Retrofit-first approach will retain 70% of the original structure at 1 Moor Lane
2 days ago

Knauf commits £170m to build Deeside insulation plant

Work to start next year at former Shotton steelworks site
2 days ago

Construction trade bodies vote to keep training levy

CITB gets green light to collect contractor's cash for another three years
2 days ago

McLaren to build 2,400-bed worker campus at Sizewell C

Worker camp to raise the bar on site accommodation standards
2 days ago

Soaring costs and work drought sunk historic scaffolding firm

Rodells had been in business since 1898
2 days ago

Clarion set to tender £79m Kirkstall Road Phase 2

Bidding to start for Dyecoats blocks 1 and 3 after Graham bagged phase 1
2 days ago

TfL seeks firms for £700m civils and station framework

Works include £80m South Kensington and £60m Elephant & Castle station upgrades
2 days ago

Early market talks on £2.5bn Yorkshire mass transit plan

Supplier talks open for West Yorkshire’s biggest ever transport scheme
2 days ago

Robertson starts Redcar town centre revamp

Culture and Leisure Anchor Attraction will enhance Redcar’s Esplanade
2 days ago

Alun Griffiths set to rescue firm he sold for £36m

Tarmac to hand back Welsh civils contractor after five years of losses
5 days ago

Landsec to pump £2bn into new house building drive

Developer to build 6,000 homes as it sells offices to fund new schemes
5 days ago

Severfield to start steel on McAlpine car battery site

Specialist to start on £4bn site next month after steel package signed-off
5 days ago

Construction Manager of the Year crowned

Jason Hunt of Willmott Dixon wins for work on Bristol concert hall
5 days ago

Tide gets go-ahead for over 1,000-home London scheme

Volumetric expert gains planning for co-living homes scheme in Southwark
6 days ago

Vital Energi lands £250m Gatwick decarbonisation deal

Five-year programme to switch airport away from gas heating
5 days ago

Contractor services