Pharmaceutical giant AstraZeneca has seen the cost of its flagship Cambridge headquarters and R & D building project soar from £330m to over £500m.

Focus of construction now turns to installing the roof, cladding and fit out
Focus of construction now turns to installing the roof, cladding and fit out

Skanska is delivering the major building project, which was due to be complete for occupation at the end of last year.

Staff are set to start moving into the new building in late 2018 with the site becoming fully operational by 2019.

Chief Executive Pascal Soriot revealed the cost increase as he visited the site to mark the topping out of the concrete frame and saw-edged roofing sections being fitted.

Astrazeneca

Pharmaceutical giant marked a major milestone with the ‘topping out’ of its new headquarters in Cambridge this week.

The delay and forecast project budget increases stem from extra investment in technology and equipment in the centre, rather than unrealistic estimates or poor planning.

“We are bringing more capability to the new building than originally planned. This includes increased investment in new technologies and robotics equipment,” a spokesperson for the company said.

The new hub building at the heart of the Cambridge Biomedical Campus will become the company’s largest centre for oncology research, as well as housing scientists focused on cardiovascular and metabolic diseases, respiratory, inflammation and autoimmune diseases and conditions of the central nervous system.

The site will also be home to a joint research centre, which will see Medical Research Council-supported researchers working side-by-side with AstraZeneca’s high throughput screening group.

AstraZeneca

 

Latest news

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
39 mins ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
2 hours ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
7 hours ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
7 hours ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
7 hours ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
6 hours ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
6 hours ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
7 hours ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
6 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Contractor services