Kier quits £170m London Ram Brewery job

Aaron Morby 8 years ago
Share

Kier has become the third contractor in a week to walk away from a major project after failing to agree a final contract sum with the client amid rampant cost inflation.

Construction of the new river wall and basements are complete with work on the first three concrete cores now underway
Construction of the new river wall and basements are complete with work on the first three concrete cores now underway

The firm has been working on the £170m first phase of The Ram Quarter, a major flagship regeneration scheme in the London Borough of Wandsworth, since securing the project last summer.

At present it is completing enhanced enabling works on the site for Chinese developer Greenland, which aims to redevelop the old Young’s brewery site and build luxury flats over three phases.

Faced with spiralling cost inflation in the capital, Kier has struggled to get its price down, quoting just below £200m for phase one.

In an attempt to drive down costs further Shanghai-based developer and builder Greenland called on Kier to abandon its supply chain in favour of sourcing as much of the project as possible from China, according to project sources.

It is understood Greenland explored using Chinese suppliers for cladding, drylining and even kitchens and bathrooms.

But now after detailed consideration Kier has decided to walk away and is expected to leave the site in April.

The firm follows Morgan Sindall and Bouygues which have also decided to walk away from jobs for major blue chip clients at Cambridge University and Great Ormond Street Hospital respectively after contract negotiations faltered on price.

At the Ram Brewery, specialist contractor J Reddington is carrying out concrete works, which are now proceeding to forming three building cores for the housing element.

A source told the Enquirer: “It’s a real shame. Kier must have had around 50 personnel on the job. They were working hard to get a keen price because of the prospect of winning future high-rise phases.

“But they have clearly decided the risks are too high and it can’t be delivered to the client QS’s target cost.”

A Kier spokesperson said: “Client and contractor partners always have their own fixed points that cannot be breached in a moving market, but Greenland has been an excellent client to work with and we will support them until an alternative contractor is in place.”

A spokesperson for Greenland confirmed that Greenland and Kier had been unable to agree terms for ongoing work and Kier would now be concluding its involvement in the project in the coming months.

“We appreciate the work that Kier has done on The Ram Quarter project and we anticipate that works will be completed as scheduled with our new construction partner,” said Greenland.

The project has been complicated by section 106 agreements, which require that the old brewery is repaired and restored before flats can be occupied on the site.

Work has not advanced on this part of the project, which could cost up to £30m to complete.

dev11

Phase 1 is due for completion in early 2017

home11

Latest news

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 hours ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
10 hours ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
11 hours ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
11 hours ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
1 day ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
11 hours ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
1 day ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
11 hours ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
1 day ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
1 day ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
1 day ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
1 day ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
1 day ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
1 day ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
4 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
4 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
4 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
4 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
4 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
4 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
4 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
5 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
5 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
5 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
5 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
5 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
5 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
6 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
6 days ago

Contractor services