Mace Nova site finishes late and busts budget

Grant Prior 8 years ago
Share

Land Securities has confirmed its Nova project in Victoria has busted the budget and overrun by nine months.

The first phase at Nova was completed last month
The first phase at Nova was completed last month

The first phase of the scheme, where Mace was main contractor, was completed last month.

The developer said: “The complexities of construction – together with competition for labour in a busy sector – delayed final completion and impacted costs.”

The scheme was also hit by the failure of main concrete specialist PC Harrington.

Work was due to finish last summer and cost £248m.

In its latest results today Land Securities said is has “paused for breath” in its major development cycle as it has largely completed its latest speculative development programme.

The developer revealed a strong set of annual results today and confirmed it has its eye on the next round of opportunities in the property market.

Chief executive Robert Noel said: “Put simply, our markets remain in good health but they’ve paused for breath.”

“The foundations of the business are rock solid, underpinned by our resilient portfolio and low leverage.

“We’ve achieved our plan to have minimal development exposure and longer lease terms in London offices, a transformed retail portfolio and low gearing at this point.

In the short term, with significantly reduced risk and a portfolio of first class assets, we go forward in excellent shape, ready to make acquisitions when the time is right.

“Longer term, we remain confident in our market and our ability to deliver sustainable growth.”

Plans are being drawn-up for a second Nova East phase and Land Securities also has planning at 21 Moorfields in the City where demolition is complete with piling work set to start shortly ahead of construction of a raft that will sit above the eastern entrance to Liverpool Street Crossrail station.

It will be the platform for 522,000 sq ft of space across two buildings.

The firm said: “Completing the raft in July 2018 will mean we can complete construction of the buildings in 24 months, providing an excellent prospect for the pre-letting market.”

Land Securities also has planning consent for a 142,000 sq ft mixed use scheme in Westminster at 1 Sherwood Street, W1 and a 134,000 sq ft development in Southwark, at Sumner Street, SE1.

Latest news

Ardmore Construction Ltd falls into administration

Move isolates fire safety claims, leaving main Ardmore group free to grow profitability
2 days ago

Aston Villa gets go-ahead for £100m North Stand expansion

Project to modernise 1897-built ground ahead of EURO 2028
2 days ago

Quartet wins £1.75bn Midlands Rail Hub upgrade deal

VolkerRail, Laing O’Rourke, AtkinsRéalis and Siemens team up on Birmingham upgrade
3 days ago

McLaren confirmed for £250m Cardiff arena

Robertson Property secures planning green light for 16,500-capacity venue
3 days ago

John F Hunt starts work on £150m West End office revamp

Six month strip out deal at 125 Shaftesbury Avenue
2 days ago

Former Skanska vice president to join Galliford Try

Thomas Faulkner to head up specialist services division
2 days ago

Bowmer + Kirkland snaps up office fit-out firm Denton

Acquisition gives £40m turnover interiors specialist firepower to chase bigger jobs
3 days ago

Contractors sought for £667m Welsh Water mega project

Utility tests appetite for design, build and finance for twin water treatment jobs
3 days ago

Worker killed on Mace London site

Fatal accident on major site in Brent
4 days ago

Willmott Dixon veteran takes construction COO role

Former trainee Stewart Brundell promoted after nearly 40 years at the firm
4 days ago

BSR delays dent margins at OHOB despite record sales

Turnover up 18% to £369m as pre-tax profit nudges £22m
3 days ago

Plans go in for 30-storey Preston tower

£40m scheme will be tallest residential building in Lancashire
3 days ago

Former Laing O’Rourke leader to join Skanska

James Davies to oversee key defence and health projects
3 days ago

Green light for £10bn data hub prep works in Northumberland

Enabling works to roll out over 16 months on former Blyth Power Station site
5 days ago

VolkerWessels UK profits jump as rail and marine work surges

Infrastructure contractor posts £48m pre-tax profit and stronger order book
5 days ago

Groundworks boss wins payout over gagging order

Subcontractor raised fears over asbestos on housing sites
4 days ago

B+K to start £50m rebuild of Northumberland school

Cramlington Learning Village redevelopment contract signed off
5 days ago

New Homes Accelerator targets six new major sites

Construction to be sped-up on another 12,000 homes
4 days ago

Network Rail spend down as CP7 shift bites contractors

Firms warn of inflation squeeze and reprofiled workbanks
5 days ago

Wall of six towers planned for North London strip site

Hendon Goods Yard site plan for line of resi blocks rising to 29 storeys
5 days ago

SCF opens door to single stage tenders for first time

Gen-6 Southern Construction Framework to widen scope for smaller jobs
5 days ago

M&J Evans lifts profits as eastward regional push pays off

Groundworks specialist sharpens tender strike rate and grows pipeline to £504m
5 days ago

CHIC confirms 33 winners on £1bn housing framework

Equans, Guildmore, Seddon and Wates land spots on new four-year deal
5 days ago

Trade body joins attack on CITB over funding changes

Fit out specialists describe move as a "kick in the teeth"
5 days ago

Carey demolition cartel claim settled with developer

Legal action withdrawn after both sides agree settlement
1 week ago

Strabag seals financial close for £3bn HARP project

Work to start next year on North West's Haweswater aqueduct upgrade
1 week ago

Civils winners revealed for £12bn National Grid high voltage work

Contractor wins complete £59bn investment programme
1 week ago

Watch giant HS2 bridge move complete ahead of schedule

Video highlights engineering feat in Birmingham
1 week ago

Lee Marley posts record revenue despite project delays

Brickwork contractor weathers hiatus in high-rise starts to deliver fifth year of growth
1 week ago

Latest contract winners in military living revamp

First phase sites allocated under new approach to Single Living Accommodation
1 week ago