Giant bridge beam lift across M8: Video

Grant Prior 9 years ago
Share

A series of 200 tonne beams have been lifted into place to help form the largest single span bridge being built as part of the £500m M8 M73 M74 Motorway Improvements Project.

Transport Scotland has released time lapse footage of the work overseen by the Scottish Roads Partnership and its main contractors Ferrovial Lagan and Amey

The film shows nine pairs of 3m high steel beams, approximately 77m in length and weighing almost 2,000 tonnes, being lowered into position over the North Calder Water, near Bellshill in North Lanarkshire.

The construction of North Calder Water Bridge is part of major works to upgrade Shawhead Junction.

The new bridge will carry traffic on the new M8 over the North Calder Water to the south of the existing A8.

Before any lifting could begin, a  massive 1350 tonne crane – the largest crawler crane in the UK and one of the biggest in Europe – was delivered to site by a fleet of 33 HGVs and assembled on site over five days.

When fully assembled the crane stood 90 metres in height, towering over the Lanarkshire skyline, and required two smaller cranes – a 750 tonne and a 200 tonne crane to build it.

With a maximum lifting capacity of 1350 tonnes, the operator had to perfectly balance the crane with counterbalance weights ahead of every lift – a slow and meticulous process to ensure a precise and safe operation.

Dario Saavedra, construction manager for Ferrovial Lagan Joint Venture, said: “This is a significant milestone for the project and a successful operation which we are very proud of.

“The beam installation took nine days to complete, lifting the giant beams onto the two new bridge abutments, each of which contain over 6000 tonnes of reinforced concrete.

“The beam lift was a complex piece of engineering and an important step towards completion of this impressive project.”

Lyle Cairns, section site engineer, has overseen the progress of the new structure.

He said: “The first excavation for the bridge began in summer 2015 and it is scheduled for completion in September of this year.

“The beam lift was very exciting to be part of as this was a challenging engineering operation, however, from a personal point of view; it’s pleasing to see the entire construction from start to finish. The most challenging aspect of this structure was the sheer scale and size involved.”

Latest news

Lynch appeal sees £800,000 abnormal load fine reduced to £10k

Judge rules original fine was was 'manifestly excessive'
53 minutes ago

Government calls up firms to explore PPP healthcare projects

New public-private partnership idea to be scoped out with contractors
60 minutes ago

Balfour Beatty terminates Danny Sullivan labour deals

Around 500 workers on HS2 will be moved to alternative agencies or be taken on direct
2 days ago

Prosper picks 34 firms for £1bn retrofit bonanza

Equans, Fortem, Mears and Vinci among winners on four-year PAS 2035 framework
22 minutes ago

Trio face prosecution after Hinkley site death

Main contractors and client to face charges over death of site supervisor
2 days ago

£60m raised to advance world-first cement CCS project

Five lime and cement plants to capture emissions for storage under Irish Sea
34 minutes ago

Buyers see recovery in house building sector

But civil and commercial work still in the doldrums
3 days ago

Apprentice saws-off thumb on hotel refurb site

Court hears how digit was reattached and teenager continued training with another firm
3 days ago

Laing O’Rourke tops June contracts league

£919m animal super lab dominates new orders
3 days ago

TSL turnover smashes £500m as profit almost trebles

Data centre and logistics contractor rises high on surging demand
3 days ago

Gleeson Homes chief exec leaves business after restructure

Management revamp after "challenging" year
3 days ago

Green light for 1,600-home Oldham town centre overhaul

Plans for over 1,600 homes across six regeneration sites approved
3 days ago

DSM wins Norwich city centre clearance job

Anglia Square shopping centre clearance for £300m scheme
3 days ago

13-year-old becomes UK’s youngest qualified digger driver

Grandson of Gallagher Group chairman sets industry record
3 days ago

Cubby reborn in £12m Svella-backed takeover

£50m revenue target set as 14 firms combine under new Cubby Group banner
4 days ago

North East NHS trusts plot £3bn health estate overhaul

Market engagement begins for major construction push across four trusts
4 days ago

HG goes green on cranes in £1.2m switch to battery power

Diesel-free crane drive cuts fuel bills by 94%
4 days ago

Developer fined £165,000 for fire safety failings

Firm ignored fire safety orders on apartment job in Preston
4 days ago

Bidding to start for £1.8bn North West framework

Contractors invited to bid for latest Procure Partnerships deal
4 days ago

Hill hits record £90m profit as homes pipeline swells

Build-to-rent push and £4.8bn contracting book to fuel next growth phase
5 days ago

Rayner unveils £39bn plan to build 300,000 social homes

Council building revival and rent reform feature in social and affordable homes plan
5 days ago

Keltbray bounces back with £3.2m profit

Tighter controls and smarter project selection fuel strong turnaround
5 days ago

VINCI JV wins 500-home twin town centre revamps

Chester Northgate phase 2 and Northwich Weaver Square schemes move to delivery stage
5 days ago

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
6 days ago

How to see your stories on the Enquirer

Join our Suppliers and Buyers directory to get your news published
5 days ago

Henley lands Midland Mill revamp on Leeds tower scheme

Restoration of 18th-century mill kicks off on South Bank regeneration project
5 days ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
5 days ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
6 days ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
6 days ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
6 days ago