HS2 phase one opening could be delayed a year

Aaron Morby 8 years ago
Share

Government spending watchdog, the NAO, has warned that the HS2 high-speed rail project has an “unrealistic timetable” and faces major cost pressures.

A report out today says the 2026 target for the opening of phase one is at risk despite good progress with some major procurements.

The NAO revealed that options for extending the opening date for phase 1 are now being considered and steps are being taken to bring cost estimates within available funding.

Phase one of HS2 is expected to cost £27.4bn, exceeding available funding by £204m, according to the report.

The estimated cost of phase two was also over budget although potential savings had been identified.

Now Department for Transport official have asked HS2 to revisit the programme schedule in order to increase confidence for delivery from 60% to 80%, without increasing costs.

It has also asked HS2 to assess the impact of extending the timetable for opening Phase 1 by up to 12 months.

Amyas Morse, head of the NAO, said:“HS2 is a large, complex and ambitious programme, which is facing cost and time pressures.

“The unrealistic timetable set for HS2 by the department means they are not as ready to deliver as they hoped to be at this point.

“The department now needs to get the project working to a timescale that is achievable.”

MPs are due to vote on phase one of HS2 later this year. If they approve the bill, that’s effectively the green light to start building the line from London to Birmingham.

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
3 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
3 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
3 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
3 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
4 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
4 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
4 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
4 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
5 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
5 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
5 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
5 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
5 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
6 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
6 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
6 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
6 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
6 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
7 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
7 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
7 days ago

Contractor services