Two-year rebuild complete of Battersea chimneys

Grant Prior 7 years ago
Share

Battersea Power Station’s four iconic chimneys have now been fully rebuilt using the same construction technique as when they were first erected.

Since the first pour in May 2015, nearly 25,000 wheelbarrow loads of concrete have been hand-poured into the chimneys that each stand 51 metres tall.

Rather than use a hose to pour the concrete, it was decided to replicate the original construction methods and 680 tonnes of concrete was lifted in a hoist to the top of the chimney, transferred into wheelbarrows and then hand poured into the structures.

The rings that can be seen around the new chimneys, and that could also be seen around the old ones, are formed by using a ‘Jump Form’ shuttering method.

Using steel and timber, the metal rings are filled with concrete then moved up and filled again. Overall, the hoist has travelled the equivalent of 21 miles, lifting the concrete to the eight workers waiting on boards high above the ground.

The original chimneys, two were built in the 1930s and the second pair in the 1950s, had to be demolished as they were deemed unsafe because they were badly crumbling after so many years.

The rebuilding of the chimneys was overseen by main contractor Skanska and led by specialist engineers Beroa Bierrum working with Delta, the specialist dismantling contractor.

Rob Tincknell, CEO of Battersea Power Station Development Company, said: “Battersea Power Station’s chimneys have been the backdrop for films, music videos and album covers and really are world famous.

“On behalf of our shareholders, I would like to say it has been an honour to restore this iconic symbol to the London skyline so that it can be enjoyed by generations to come.”

Cllr Ravi Govindia, Leader of Wandsworth Council, said: “These giant chimneys are recognised the world over and as the local planning authority we have a profound duty of care to make sure the rebuilding process is a success.

“The site’s owners have understood their significance from day one and have gone to great lengths to restore them to their former glory. And delivered on their promises.”

Emily Gee, London Planning Director at Historic England, said: “Historic England welcomes this final stage of the rebuilding of the chimneys, ensuring that the Power Station will retain its landmark status along this evolving part of London’s skyline.”

Chimney rebuild image 1

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
1 day ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
2 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
2 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
2 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
2 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
2 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
2 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
2 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
3 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
3 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
3 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
3 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
3 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
3 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
4 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
4 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
4 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
4 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
4 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
4 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
5 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
5 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
5 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
5 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
5 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
5 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
5 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
6 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
6 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
6 days ago

Contractor services