Phase One of £56bn HS2 gains Royal Assent

Aaron Morby 7 years ago
Share

Britain’s biggest infrastructure project in decades cleared the final hurdle to construction yesterday as the HS2 Hybrid Bill received Royal Assent.

It paves the way for the nine-year construction programme to start between central London and Birmingham’s Eastside district.

Enabling works packages have already awarded across the three key sections of 140-mile route .

Despite years off waiting, work is unlikely to get off to a flying start with contractors saying they will only be steadily gearing up now, with consultations still ongoing.

Enabling work on phase one is set to begin proper in the spring.

The Act of Parliament today and means the West Midlands can press ahead with plans to use the rail link as a catalyst to drive economic growth around the planned Birmingham Curzon terminal unlocking £1bn of regeneration opportunities.

Curzon Street HS2

It will also light fire under plans to redevelop Euston station and its surrounding area.

HS2 will create around 25,000 jobs during construction as well as 2,000 apprenticeships. It will also support growth in the wider economy, worth an additional 100,000 jobs.

The £900m package of enabling works has been shared between seven firms in three consortia.

A Costain Skanska joint venture has the southern area, a three way joint venture between Morgan Sindall, BAM Nuttall and Ferrovial Agroman (UK) has secured the central section, which Morgan Sindall expects to be worth £100m to it.

Laing O’Rourke Construction in joint venture with J Murphy & Sons has the northern stretch of the route to Birmingham.

HS2 procurement chiefs are busily working to try to award £7bn-£12bn worth of civils packages this summer, although there are fears among contractors that this date will slip.

Eight joint ventures and Bechtel are battling it out for the seven packages along the route from London to Birmingham.

Work on these contracts is expected to start in 2018.

Phase one of the £56bn scheme is scheduled to open in December 2026, with a second Y-shaped phase launching in two stages.

Phase 2a from the West Midlands to Crewe will open in 2027 and phase 2b, from Crewe to Manchester and from the West Midlands to Leeds, South Yorkshire and the East Midlands, will begin operation in 2033.

David Higgins, Chairman of HS2, said: “Achieving Royal Assent for phase one of HS2 between Birmingham and London with such significant parliamentary support, is a monumental step in transforming rail travel in Britain.

“We have a long journey ahead of us to build the railway and secure permission for Phase Two to make sure that the full benefits of HS2 are realised.”

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
4 hours ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
10 hours ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
9 hours ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
10 hours ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
10 hours ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
1 day ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
1 day ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
1 day ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
1 day ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
2 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
1 day ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
2 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
1 day ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
1 day ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
2 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
2 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
3 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
2 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
2 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
2 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
3 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
3 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
3 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
4 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
3 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
4 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
3 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
4 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
4 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
4 days ago

Contractor services