Northern Line Tube Extension cost to soar by £240m

Aaron Morby 8 years ago
Share

The developers of Battersea Power Station and Transport for London are locked in talks about who will foot an extra £240m bill for design changes to the Northern Line Extension station.

Original designs for over-station developments have been significantly revised
Original designs for over-station developments have been significantly revised

One of two new tube stations will be located on the Battersea Power Station redevelopment site within phase three of the scheme.

The Malaysia developers, who have already agreed to pay £200m towards the £1bn tube extension, now have decided to significantly increase the over-station development.

This has necessitated a far stronger station box design, which could add up to £240m to the final cost, according to a report in the London Evening Standard.

Last month, the Enquirer exclusively revealed the main tunnel drive starting date within the Battersea station box had been put back by six months.

At the time TfL said the programme had drifted because of some modifications to the work schedule but said the extension would be still be completed in 2020 as originally planned – although the date is understood to have slipped within the year.

Now it has been revealed that the delays have come from a major redesign of the station box to carry one of five major new buildings designed by architect Frank Gehry.

David Hughes, director of major programme sponsorship at London Underground, said: “Changes have been made to the proposed development at Battersea and to the new Tube station beneath.

“We are now working with Battersea Power Station to agree the necessary changes to the contractual arrangements between us to reflect these revised designs.

“These design changes will lead to an increase in the overall cost of the project and we are in constructive discussions with the developer about how this cost will be attributed.

“We are also working to deliver the project even more efficiently, further bearing down on costs.  But any suggestion that we are about to go to arbitration over this is incorrect.”

The change will also see joint venture contractor Ferrovial Laing O’Rourke’s £500m contract, awarded back in 2015, revised to cover increased work.

Under the original masterplan the station was due to have a modest station entrance over-site development. But the new plan is to fully incorporate the station into Ghery’s Prospect Place building complex, delivering passengers direct into one of its most striking buildings.

captures-17013-870x420

Frank Gehry’s striking Prospect Place design for phase three of the £9bn Battersea Power Station development

These enhancements include separating the station entrance to provide a western and an eastern entrance at ground level with the main building sitting above the station box.

A Battersea Power Station spokeswoman said: “Provision for design changes was made at the outset, given the scale and complexity of this major infrastructure project. TfL and BPS are working collaboratively on those designs and any related costs.”

Battersea-station-section_web

Original design for station box, without major oversite building

Battersea Northern line station station

Revised plan with Gehry designed building sitting above the station

 

 

Latest news

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
50 mins ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
42 mins ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
16 hours ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
19 hours ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
59 mins ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
24 hours ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
24 hours ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
23 hours ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
23 hours ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
23 hours ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme
23 hours ago
Walker Modular Limited

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
23 hours ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
4 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
4 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
4 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
4 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
4 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
4 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
4 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
5 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
5 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
5 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
5 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
5 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
5 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
6 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
6 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
6 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
6 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
6 days ago

Contractor services